About this file

This is a Schedule of Items pricing template for the Baptist Camp Bridge Maintenance project located on the Tonto National Forest in the Payson Ranger District. The document outlines eight line items required for bridge repair and maintenance work, including mobilization (LS), repair of wearing surface with timber installation (580 SF), filler and sealant installation (580 SF), drainage restoration on the A1 US side (LS), replacement of 10 timber posts (EA), asphalt repair at bridge approaches (64 SF), installation of four object markers per MUTCD standards (EA), and temporary traffic control (LS). The template is fillable and requires unit pricing and extended amounts to be entered by the contractor for each line item to establish the total contract value.

This pricing template is part of solicitation 127EAX26Q0009, issued as a Request for Quotation (RFQ) by the Department of Agriculture Forest Service for a small business set-aside, specifically reserved for SBA Certified Women-Owned Small Businesses (WOSB). The applicable NAICS code is 237310 with a small business size standard of $45 million. All responsible sources may submit quotations for consideration.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule of Items Fillable

PROJECTBaptist Camp Bridge Maintenance
FORESTTonto National Forest
DISTRICTPayson Ranger District
SOL #127EAX26Q0009
ITEM NO.ITEM DESCRIPTIONUnitQtyUnit PriceAmount
15101MobilizationLS1
--Repair Wearing Surface - Install timber wearing surface along the entire travelwaySF580
--Filler and sealant installation - Apply and install COR approved filler and sealant to the bridge deck along the entire travelwaySF580
60701Drainage Restoration - Improve drainage on A1 US side, where water ponds.LS1
55601Replace Timber PostsEA10
40301Repair Asphalt - at approaches to remove existing bumpsSF64
71805Replace Object Markers - Install object markers (OM-3L and OM-3R) in accordance with the latest version of the MUTCDEA4
63501Temporary Traffic ControlLS1
TOTAL$0