This document is a Request for Quote (RFQ) for a Comprehensive Hazardous Materials Survey and Hazard Assessment at the Golden Gate National Recreation Area, Fort Mason Pier One in San Francisco, California.
The RFQ includes a Quote Sheet with 6 contract line items: Project Management, Hazardous Materials Survey Work Plan and Health and Safety Plan, Conducting Field Work, Survey Specification and Reporting, an Option for Surveying Additional Rooms, and an Option for Overseeing Third Party Hazmat Abatement. Offerors must provide pricing for the base line items and all additive options. The RFQ Solicitation Number is 140P8624Q0028 and it is being issued by the Department of the Interior National Park Service, Pacific West Region. The Quote Sheet indicates the required response and pricing structure, including unit prices and extended totals. No specific response dates, award dates, or set asides are provided in this document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ No. 140P8624Q0028
QUOTE SHEET
| RFQ NO. | 140P8624Q0028 |
| PROJECT AREA: | Golden Gate National Recreation Area, San Francisco County, California |
PROJECT TITLE: Comprehensive Hazardous Materials Survey and Hazard Assessment
NOTICE: Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all Additive line items. Failure to do so may render this proposal unacceptable. On lump‐sum (LS) line items, provide the total price only. For all unit‐price (UP) line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs on a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern.
| Contract Line-Item Number (CLIN) |
| Contract Line-Item Title |
| Quantity |
| Unit Of Measure |
| Price Per Unit |
| Total Price |
| 0010 |
| Project Management and Review Existing Documentation and Data |
| 1 |
| Each (EA) |
| 0020 |
| Develop Hazardous Materials Survey Work Plan and Health and Safety Plan |
| 1 |
| Each (EA) |
| 0030 |
| Conduct Field Work |
| 1 |
| Each (EA) |
| 0040 |
| Survey, Specification and Report |
| 0050 |
| Option: Survey Additional Rooms or portions of room (per square foot) |
For bidding purposes please assume 100 Square Feet.
This item price reflects price to conduct a full survey for building materials or goods previously unknown and discovered during survey.
| 1 |
| Each (EA) |
| 0060 |
| Option: Oversee Third Party Hazmat Abatement per Compliance Plan (Lump Sum) |
This item price reflects price to conduct a oversight of Construction contractor – including presence and monitoring during field work, review of analytical data and final reporting, hired via a separate contract, to abate conditions discovered during survey.
| 1 |
| Each (EA) |
TOTAL: