Attach 01 Statement of Work.pdf
PDF 400 KB Posted
- Attached to
- Baptist Camp Bridge Maintenance Federal contract opportunity
- Solicitation number
- 127EAX26Q0009
- Issued by
- Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the Baptist Camp Bridge Maintenance project issued by the U.S. Department of Agriculture (USDA), Payson Ranger District, Tonto National Forest, dated 16 March 2026. The project involves comprehensive maintenance and repair of Baptist Camp Bridge, a timber structure spanning Tonto Creek in Arizona that was constructed in 1973 with an overall length of 41 feet and roadway width of 14 feet.
The primary scope of work includes: (1) mobilization with bonding costs; (2) temporary traffic control design, permitting, installation and removal; (3) repair of the wearing surface by installing treated timber planks (10-12 inches wide, 2.5-3 inches thick) across the entire travel way using copper naphthenate wood preservative treated to AWPA use category UC4A; (4) cleaning and treating the existing deck with approved wood preservatives; (5) filler and sealant installation; (6) drainage restoration; (7) replacement of missing and damaged timber posts and guardrail blocks; (8) asphalt repair at bridge approaches using 4 inches of base aggregate and 3 inches of asphalt pavement; and (9) installation of new object markers per MUTCD specifications. All work must comply with FP-14 federal highway construction standards and Forest Service supplemental specifications. The contractor must submit five initial deliverables within five to ten business days of contract award: Temporary Traffic Control Plan, Project Schedule, Hazardous Spill Prevention Plan, Erosion and Sediment Control Plan, and Manufacturer Specifications for all materials. Road closures must be coordinated with the Contracting Officer's Representative at least three weeks in advance. The contractor is responsible for providing all labor, materials, equipment, and tools, and must ensure complete site cleanup with no debris left behind or discharged into waterways.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend 0001 03 127EAX26Q0009 Baptist Camp Bridge Q and As.pdf | ||
| Amend 0001 01 127EAX26Q0009 RFQ continuation.pdf | ||
| Amend 0001 02 127EAX26Q0009 Site Visit Sign In Sheet 032326.pdf | ||
| 00 127EAX26Q0009 RFQ Baptist Camp Bridge.pdf | ||
| Amend 0001 00 127EAX26Q0009 SF30.pdf | ||
| Attach 07 Picture Previous Project.pdf | ||
| Attach 04 Fire Plan AZ-TNF 2024.pdf | ||
| 00 127EAX26Q0009 RFQ Baptist Camp Bridge.pdf | ||
| Attach 06 FP-14 Specifications.pdf | ||
| Attach 02 Maps.pdf | ||
| Attach 03 FS Sup Specs to the FP-14.pdf | ||
| Attach 05 Wage Decision AZ20250051 01 02 2026.pdf | ||
| Attach 08 Schedule of Items - Fillable.xlsx | XLSX spreadsheet | |
| Attach 01 Statement of Work.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Baptist Camp Bridge Maintenance
Statement of Work
US Department of Agriculture (USDA)
Payson Ranger District
Tonto National Forest
16 March 2026
Contents
Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
Project Baptist Camp Bridge Maintenance
General Information
1.0 Scope of Work
This project requires the Contractor to perform work on Baptist Camp Bridge in the Tonto National Forest in the Payson district.
Baptist Camp Bridge is located on Forest Service Road 3675 at N 34° 21.236’ W 111° 05.880’, about 200 feet east of Tonto Creek Road (FR 289). Constructed in 1973 from timber sawn multi-girders on timber wall abutments, it is a one-lane bridge spanning Tonto Creek providing access to Tonto Rim Christian Camp. Overall length of the bridge is 41.0 feet with a maximum span of 40.0 feet, with a roadway width of 14.0 feet. The wooden deck is constructed from treated timber and formerly had steel running planks on the surface, but these planks were removed in August 2024 due to metal degradation and loose bolts.
Summary of Project Work Items Include the following:
Mobilization, Including Bonding Costs shall include payment for personnel, equipment, material, and incidentals to mobilize to and from the project site for the completion of this project.
Temporary Traffic Control includes all work necessary to design, permit, install and remove temporary traffic control for the site. Temporary traffic control plans shall be submitted to the COR for review and approval for the project site. Temporary Traffic Control is measured as a lump sum item.
Repair Wearing Surface includes all work necessary to install a timber wearing surface across the entire travel way and treat the new surface with wood preservative. This timber wearing surface consists of timber planks treated with copper naphthenate wood preservative.
Materials
New Wearing Surface Material:
Species such as Douglas Fir-Larch, Hemlock, and Spruce are acceptable. Edge-grain planks are preferred (growth rings form an angle of 45° to 90° with wide surface of the plank); when edge-grain material is not available, notify the Contract Officer (CO).
New Wearing Surface Treatment:
Waterborne preservatives should be used to treat the new lumber planks to AWPA use category UC4A. The following are acceptable waterborne preservatives: Alkaline Copper Quat (formulation A, B, C, or D), Copper Azole (formulation B or C), or Micronized copper azole (formulation C).
Process
Clean Bridge Deck:
Remove all material/debris from the deck surface. Removed material and debris must not be allowed to enter the stream.
Existing Deck Treatment:
Fill and seal existing deck to create even surface upon which to install timber wearing surface. See “Filler and Sealant Installation” below.
New Wearing Surface Configuration:
The new lumber wearing surface must consist of a series of rough-sawn lumber planks placed edge to edge across the deck width. The new wearing surface must cover the full travel width. Planks must be 10- to 12-in wide, 2.5- to 3-in thick, a minimum of 8-ft long, and oriented in the direction of traffic. The most economical arrangement is an alternating repetition of longitudinal planks with odd lengths at the bridge ends. End joints in adjacent planks should be staggered by 3-ft minimum (see Figure 1). When seasoned planks are used, a gap of ¼-in must be left between edge joints to allow for expansion. Tight edge joints are used for unseasoned (green) planks. At bridge approaches, bevel plank ends as depicted on Figure 2, unless the COR decides otherwise.
Figure 1: Plank layout for lumber wearing surface
Figure 2: Beveled end-plank configuration
Wearing Surface Deck Attachment:
The connection must keep the planks firmly attached. Fasteners should be recessed below the road-way surface. Seal the recessed holes with mastic or caulk. To minimize decay and prevent splitting the existing deck, all fasteners must be placed in lead holes that are pre-bored and field treated with liquid wood preservative. Connection to the deck must employ 3/8-in diameter, 5.5-in long, zinc-plated or hot dipped galvanized lag screws, inserted vertically with a round steel cut washer under the head. Install lag screws using two pre-bored lead holes (Figure 3), one diameter hole for the shank (1/16-in larger than shank diameter) and bored to the depth of penetration of the shank. The lead hole dia-meter for the threaded portion, which is bored at least the length of the threads, should have diameter between 65% to 85% of the shank diameter. Plank attachment pattern is illustrated in Figure
4. When installing lag screws, the threaded portion must be inserted in the lead hole by turning with a wrench.
Figure 3: Lag screw attachment details
Figure 4: Wearing surface plank attachment pattern, using lag screws
Filler and Sealant Installation includes all work necessary to apply wood preservative approved by the COR to the deck surface and applying a wood filler to the deck to remove ruts and ensure a smooth flat surface prior to installing the timber wearing surface. Conventional liquid wood preservatives should be applied by brushing, squirting, or spray-flooding the wood surface. Creosote heated to 150o to 200o F, pentachlorophenol (Penta), and copper naphthenate (Cu-Nap) may be used. Alternate oil-based products may be considered. The Contractor should submit the proposed preservative to the CO for approval. The wood surface should be thoroughly saturated with preservative so that all cracks and crevices are treated; however, care must be exercised to prevent excessive amounts from spilling or running off the surface and contaminating water or soil. This item also includes removing nails from the deck and adding new nails or implementing other COR-approved methods to stabilize the deck prior to installing the timber wearing surface.
Drainage Restoration includes all work and materials necessary to improve drainage on the upstream side, where water ponds.
Replace Timber Posts includes all work and materials necessary to replace missing and damaged timber posts and blocks attached to the bridge guardrail.
Repair Asphalt includes all work and materials necessary to repair bridge approaches to remove existing bumps and create a smooth surface. This will require removing the full width of the asphalt sections adjacent to the bridge approaches and replacing with new base aggregate and asphalt pavement. The new asphalt pavement shall provide a smooth transition to the bridge’s new timber wearing surface.
Resurface both approaches with a compacted layer of base aggregate 4” thick and asphalt concrete pavement 3” thick.
Base aggregate shall be provided and installed in accordance with Section 301 of FP-14. Asphalt concrete pavement shall be provided and installed in accordance with Section 403 of FP-14. Submit aggregate gradation and an asphalt job mix design to the CO for approval.
Replace Object Markers includes all work and materials necessary to install new object markers and posts to Manual on Uniform Traffic Control Devices (MUTCD) specifications and to replace any existing markers with new markers. Object marker locations need to be adjusted to end terminal locations. Removed material shall be disposed of off National Forest lands. New signs shall meet current MUTCD reflectivity standards.
The Contractor shall provide all labor, materials, equipment, and tools, including incidentals, necessary for the bridge maintenance work items and traffic control required within this project.
2.0 Background
This bridge maintenance project is located within the Payson Ranger District of Tonto National Forest, located in Gila County, Arizona. Directions to the project sites from the Payson area are as follows:
Baptist Camp Bridge
From the entrance to Payson Ranger Station on Highway 260, drive east on 260 for about 15.3 miles to Tonto Creek Road (FR 289). Turn left and travel north on FR 289 for 1.8 miles to Tonto Rim Ranch Road (FR 3675). Turn right on FR 3675 for about 200 feet to Baptist Camp Bridge at N 34° 21.236’ W 111° 05.880’.
Contractor Requirements
3.0 Technical Requirements / Tasks
All construction and maintenance work shall meet the following standards:
1) US Department of Transportation, Federal Highway Administration “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14,” available online at https://flh.fhwa.dot.gov/resources/specs/
2) Forest Service Supplemental Specifications to the FP-14 (attached)
The contractor shall give the Forest Service notice of project/construction schedule so that FS staff may perform regular inspections of the project and may also be present on site to inspect the finished product before the contractor mobilizes off-site.
The Contractor shall become familiar with and follow the Tonto Fire Plan to prevent any wildfires starting as a result of the work in this contract. Any questions regarding the Tonto Fire Plan shall be directed to the COR.
Contractor to provide their own water for project construction, if needed. Contractor may not pump water from Tonto Creek or other nearby waterways.
https://flh.fhwa.dot.gov/resources/specs/
Upon completion of construction, the Contractor must ensure the site is thoroughly cleaned, with no materials—such as screws, nails, or other construction or hardware debris—left behind or discarded into the waterway. Any leftover debris or materials, such as asphalt shall be disposed of off Forest Service land.
Measurement and payment performed for all work under this contract shall be in accordance with the Schedule of Items. All other work and materials will be considered as incidental to the payment of items shown.
4.0 Government Furnished
The intent of the contract is to provide for the completion of the project described in the contract.
Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract.
5.0 Deliverables / Schedule
Closures of any forest roads or recreation sites must be coordinated with the COR at least three (3) weeks in advance so proper public notices can be made by the Forest Service.
Timely submission of deliverables is essential to successfully completing the project. Schedules for initial deliverables are specified in the table below. All deliverables shall be prepared and submitted according to format, content, and schedule described in the SOW.
Initial Deliverables
Item No. Deliverable Objective Due
Temporary Traffic Control Plan
Provide for continuity of motor vehicle, bicycles, pedestrian, and equestrian traffic when normal function of roadways is temporarily suspended.
No later than five (5) business days after contract award
2 Project Schedule Facilitates timely inspections of project work by Forest Service for each road or site.
No later than five (5) business days after contract award
3 Hazardous Spill Prevention Plan
Provides planning for containment procedures, such as ground tarps and absorbent material for all diesel fuel, gasoline, hydraulic fluid, motor oil, and other hazardous materials
No later than five (5) business days after contract award
Erosion and Sediment Control Plan
Mitigates environmental damage to nearby waterways No later than five (5) business days after contract award
5 Manufacturer Specifications
• Wood Preservative Manufacturer Specifications
• Wood Filler Manufacturer Specifications
• Timber Post and Block Specifications
• Timber Deck Specifications
• Asphalt Manufacturer Specifications
No later than ten
(10) business days after contract award
• Object Marker Signs, Posts, and Fasteners Specifications
Final deliverables include construction and maintenance that conform to all requirements outlined in the Statement of Work and specifications for this project.
6.0 Travel
N/A
7.0 Contractor’s Key Personnel
Key positions include personnel who have experience which correlates to the Statement of Work requirements for this project.
8.0 Security Requirements
N/A
9.0 Data Rights
N/A
10.0 Section 508 – Electronic and Information Technology Standards N/A
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |