This daily report template is used to track construction progress on a federal construction project. It requires the contractor to report details of the work performed each day such as the weather, equipment used, inspections conducted, workforce size and trades, and accidents. The related federal opportunity is a solicitation to replace HVAC systems at three buildings at the Federal Law Enforcement Training Center in Glynco, Georgia. Interested offerors must attend a mandatory site visit on June 30th and submit any request for information by July 7th to the contracting officer. The construction value is between $250,000 and $500,000. The selected contractor will be awarded a contract from the Department of Homeland Security's Federal Law Enforcement Training Center to complete the HVAC repair and replacement work.

View the file

Other files

File Type Posted
70LGLY21RSSB000090001 Amendment 1.pdf PDF
Att 23 Financial Questionnaire.pdf PDF
RFI Questions and Answers.xlsx XLSX spreadsheet
Site Visit Sign-in page 2.jpg JPG image
Site Visit Sign-in page 1.jpg JPG image
HVAC Requirement Specifications.pdf PDF
Scope of Work - Section 01 11 00 (amendment 1).pdf PDF
Att 16 Security Handout.pdf PDF
Att 17 Security Training List.pdf PDF
Att 11 Non-Disclosure Agreement.pdf PDF
70LGLY21RSSB00009.pdf PDF
Att 07 FMD_70.pdf PDF
Att 20 SF1444.pdf PDF
Att 18 GA Construction Requirements Statue Wage Determination Bldg. (GA20210160).pdf PDF
Att 08 WH-347 Instruction.pdf PDF
Att 13 I-9.pdf PDF
Att 01 Statement of Work.pdf PDF
Att 15 SF85.pdf PDF
Att 03 SF25A.pdf PDF
Att 19 SF1413.pdf PDF
Att 04 SF28.pdf PDF
Att 21 SF24.pdf PDF
Att 14 OF306.pdf PDF
Att 02 SF25-14.pdf PDF
Att 22 SF LLC.pdf PDF
Att 24 DHS-Form-700-3.pdf PDF
Att 06 Format FIN INST ILC CONFIRM.pdf PDF
Att 12 FLETC Form 121-00-02 (5 days or less).pdf PDF
Att 23 Financial Questionnaire.pdf PDF
Att 05 Format ILC.pdf PDF
Att 25 WH1321 DOL POSTER.pdf PDF
Att 09 WH 347.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FTC-FMD-42 (12/09) 1 of 2

CONTRACT NO. TITLE AND LOCATION DATE

REPORT NO.

CONTRACTOR (Prime or Subcontractor) NAME OF SUPERINTENDENT OR FOREMAN

WEATHER - A.M. TEMPERATURE - A.M.

WEATHER - P.M. TEMPERATURE - P.M.

EMPLOYER

SPEC.PARA.

AND / OR

DRAWING NO.

EQUIPMENT / MATERIAL RECEIVED TODAY

TO BE INCORPORATED IN JOB

(Description, Sizes, Quantity)

SUBMITTAL NO. OR

CERTIFICATION

DATE

APPROV

WERE THERE ANY LOST TIME ACCIDENTS THIS DATE?

REMARKS

RESULTS OF INSPECTION

TESTING

LOCATION AND / OR

ELEMENT OF WORK

TOTAL WORK HOURS FROM

START OF CONSTRUCTION

TOTAL WORK HOURS

ON JOB SITE THIS

DATE

CUMULATIVE TOTAL

OF HOURS FROM

PREVIOUS REPORT

HOURS

INSPECTION AND / OR TESTING

PERFORMED TODAY - - FOLLOW

WITH REPORT

DAILY REPORT TO INSPECTOR

LOCATION AND DESCRIPTION OF WORK

PERFORMED(Use additional sheets if required)

PRIME CONTRACTOR / SUBCONTRACTOR WORKFORCE

NUMBER TRADE

YES NO