ATT1 WI YR30-L245 - FWD WEATHER DECK ACCESS.pdf
PDF 90 KB Posted
- Solicitation number
- N62664926RA042
About this file
This is a Statement of Work (SOW) for Ship YRB-30, Item YR30-L245, detailing the replacement of a life rail and stanchion on the main deck of a naval vessel. The work is located on the main deck weather deck, starboard side, with the exact stanchion location to be identified by the Government during a pre-performance ship check. The planner is A. Petty, and the COAR is 18KTA.
The Contractor must submit a Process Control Procedure (PCP) for Government approval prior to commencing work, which shall include detailed steps for hot work, structural modifications, fastener installation, and restoration of watertight integrity. The Contractor is required to remove the existing fixed life stanchion and all associated hardware while preserving surrounding structure and coatings, then install a new removable life rail stanchion assembly with a deck-mounted socket or base. The stanchion installation must comply with applicable safety standards and be guided by referenced technical drawings (ELM-081775 and ELM-230018). All materials and components must meet applicable MIL-SPEC or ASTM standards suitable for marine and weather deck service. Work completion includes cleaning and touch-up painting of disturbed surfaces in accordance with Standard Item 009-32, with the coating system matching adjacent surfaces. The Government will furnish removable life rail stanchion chains with quantity and specifications identified in the referenced drawings; the Contractor must receive, inspect, and verify the condition of all Government-furnished material prior to installation and report any discrepancies immediately. All work shall comply with 29 CFR Part 1915 occupational safety standards and be accomplished in accordance with Standard Item 009-11, with all penetrations and routing coordinated with the Government prior to execution.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHIP YRB-30 ITEM NO. YR30-L245
COAR 18KTA
PLANNER A. PETTY
1 : SCOPE
1.1 Title: REPLACEMENT OF LIFERAIL & STANCHION ON MAIN DECK
1.2 Location of Work
1.2.1 MAIN DECK; WEATHER DECK, STARBOARD
1.2.2 The Government will identify the exact stanchion to be removed and the installation location for the new removable life rail stanchion during the pre-performance ship check. Reference 2.4, 2.5 and 2.6 shall be used by the Contractor as technical guidance for configuration and installation intent.
2. .REFERENCES
2.1 FY26 Standard Items
2.2 29 CFR PART 1915, Occupational Safety and Health Standards
2.3 YRB-30 GEN DRAWING (GFI)
2.4 ELM-081775 REPLACEMENT OF LIFERAIL & STANCHION ON MAIN DECK_A (GFI)
2.5 ELM-230018 FAB-INSTL OF LIFERAIL STAN ASSY ON MN DK (WEATHER STBD) (GFI)
2.6 PHOTO REFERENCE OF FWD WEATHERDECK - Weather Deck Stanchion Location, STBD Side (GFI)
3. REQUIREMENTS
3.1 Submit a Process Control Procedure (PCP) in accordance with 2.1, Standard Item 009-09, for the removal of the existing stanchion and installation of the new removable life rail stanchion. The PCP shall include detailed steps for hot work, structural modifications, fastener installation, and restoration of watertight integrity. Work shall not commence until the PCP is reviewed and approved by the Government.
3.2 Remove the existing fixed life stanchion from the weather deck at the location identified in 1.3. Removal shall include all associated hardware, base plates, and securing components. Preserve surrounding structure and coatings to the maximum extent practicable.
3.3 Install a new removable life rail stanchion assembly in the location identified in
1.3. Installation shall be guided by the configuration and intent described in 2.5 and 2.6, and shall include:
3.3.1 Fabrication or installation of a deck-mounted socket or base to receive the removable stanchion.
3.3.2 Installation of the removable stanchion and associated hardware, ensuring secure fit and ease of removal.
3.3.3 Alignment and height of the stanchion shall comply with applicable safety standards for personnel protection and gangway operations.
3.4 Ensure all materials and components meet applicable MIL-SPEC or ASTM standards and are suitable for marine and weather deck service.
3.5 Accomplish cleaning and touch-up painting of all disturbed or newly installed surfaces in accordance with 2.1, Standard Item 009-32. Coating system shall match adjacent surfaces and comply with the applicable paint schedule.
4. NOTES.
4.1 All work shall be accomplished in accordance with 2.1, 009-11.
4.2 Coordinate all penetrations and routing with the Government prior to execution.
4.3 All measurements and routing shall be verified during the pre-performance ship check.
5. GOVERNMENT FURNISHED MATERIAL
5.1 The Government will furnish the following material for use in this work item:
5.1.1. Removable life rail stanchion chains, quantity and specifications as identified in 2.4 & 2.5.
5.1.2. The Contractor shall receive, inspect, and verify the condition and quantity of all GFM prior to installation.
Any discrepancies shall be reported to the Government immediately.
5.1.3. The Contractor shall install the GFM chains in accordance with the configuration and intent described in 2.4,
2.5 and 2.6, and as directed by the Government during the pre-performance ship check.
5.2 PUSH MATERIAL
1. None
5.3 KITTED MATERIAL
1. None
| 3. REQUIREMENTS |
| 4. NOTES. |
| 5. GOVERNMENT FURNISHED MATERIAL |
File details come from the government source that posted it. Updated .