Att.1 - Specifications.pdf
PDF 1 MB Posted
- Attached to
- Forest Lodge - Main Lodge & Machine Shed, Bayfield County, WI Chequamegon-Nicolet National Forest
- Solicitation number
- 12569R20Q0014
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| Amendment 4 Revisions 05.15.2020.pdf | ||
| Amendment 4 - Solicitation12569R20Q0014.docx | DOCX document | |
| Amendment 4 SF30.pdf | ||
| Amendment 3-SF30.pdf | ||
| Amendment 2-SF30.pdf | ||
| Solicitation12569R20Q0014-Amendment2.docx | DOCX document | |
| Solicitation12569R20Q0014-Amendment1.docx | DOCX document | |
| Attachment 4 - Section 08 3613 Sectional Doors.pdf | ||
| Amendment 1-SF30.pdf | ||
| Att.2 - Plans.pdf | ||
| Att.3 - WageDetermination.pdf | ||
| Solicitation12569R20Q0014.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
FOREST LODGE - MAIN LODGE AND
MACHINE SHED
100% BID SET
Cable, Wisconsin
Modified by Forest Service: February 11, 2020 a r c hi t ec t ur e • interior designꞏ pl ann i ng
FOREST LODGE THREE BUILDING HISTORIC REHABILITATION
Project No. 19042
TITLE PAGE
00 0001-1
PROJECT MANUAL TITLE PAGE
PROJECT: FOREST LODGE THREE BUILDING HISTORIC REHABILITATION
22230 GARMISCH ROAD
CABLE, WISCONSIN 54821
ISSUED BY: USDA FOREST SERVICE
500 HANSON LAKE ROAD
RHINELANDER, WISCONSIN 54501
ADMINISTERED BY: USDA FOREST SERVICE
LAKE STATES ACQUISITION TEAM
500 HANSON LAKE ROAD
RHINELANDER, WISCONSIN 54501
ARCHITECT: DIMENSION IV MADISON DESIGN GROUP
6515 Grand Teton Plaza, Suite 120 Madison, Wisconsin 53719 Project Manager: Jim Gersich 608.829.4453 Project Architect: Ron Siggelkow 608.829.4455
STRUCTURAL ENGINEER: STRATEGIC STRUCTURAL DESIGN, LLC
725 Heartland Trail, Suite 203 Madison, Wisconsin 53717 Contact: Michael Leiferman 608.658.0436
MEP ENGINEERING: APEX Engineering 110A East Grand Avenue Eau Claire, Wisconsin 54701 Contact: Dan Peterson 715.841.1859
DIMENSION IV MADISON PROJECT NO.: 19042
DATE OF PROJECT MANUAL BID SET: January 17, 2020 (Modified by Forest Service February 11, 2020)
END OF DOCUMENT 00 0001
TITLE PAGE
00 0001-1
THIS PAGE INTENTIONALLY LEFT BLANK
TABLE OF CONTENTS
Page - 1
CABLE, WISCONSIN
January 17, 2020
PROJECT SPECIFICATIONS
DIVISION 01 GENERAL REQUIREMENTS
SECTION 01 2400 CHANGE ORDER PROCEDURE: FAR 52.243-1
01 2500 PRODUCT SUBSTITUTIONS: FAR 52.236.21
01 3100 PROJECT MANAGEMENT & COORDINATION: FAR 52.236-6, FAR 52.236-15, FAR
52.236-26
01 3300 SUBMITTAL PROCEDURES
01 3591 HISTORIC TREATMENT PROCEDURES
01 4000 QUALITY REQUIREMENTS: FAR 52.236-5
01 4200 REFERENCES
01 5000 TEMPORARY FACILITIES AND CONTROLS
01 6000 PRODUCT REQUIREMENTS: FAR 52.236-5, FAR 52.246-21
01 7300 EXECUTION REQUIREMENTS: FAR 52.236-17
01 7329 CUTTING AND PATCHING
01 7419 CONSTRUCTION WASTE MANAGEMENT & DISPOSAL: FAR 52.236-12
01 7700 CLOSEOUT PROCEDURES
01 7823 OPERATION AND MAINTENANCE DATA
DIVISION 02 EXISTING CONDITIONS
SECTION 02 4119 SELECTIVE DEMOLITION
02 8716.13 EXCREMENT REMOVAL
DIVISION 05 METALS
SECTION 05 5000 METAL FABRICATIONS
DIVISION 06 WOODS, PLASTICS, AND COMPOSITES
SECTION 06 1000 ROUGH CARPENTRY
06 1600 SHEATHING
06 1753 SHOP-FABRICATED WOOD TRUSSES
06 1800 GLUED-LAMINATED CONSTRUCTION
06 4023 INTERIOR ARCHITECTURAL WOODWORK
Page - 2
DIVISION 07 THERMAL AND MOISTURE PROTECTION
SECTION 07 1113 BITUMINOUS DAMPPROOFING
07 2100 THERMAL INSULATION
07 2500 WEATHER BARRIERS
07 6200 SHEET METAL FLASHING AND TRIM
07 8413 PENETRATION FIRESTOPPING
07 9200 JOINT SEALANTS
DIVISION 08 OPENINGS
SECTION
08 1113 HOLLOW METAL DOORS & FRAMES
08 7100 DOOR HARDWARE
DIVISION 09 FINISHES
SECTION 09 2900 GYPSUM BOARD
09 9123 INTERIOR PAINTING
DIVISION 10 SPECIALTIES
SECTION
10 4416 FIRE EXTINGUISEHRS, CABINETS & ACCESSORIES
Page - 3
DIVISION 22 PLUMBING
SECTION 22 0500 COMMON WORK RULES FOR PLUMBING
22 1005 PLUMBING PIPING
DIVISION 23 HVAC
SECTION 23 0500 COMMON WORK RESULTS FOR HVAC
23 0513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
23 0529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
23 0548 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT
23 5100 BREECHINGS, CHIMNEYS, AND STACKS
23 5500 FUEL-FIRED HEATERS
DIVISION 26 ELECTRICAL
SECTION 26 0100 BASIC ELECTRICAL REQUIREMENTS
26 0110 BASIC ELECTRICAL MATERIALS AND METHODS
26 0115 TEMPORARY SERVICE
26 0501 MINOR ELECTRICAL DEMOLITION
26 0519 LOW-VOLTAGE ELETRICAL POWER CONDUCTORS AND CABLES
26 0526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 0529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
Page - 4
26 0534 CONDUIT
26 0535 SURFACE RACEWAYS
26 0537 BOXES
26 0553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 2416 PANELBOARDS
26 2701 ELECTRICAL SERVICE ENTRANCE
26 2716 ELECTRICAL CABINETS AND ENCLOSURES
26 2717 EQUIPMENT WIRING
26 2726 WIRING DEVICES
26 2818 ENCLOSED SWITCHES
26 5100 INTERIOR LIGHTING
DIVISION 31 EARTHWORK
31 2000 EARTH MOVING
DIVISION 32 EXTERIOR IMPROVEMENTS
32 1200 GRAVEL ROAD SURFACING
CHANGE ORDER PROCEDURE
01 2400 - 1
SECTION 01 2400 – CHANGE ORDER PROCEDURE: FAR 52.243-1
CHANGE ORDER PROCEDURE
01 2400 - 2
PRODUCT SUBSTITUTIONS
01 2500-1
SECTION 01 2500 – PRODUCT SUBSTITUTUIONS: FAR 52.236-21
Project No. 19042 01 2500-2
FOREST LODGE THREE BUILDING HISTORIC REHABILITATION PRODUCT SUBSTITUTIONS
PROJECT MANAGEMENT AND COORDINATION
01 3100 - 1
SECTION 01 3100 – PROJECT MANAGEMENT AND COORDINATION: FAR 52.236-6, FAR 52.236-15, FAR 52.236-26
PROJECT MANAGEMENT AND COORDINATION
01 3100 - 2
SUBMITTAL PROCEDURES
01 3300 - 1
SECTION 01 3300 – SUBMITTAL PROCEDURES
PART 1 – GENERAL
1.1 SUBMITTALS
A. Within 10 days after Award of Contract and before any items are submitted for approval, submit to the Contracting Officer’s Representative (COR) two copies of the schedule (refer to FAR 52.236-15).
B. Submittals shall be made identifying document or section number and title. Each item shall be identified separately on the transmittal.
C. All submittals required or referenced in this Project Manual are to be submitted to the Contracting Officer’s Representative (COR). Such submittals will be further distributed per the COR’s discretion.
PART 2 – PRODUCTS
2.1 SHOP DRAWINGS AND SUBMITTALS LOG
A. Compile a complete and comprehensive schedule (refer to FAR 52.236.15) of all submittals anticipated to be made during progress of the work. Include a list of each type of item for which Contractor’s drawings, shop drawings, material samples, guarantees or other types of submittals are required.
2.2 SUBCONTRACTORS AND SUPPLIERS SCHEDULE
A. Within 10 days after notification of selection for award of contract, provide a listing of major subcontractors; include their address, phone number and the portions of work which they will perform.
B. Within 30 days after notification of selection for award of contract, provide a listing of suppliers and manufacturers;
include their address, phone number and the portions of work which they will perform.
2.3 SHOP DRAWINGS AND COORDINATION DRAWINGS
A. Shop Drawings.
1. Make to a scale sufficiently large to show all pertinent aspects of the item and its method of connection.
2. Submit one (1) copy of shop drawings via email using PDF format.
a. COR will forward one (1) copy to A/E.
b. A/E will keep one copy for A/E file and provide one copy in PDF format for owner.
c. A/E will forward one copy with review comments in PDF format via email to general contractor.
3. All review comments of A/E will be shown on the shop drawing copy returned to contractor. Contractor: make and distribute all copies required for his purposes.
4. Shop drawings shall be prepared specifically for this project. No reproduction of A/E’s drawings will be accepted.
B. Shop Drawing Approvals.
1. Reviewing and conditional approval are only for conformance with the design concept of the project and compliance with the information given in the contract documents.
2. Conditions of Approval: The Contractor is responsible for dimensions to be confirmed and correlated at the site;
for information that pertains solely to the fabrication process or to the means, methods, techniques, sequences and procedures of construction and for coordination of the work of all trades. Corrections or comments made on
01 3300 - 2 this shop drawing submittal do not relieve the Contractor from compliance with requirements of contract documents.
2.4 PRODUCT DATA
A. Where contents of submitted product data includes data not pertinent to the submittal, clearly indicate which portion of the contents is being submitted for review.
2.5 SAMPLES
A. Samples shall be of the precise article proposed to be furnished.
B. Submit all samples in the quantity which is required to be returned plus two which will be retained by A/E.
C. In situations specifically so approved by A/E, A/E’s retained sample may be used in the construction as one of the installed items.
D. Even when the precise color and pattern is specifically described in the contract documents and wherever a choice of color or pattern is available in a specified product, provide color choices and patterns for approval, including the color specified.
2.6 SCHEDULE OF VALUES
A. Prepare the Schedule of Values required by the General Conditions, in conjunction with the preparation of the Progress Schedule. Correlate line items with other administrative schedules and forms required for the work.
B. Submit the Schedule of Values to A/E no later than 10 days before submission of the first Application for Payment.
Refer to the Supplementary Conditions for detail of format and content of Schedule of Values.
C. Cost breakdown shall be on a product section-by-product section basis. Dollar value shall be rounded off to the nearest $1.00.
D. Cost breakdown will be used for project completion percentages only.
2.7 MISCELLANEOUS SUBMITTALS
A. Test Reports and Data: Submit test reports and data to the A/E according to Section 01 400 and elsewhere in the project specifications.
B. Guarantees, Warranties, Certificates, Operating Instructions and Maintenance Instructions: Submit all such items to the Owner thru the A/E as required by Section 01 7700 and others as applicable.
C. Consent of Surety Form: Contractor request for final payment shall be accompanied by a properly executed copy of
Document 00 6220 Consent of Surety to Final Payment as bound in this Project Manual.
D. Warranties: Provide standard warranty for 1year parts and labor.
2.8 FINAL SUBMITTALS
A. Final submittal shall be in accordance with Section 01 7700 Closeout Procedures.
01 3300 - 3
PART 3 – EXECUTION
3.1 TIMING OF SUBMITTALS
A. Make all submittals far enough in advance of scheduled dates for installation to provide all time required for reviews, for securing necessary approvals, for possible revisions and resubmittals and for placing orders and securing delivery.
Submit written substitution requests to the A/E at least 10 days prior to bid due date. Requests received after this time will not be considered.
B. In scheduling, allow at least 10 calendar days for review by A/E following his receipt of the submittal.
C. Any submittals that may affect historic characteristics of the building may require an additional 30 days for submittal review.
D. Delays caused by tardiness in receipt of submittals will not be an acceptable basis for extension of the contract completion date.
END OF SECTION 01 3300
01 3300 - 4
HISTORIC TREATMENT PROCEDURES
01 3591 - 1
SECTION 01 3591 – HISTORIC TREATMENT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes general protection and treatment procedures for designated historic spaces, areas, rooms, and surfaces in Project.
1.2 DEFINITIONS
A. Consolidate: To strengthen loose or deteriorated materials in place.
B. Design Reference Sample: A sample that represents Architect's prebid selection of work to be matched; it may be existing work or work specially produced for Project.
C. Dismantle: To disassemble or detach a historic item from a surface, or a nonhistoric item from a historic surface, using gentle methods and equipment to prevent damage to historic items and surfaces; disposing of items unless indicated to be salvaged or reinstalled.
D. Historic: Spaces, areas, rooms, surfaces, materials, finishes, and overall appearance that are important to the successful rehabilitation, restoration, and reconstruction as determined by Architect. Designated historic rooms and surfaces are indicated on Drawings
1. Renovation Zones: Areas of significant architectural importance, integrity, and visibility; to be preserved and restored consistent with the remaining historic fabric and to the extent indicated on Drawings.
2. Alteration Zones: Areas of slight architectural importance, integrity, and visibility; to leave any remaining original fabric untouched insofar as is consistent with accommodating modern uses for the building as indicated on Drawings.
E. Match: To blend with adjacent construction and manifest no apparent difference in material type, species, cut, form, detail, color, grain, texture, or finish; as approved by Architect.
F. Refinish: To remove existing finishes to base material and apply new finish to match original, or as otherwise indicated.
G. Reinstall: To protect removed or dismantled item, repair and clean it as indicated for reuse, and reinstall it in original position, or where indicated.
H. Remove: To take down or detach a non-historic item located within a historic space, area, or room, using methods and equipment to prevent damage to historic items and surfaces; disposing of items unless indicated to be salvaged or reinstalled.
I. Repair: To correct damage and defects, retaining existing materials, features, and finishes while employing as little new material as possible. This includes patching, piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials.
J. Replace: To remove, duplicate, and reinstall entire item with new material. The original item is the pattern for creating duplicates unless otherwise indicated.
K. Replicate: To reproduce in exact detail, materials, and finish unless otherwise indicated.
01 3591 - 2
L. Reproduce: To fabricate a new item, accurate in detail to the original, and from either the same or a similar material as the original, unless otherwise indicated.
M. Restore: To consolidate, replicate, reproduce, repair, and refinish as required to achieve the indicated results.
N. Retain: To keep existing items that are not to be removed or dismantled.
O. Reversible: New construction work, treatments, or processes that can be removed or undone in the future without damaging historic materials unless otherwise indicated.
P. Salvage: To protect removed or dismantled items and deliver them to Owner [ready for reuse].
Q. Stabilize: To provide structural reinforcement of unsafe or deteriorated items while maintaining the essential form as it exists at present; also, to reestablish a weather-resistant enclosure.
R. Strip: To remove existing finish down to base material unless otherwise indicated.
1.3 PROJECT MEETINGS FOR HISTORIC TREATMENT
A. Preliminary Historic Treatment Conference: Before starting historic treatment work, conduct conference at Project site.
1. Attendees: In addition to representatives of Owner, Architect, and Contractor, testing service representative, historic treatment specialists, chemical-cleaner manufacturer(s), and installers whose work interfaces with or affects historic treatment shall be represented at the meeting.
2. Agenda: Discuss items of significance that could affect progress of historic treatment work, including review of the following:
a. Fire-prevention plan.
b. Governing regulations.
c. Areas where existing construction is to remain and the required protection.
d. Hauling routes.
e. Sequence of historic treatment work operations.
f. Storage, protection, and accounting for salvaged and specially fabricated items.
g. Existing conditions, staging, and structural loading limitations of areas where materials are stored.
3. Reporting: Architect will record conference results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from conference.
B. Coordination Meetings: Conduct specifically for historic treatment work at monthly intervals. Coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and preinstallation conferences.
1. Agenda: Review and correct or approve minutes of previous coordination meeting. Review other items of significance that could affect progress of historic treatment work. Include topics for discussion as appropriate to status of Project.
2. Reporting: Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.
1.4 MATERIALS OWNERSHIP
A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, antiques, and other items of interest or value to Owner that may be
01 3591 - 3 encountered or uncovered during the Work, regardless of whether they were previously documented, remain Owner's property.
1.5 INFORMATIONAL SUBMITTALS
A. Historic Treatment Program: Submit 30 days before work begins.
B. Fire-Prevention Plan: Submit 30 days before work begins.
1.6 QUALITY ASSURANCE
A. Historic Treatment Specialist Qualifications: An experienced firm regularly engaged in historic treatments similar in nature, materials, design, and extent to the work as specified in each Section and that has completed a minimum of five recent projects with a record of successful in-service performance that demonstrates the firm's qualifications to perform this work.
1. Field Supervisor Qualifications: Full-time supervisors experienced in historic treatment work similar in nature, material, design, and extent to that indicated for this Project. Supervisors shall be on site when historic treatment work begins and during its progress. Supervisors shall not be changed during Project except for causes beyond control of the specialist firm.
B. Title X Requirement: Each firm conducting activities that disturb painted surfaces shall be a "Lead-Safe Certified Firm" according to 40 CFR 745, Subpart E, and use only workers that are trained in lead-safe work practices.
C. Historic Treatment Program: Prepare a written plan for historic treatment for whole Project, including each phase or process and protection of surrounding materials during operations. Describe in detail the materials, methods, and equipment to be used for each phase of work. Show compliance with indicated methods and procedures specified in this and other Sections. Coordinate this whole-Project historic treatment program with specific requirements of programs required in other historic treatment Sections.
1. Dust and Noise Control: Include locations of proposed temporary dust- and noise-control partitions and means of egress from occupied areas coordinated with continuing on-site operations and other known work in progress.
2. Debris Hauling: Include plans clearly marked to show debris hauling routes, turning radii, and locations and details of temporary protective barriers.
D. Fire-Prevention Plan: Prepare a written plan for preventing fires during the Work, including placement of fire extinguishers, fire blankets, rag buckets, and other fire-control devices during each phase or process. Coordinate plan with Owner's fire-protection equipment and requirements. Include fire-watch personnel's training, duties, and authority to enforce fire safety.
E. Safety and Health Standard: ANSI/ASSE A10.6.
1.7 STORAGE AND HANDLING OF HISTORIC MATERIALS
A. Salvaged Historic Materials:
1. Clean loose dirt and debris from salvaged historic items unless more extensive cleaning is indicated.
2. Pack or crate items after cleaning; cushion against damage during handling. Label contents of containers.
3. Store items in a secure area until delivery to Owner.
4. Transport items to Owner's storage area on-site designated by Owner.
5. Protect items from damage during transport and storage.
01 3591 - 4
B. Historic Materials for Reinstallation:
1. Repair and clean historic items for reuse as indicated.
2. Pack or crate items after cleaning and repairing; cushion against damage during handling. Label contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment unless otherwise indicated. Provide connections, supports, and miscellaneous materials to make items functional for use indicated.
C. Existing Historic Materials to Remain: Protect construction indicated to remain against damage and soiling from construction work. Where permitted by Architect, items may be dismantled and taken to a suitable, protected storage location during construction work and reinstalled in their original locations after historic treatment and construction work in the vicinity is complete.
D. Storage: Catalog and store historic items within a weathertight enclosure where they are protected from moisture, weather, condensation, and freezing temperatures.
1. Identify each item with a nonpermanent mark to document its original location. Indicate original locations on plans, elevations, sections, or photographs by annotating the identifying marks.
2. Secure stored materials to protect from theft.
3. Control humidity so that it does not exceed 85 percent. Maintain temperatures 5 deg F (3 deg C) or more above the dew point.
PART 2 - PRODUCTS - (Not Used)
PART 3 - EXECUTION
3.1 PROTECTION
A. Protect persons, motor vehicles, surrounding surfaces of building, building site, plants, and surrounding buildings from harm resulting from historic treatment procedures.
1. Use only proven protection methods, appropriate to each area and surface being protected.
2. Provide temporary barricades, barriers, and directional signage to exclude the public from areas where historic treatment work is being performed.
3. Erect temporary barriers to form and maintain fire-egress routes.
4. Erect temporary protective covers over walkways and at points of pedestrian and vehicular entrance and exit that must remain in service during historic treatment work.
5. Contain dust and debris generated by historic treatment work, and prevent it from reaching the public or adjacent surfaces.
6. Provide shoring, bracing, and supports as necessary. Do not overload structural elements.
7. Protect floors and other surfaces along hauling routes from damage, wear, and staining.
8. Provide supplemental sound-control treatment to isolate removal and dismantling work from other areas of the building.
B. Temporary Protection of Historic Materials:
1. Protect existing historic materials with temporary protections and construction. Do not remove existing materials unless otherwise indicated.
2. Do not attach temporary protection to historic surfaces except as indicated as part of the historic treatment program and approved by Architect.
01 3591 - 5
C. Comply with each product manufacturer's written instructions for protections and precautions. Protect against adverse effects of products and procedures on people and adjacent materials, components, and vegetation.
D. Utility and Communications Services:
1. Notify Owner, Architect, authorities having jurisdiction, and entities owning or controlling wires, conduits, pipes, and other services affected by historic treatment work before commencing operations.
2. Disconnect and cap pipes and services as required by authorities having jurisdiction, as required for historic treatment work.
3. Maintain existing services unless otherwise indicated; keep in service and protect against damage during operations. Provide temporary services during interruptions to existing utilities.
E. Existing Drains: Prior to the start of work in an area, test drainage system to ensure that it is functioning properly. Notify Architect immediately of inadequate drainage or blockage. Do not begin work in an area until the drainage system is functioning properly.
1. Prevent solids such as stone or mortar residue or other debris from entering the drainage system. Clean out drains and drain lines that become sluggish or blocked by sand or other materials resulting from historic treatment work.
2. Protect drains from pollutants. Block drains or filter out sediments, allowing only clean water to pass.
F. Existing Roofing: Prior to the start of work in an area, install roofing protection.
3.2 PROTECTION FROM FIRE
A. Follow fire-prevention plan and the following:
1. Comply with NFPA 241 requirements unless otherwise indicated.
2. Remove and keep area free of combustibles, including rubbish, paper, waste, and chemicals, unless necessary for the immediate work.
a. If combustible material cannot be removed, provide fire blankets to cover such materials.
3. Prohibit smoking by all persons within Project work and staging areas.
B. Heat-Generating Equipment and Combustible Materials: Comply with the following procedures while performing work with heat-generating equipment or combustible materials, including welding, torch-cutting, soldering, brazing, removing paint with heat, or other operations where open flames or implements using high heat or combustible solvents and chemicals are anticipated:
1. Obtain Owner's approval for operations involving use of open-flame or welding or other high-heat equipment.
Notify Owner at least 48 hours before each occurrence, indicating location of such work.
2. As far as practicable, restrict heat-generating equipment to shop areas or outside the building.
3. Do not perform work with heat-generating equipment in or near rooms or in areas where flammable liquids or explosive vapors are present or thought to be present. Use a combustible gas indicator test to ensure that area is safe.
4. Use fireproof baffles to prevent flames, sparks, hot gases, or other high-temperature material from reaching surrounding combustible material.
5. Prevent the spread of sparks and particles of hot metal through open windows, doors, holes, and cracks in floors, walls, ceilings, roofs, and other openings.
6. Fire Watch: Before working with heat-generating equipment or combustible materials, station personnel to serve as a fire watch at each location where such work is performed. Fire-watch personnel shall have the authority to enforce fire safety. Station fire watch according to NFPA 51B, NFPA 241, and as follows:
01 3591 - 6
a. Train each fire watch in proper operation of fire-control equipment and alarms.
b. Prohibit fire-watch personnel from other work that would distract from fire-watch duties.
c. Cease work with heat-generating equipment whenever fire-watch personnel are not present.
d. Have fire-watch personnel perform final fire-safety inspection each day beginning no sooner than 30 minutes after conclusion of work to detect hidden or smoldering fires and to ensure that proper fire prevention is maintained.
e. Maintain fire-watch personnel at Project site until two hours after conclusion of daily work.
C. Fire-Control Devices: Provide and maintain fire extinguishers, fire blankets, and rag buckets for disposal of rags with combustible liquids. Maintain each as suitable for type of fire risk in each work area. Ensure that nearby personnel and fire-watch personnel are trained in fire-extinguisher and blanket use.
3.3 PROTECTION DURING APPLICATION OF CHEMICALS
A. Protect motor vehicles, surrounding surfaces of building being restored, building site, plants, and surrounding buildings from harm or spillage resulting from applications of chemicals and adhesives.
B. Cover adjacent surfaces with protective materials that are proven to resist chemicals selected for Project unless chemicals being used will not damage adjacent surfaces as indicated in historic treatment program. Use covering materials and masking agents that are waterproof and UV resistant and that will not stain or leave residue on surfaces to which they are applied. Apply protective materials according to manufacturer's written instructions. Do not apply liquid masking agents or adhesives to painted or porous surfaces. When no longer needed, promptly remove protective materials.
C. Do not apply chemicals during winds of sufficient force to spread them to unprotected surfaces.
D. Neutralize alkaline and acid wastes and legally dispose of off Owner's property.
E. Collect and dispose of runoff from chemical operations by legal means and in a manner that prevents soil contamination, soil erosion, undermining of paving and foundations, damage to landscaping, or water penetration into building interior.
3.4 GENERAL HISTORIC TREATMENT
A. Have historic treatment work performed only by qualified historic treatment specialists.
B. Ensure that supervisory personnel are present when historic treatment work begins and during its progress.
C. Record existing work before each procedure (preconstruction), and record progress during the work. Use digital preconstruction documentation photographs.
D. Perform regular inspections of Project site as the Work progresses to detect hazards resulting from historic treatment procedures.
E. Follow the procedures in subparagraphs below and procedures approved in historic treatment program unless otherwise indicated:
1. Retain as much existing material as possible; repair and consolidate rather than replace.
2. Use additional material or structure to reinforce, strengthen, prop, tie, and support existing material or structure.
3. Use reversible processes wherever possible.
4. Use historically accurate repair and replacement materials and techniques unless otherwise indicated.
01 3591 - 7
5. Record existing work before each procedure (preconstruction) and progress during the work with digital preconstruction documentation photographs. Comply with requirements in Section 013233 "Photographic Documentation."
F. Notify Architect of visible changes in the integrity of material or components whether from environmental causes including biological attack, UV degradation, freezing, or thawing or from structural defects including cracks, movement, or distortion.
1. Do not proceed with the work in question until directed by Architect.
G. Where missing features are indicated to be repaired or replaced, provide work with appearance based on accurate duplications rather than on conjecture, subject to approval of Architect.
H. Where work requires existing features to be removed or dismantled and reinstalled, perform these operations without damage to the material itself, to adjacent materials, or to the substrate.
I. Identify new and replacement materials and features with permanent marks hidden in the completed Work to distinguish them from original materials. Record a legend of identification marks and the locations of the items on record Drawings.
END OF SECTION 01 3591
01 3591 - 8
QUALITY REQUIREMENTS
01 4000 - 1
SECTION 01 4000 – QUALITY REQUIREMENTS: FAR 52.236-5
QUALITY REQUIREMENTS
01 4000 - 2
REFERENCES
01 4200 - 1
SECTION 01 4200 – REFERENCES
PART 1 – GENERAL
A. This Section specifies administrative requirements for compliance with standards.
1. Refer to General and Supplementary Conditions for requirements for compliance with governing regulations.
A. Indicated refers to graphic representations, notes or schedules on the Drawings or other Paragraphs or Schedules in Specifications and similar requirements in Contract Documents. Where terms such as shown, noted, scheduled and specified are used, it is to help locate the reference; no limitation on location is intended except as specifically noted.
B. The term furnish is used to mean supply and deliver to the project site, ready for unloading, unpacking, assembly, installation and similar operations.
C. The term install is used to describe operations at project site including the actual unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning and similar operations.
D. The term “provide” means to furnish and install, complete and ready for the intended use.
1.3 INDUSTRY STANDARDS
A. Trade association names and titles of general standards are frequently abbreviated. The following acronyms or abbreviations as referenced in Contract Documents are defined to mean the associated names. Names and addresses are subject to change and are believed to be, but are not assured to be, accurate and up-to-date as of date of Contract Documents.
AA ALUMINUM ASSOCIATION
818 Connecticut Avenue, N.W.
Washington, DC 20006
AABC ASSOCIATED AIR BALANCE COUNCIL
100 Vermont Avenue, N.W.
Washington, DC 20005
ABA ARCHITECTURAL BARRIERS ACT ACCESSILIBITY STANDARDS
U. S. Access Board 1331 F Street, N.W., Suite 1000 Washington, DC 20004
ACI AMERICAN CONCRETE INSTITUTE
Box 19150 Redford Station Detroit, MI 48219
ADC AIR DIFFUSION COUNCIL
435 North Michigan Avenue Chicago, IL 60611
01 4200 - 2
AGC ASSOCIATED GENERAL CONTRACTORS
OF AMERICA
1957 E. Street, N.W.
Washington, DC 20006
AISC AMERICAN INSTITUTE OF STEEL
CONSTRUCTION
1221 Avenue of the Americas New York, NY 10020
AISI AMERICAN IRON & STEEL INSTITUTE
1000 16th Street, N.W.
Washington, D.C. 20036
AMCA AIR MOVEMENT & CONTROL ASSOCIATION
30 West University Drive Arlington Heights, IL 60004
ANSI AMERICAN NATIONAL STANDARDS INSTITUTE
1430 Broadway New York, NY 10018
APA AMERICAN PLYWOOD ASSOCIATION
Box 11700 Tacoma, WI 98411
ARI AIR CONDITIONING & REFRIGERATION
INSTITUTE
1815 North Fort Myer Drive Arlington, VA 22209
ASHRAE AMERICAN SOCIETY OF HEATING,
REFRIGERATION & AIR CONDITIONING
ENGINEERS
345 East 47th Street New York, NY 10017
ASME AMERICAN SOCIETY OF MECHANICAL
ENGINEERS
ASTM AMERICAN SOCIETY FOR TESTING &
MATERIALS
1916 Race Street Philadelphia, PA 19103
AWI ARCHITECTURAL WOODWORK INSTITUTE
2310 South Walter Reed Drive Arlington, VA 22206
AWPA AMERICAN WOOD-PERSERVERS ASSOCIATION
7735 Old Georgetown Road Bethesda, MD 20014
01 4200 - 3
AWS AMERICAN WELDING SOCIETY
2501 NW 7th Street Miami, FL 33125
CRSI CONCRETE REINFORCING STEEL INSTITUTE
933 Plum Grove Road Schaumburg, IL 60195
FS FEDERAL SPECIFICATION
GENERAL SERVICES ADMINISTRATION
SPECIFICATIONS and CONSUMER INFORMATION Distribution Section (WFSIS) Washington Navy Yard, Bldg. 197 Washington, DC 20407
IEEE INSTITUTE OF ELECTRICAL & ELECTRONICS
ENGINEERS
IMIAC INTERNATIONAL MASONRY INDUSTRY
ALL-WEATHER COUNCIL
INTERNATIONAL MASONRY INSTITUTE
823 15th Street, N.W.
Washington, DC 20005
NAAMM NATIONAL ASSOCIATION OF ARCHITECTURAL
METAL MANUFACTURERS
221 North LaSalle Street Chicago, IL 60601
NEBB NATIONAL ENVIRONMENTAL BALANCING BUREAU
8224 Old Courthouse Road Vienna, VA 22180
NEMA NATIONAL ELECTRICAL MANUFACTURER'S
ASSOCIATION
2101 L Street, N.W.
Washington, DC 20037
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
Battery March Park Quincy, MA 02269
PCA PORTLAND CEMENT ASSOCIATION
5420 Old Orchard Road Skokie, IL 20076
PCI PRESTRESSED CONCRETE INSTITUTE
20 North Wacker Drive Chicago, IL 60606
SMACNA SHEET METAL & AIR CONDITIONING
01 4200 - 4
CONTRACTOR'S NATIONAL ASSOCIATION
8224 Old Courthouse Road Vienna, VA 22180
SSPC STEEL STRUCTURES PAINTING COUNCIL
4400 Fifth Avenue Pittsburgh, PA 15213
TCA TILE COUNCIL OF AMERICA, INC.
Box 326 Princeton, NJ 08540
UL UNDERWRITER'S LABORATORIES, INC.
333 Pfingston Road Northbrook, IL 60062
END OF SECTION 01 4200
TEMPORARY FACILITIES AND CONTROLS
01 5000 - 1
SECTION 01 5000 – TEMPORARY FACILITIES AND CONTROLS
A. This Section includes requirements for temporary utilities, construction facilities, and security and protection facilities.
B. See Division 01 Section "Execution Requirements" for progress cleaning requirements.
C. See Divisions 03 through 28 Sections for temporary heat, ventilation, and humidity requirements for products in those Sections.
A. Permanent Enclosure: As determined by Architect, permanent or temporary roofing is complete, insulated, and weathertight; exterior walls are insulated and weathertight; and all openings are closed with permanent construction or substantial temporary closures.
1.3 USE CHARGES
A. General: Cost or use charges for temporary facilities shall be included in the Contract Sum. Allow other entities to use temporary services and facilities without cost, including, but not limited to, Owner's construction forces, Architect, occupants of Project, testing agencies, and authorities having jurisdiction.
B. Water Service: Water from Owner's existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.
C. Electric Power Service: Electric power from Owner's existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.
1.4 JOB CONDITIONS
A. Make all required connections to existing utility systems with minimum disruption to services in the existing utility systems. When disruption of the existing service is required, do not proceed without Architect/Engineer’s approval and, when required, provide alternate temporary service.
B. Establish and initiate use of each temporary facility at time first reasonably required for proper performance of the work.
Terminate use and remove facilities at earliest reasonable time, when no longer needed or when permanent facilities have, with authorized use, replaced the need.
C. Conditions of Use: Install, operate, maintain and protect temporary facilities in a manner and at locations which will be safe, non-hazardous, sanitary and protective of persons and property and free of deleterious effects.
1.5 SUBMITTALS
A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel.
01 5000 - 2
1.6 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use.
Obtain required certifications and permits.
1.7 VEHICULAR ACCESS
A. Provide unimpeded access for emergency vehicles. Maintain 20 foot wide driveways with turning space between and around combustible materials.
B. Provide and maintain access to fire hydrants and control valves free of obstructions.
C. Use designated existing on-site roads for construction traffic.
1.8 PARKING
A. Arrange for temporary surface parking areas to accommodate construction personnel.
B. Locate as approved by Owner.
C. When site space is not adequate, provide additional off-site parking.
D. Use of designated existing on-site streets and driveways used for construction traffic is permitted. Tracked vehicles not allowed on paved areas.
E. Use of designated areas of existing parking facilities used by construction personnel is not permitted.
F. Do not allow heavy vehicles or construction equipment in parking areas.
G. Do not allow vehicle parking on existing pavement.
1.9 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in clean and orderly condition.
1.10 DUST CONTROL
A. Execute Work by methods to minimize raising dust from construction operations.
B. Provide positive means to prevent air-borne dust from dispersing into atmosphere.
1.11 NOISE CONTROL
A. Provide methods, means, and facilities to minimize noise produced by construction operations.
01 5000 - 3
1.12 POLLUTION CONTROL
A. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations.
B. Comply with pollution and environmental control requirements of authorities having jurisdiction.
1.13 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.
PART 2 - PRODUCTS
2.1 TEMPORARY FACILITIES
A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.
B. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.
C. Temporary Toilets: Provide and maintain.
2.2 WEATHER PROTECTION
A. Protect material, apparatus, fixtures and the work from damage by wind, freezing and precipitation while in shipment, storage and in place. Cover and otherwise protect each day’s work susceptible to weather damage.
B. Keep equipment and surroundings in a clean, safe condition. Tarpaulins and other materials used for temporary enclosure of space shall be flame resistant.
C. Conditions of Use: Install, operate, maintain and protect temporary facilities in a manner and at locations which will be safe, non-hazardous, sanitary and protective of persons and property and free of deleterious effects.
2.3 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.
B. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.
1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.
2. Heating Units: Listed and labeled for type of fuel being consumed, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.
3. Permanent HVAC System: If Owner authorizes use of permanent HVAC system for temporary use during construction, provide filter with MERV of 8 at each return air grille in system and remove at end of construction.
01 5000 - 4
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.
1. Locate facilities to limit site disturbance as specified in Division 01 Section "Summary."
B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.
1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.
B. Water Service: Use of Owner's existing water service facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.
1. Where installations below an outlet might be damaged by spillage or leakage, provide a drip pan of suitable size to minimize water damage. Drain accumulated water promptly from pans.
C. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel.
Comply with authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.
D. Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed.
E. Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption.
F. Electric Power Service: Use of Owner's existing electric power service will be permitted, as long as equipment is maintained in a condition acceptable to Owner.
G. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.
1. Connect temporary service to Owner's existing power source, as directed by Owner.
H. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.
1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.
I. Telephone Service: Provide temporary telephone service in common-use facilities for use by all construction personnel.
01 5000 - 5
1. Post a list of important telephone numbers including police and fire departments, Contractor's home office, Architect's office, Owner's office, Principal subcontractors' field and home offices.
2. Provide superintendent with cellular telephone or portable two-way radio for use when away from field office.
J. Electronic Communication Service: Provide temporary electronic communication service, including electronic mail in field office.
3.3 SUPPORT FACILITIES INSTALLATION
A. General: Comply with the following:
1. Provide incombustible construction for offices, shops, and sheds located within construction area or within 30 feet of building lines. Comply with NFPA 241.
2. Maintain support facilities until near Substantial Completion. Remove before Substantial Completion.
Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.
B. Parking: Provide temporary parking areas for construction personnel.
C. Project Identification and Temporary Signs: Unauthorized signs are not permitted.
1. Provide temporary, directional signs for construction personnel and visitors.
2. Maintain and touchup signs so they are legible at all times.
D. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. Comply with Division 1 Section "Execution Requirements" for progress cleaning requirements.
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
B. Stormwater Control: Comply with authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.
C. Barriers, Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
D. Temporary Partitions: Provide floor-to-ceiling dustproof partitions to limit dust and dirt migration and to separate areas occupied by Owner and tenants from fumes and noise.
1. Construct dustproof partitions with gypsum wallboard with joints taped on occupied side, and fire-retardant plywood on construction operations side.
2. Construct dustproof partitions with 2 layers of 6-mil polyethylene sheet on each side. Cover floor with 2 layers of 6-mil polyethylene sheet, extending sheets 18 inches up the sidewalls. Overlap and tape full length of joints.
Cover floor with fire-retardant plywood.
a. Construct vestibule and airlock at each entrance through temporary partition with not less than 48 inches between doors. Maintain water-dampened foot mats in vestibule.
3. Insulate partitions to provide noise protection to occupied areas.
4. Seal joints and perimeter. Equip partitions with dustproof doors and security locks.
01 5000 - 6
5. Protect air-handling equipment.
6. Weather strip openings.
7. Provide walk-off mats at each entrance through temporary partition.
E. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241.
1. Prohibit smoking in construction areas.
2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.
3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.
4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles.
F. Temporary Existing Floor Protection: Install and maintain temporary floor protection.
3.5 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal.
1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.
C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.
D. Termination and Removal:
1. Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion.
2. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
3. Clean and repair damage caused by installation of temporary work.
4. Restore existing and permanent facilities used during construction to original condition.
5. Materials and facilities that constitute temporary facilities are property of Contractor.
6. At Substantial Completion, clean and renovate permanent facilities used during construction period. Comply with final cleaning requirements specified in Division 01 Section "Closeout Procedures."
END OF SECTION 01 5000
PRODUCT REQUIREMENTS
01 6000 - 1
SECTION 01 6000 – PRODUCT REQUIREMENTS: FAR 52.236-5, FAR 52.246-21
PRODUCT REQUIREMENTS
01 6000 - 2
EXECUTION REQUIREMENTS
01 7300 - 1
SECTION 01 7300 – EXECUTION REQUIREMENTS: FAR 52.236-17
EXECUTION REQUIREMENTS
01 7300 - 2
CUTTING AND PATCHING
01 7329 - 1
SECTION 01 7329 - CUTTING AND PATCHING
A. This Section…