This document is a detailed set of specifications for the NRS Hubbard Brook Pierce Lab Window Replacement project. The contractor will be required to remove and dispose of 8 existing windows, install 8 new vinyl windows, and optionally repair flooring in the conference area and/or replace carpeting. The project location is 234 Mirror Lake Rd, North Woodstock, NH 03262. The work is to be performed under a single prime contract, and the contractor must coordinate with the owner (USDA Forest Service - Northern Research Station) to minimize disruptions. Specific requirements are provided for product submittals, construction waste management, selective demolition, sheathing, vinyl windows, tile carpeting, exterior and interior painting, and seeding and mulching of disturbed areas. A site visit is scheduled for 07/08/2024. This document serves as the technical specifications for this federal contract opportunity.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit_Sign_In_Sheet_12445524Q0092_240708_0002.pdf | ||
| Sol_12445524Q0092_Amd_0002.pdf | ||
| Q_and_A_12445524Q0092_0002.docx | DOCX document | |
| Sol_12445524Q0092_0001.pdf | ||
| Amd_01_12445524Q0092_0001.pdf | ||
| Sol_12445524Q0092_Amd_0001.pdf | ||
| Att_06_Wage_Rates_(240419).pdf | ||
| Att_05_Site_Map_(240605).pdf | ||
| Att_01_Schedule_of_Items_(240621).docx | DOCX document | |
| Att_04_Reference_Drawings_(240605).pdf | ||
| Att_02_SOW_(240605).pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Northern Research Station
NRS Hubbard Brook Pierce Lab Window Replacement
Specifications
011000 – Summary
013300 – Submittal Procedures
017100 – Weed and Disease Prevention
017419 – Construction Waste Management and Disposal
024119 – Selective Demolition
061600 – Sheathing
085313 – Vinyl Windows
096813 – Tile Carpeting
099113 – Exterior Painting
099123 – Interior Painting
099300 – Staining and Transparent Finishing
329000 – Seeding and Mulching
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Contractor's use of site and premises.
4. Coordination with occupants.
5. Work restrictions.
6. Specification and Drawing conventions.
1.2 PROJECT INFORMATION
A. Project Identification: NRS Hubbard Brook Pierce Lab Window Replacement
1. Project Location: 234 Mirror Lake Rd, North Woodstock, NH 03262.
B. Owner: USDA Forest Service – Northern Research Station
1. Contracting Officer’s Representative: Kendre DiPietro – Kendre.DiPietro@usda.gov
2. Site Contact: Ian Halm – Ian.Halm@usda.gov
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Please reference Statement of work and other Contract Documents.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 CONTRACTOR'S USE OF SITE AND PREMISES
A. Limits on Use of Site:
1. Limit use of Project site to areas immediately in the area of work, unless otherwise approved by COR. Do not disturb portions of Project site beyond areas in which are required to complete the contract work.
2. Driveways, Walkways, and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials unless approved by the COR.
B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.
Repair damage caused by construction operations.
C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.5 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
B. Notify COR a minimum of one week prior to beginning work.
1.6 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
2. At the end of each working day, areas around the building must be swept with a magnet. Remove and dispose of any screws, nails, other debris found.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday (except Federal Holidays), unless otherwise indicated.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify COR not less than seven days in advance of proposed utility interruptions.
2. Obtain COR written or verbal permission before proceeding with utility interruptions.
D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify COR not less than seven days in advance of proposed disruptive operations.
2. Obtain COR written permission before proceeding with disruptive operations.
1.7 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
PART 2 - PRODUCTS
A. Reference Sections:
1. 061600 – Sheathing
2. 085313 – Vinyl Windows
3. 096813 – Tile Carpeting
END OF SECTION 011000
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Submittal schedule requirements.
2. Administrative and procedural requirements for submittals.
1.2 DEFINITIONS
A. Approval: Equivalent to “No Exception Taken”.
B. Approved or Approved Equivalent: To possess the same performance qualities and characteristics and fulfill the utilitarian function without any decrease in quality, durability or longevity. For equipment/products defined by the Contractor as "equivalent", substitution requests must be submitted to Contracting Officer’s Representative for consideration and be approved by the COR in writing. Approval shall constitute “No Exception Taken” and shall not be otherwise construed.
C. "No Exception Taken" constitutes that review is for general conformance with the design concept expressed in the Contract Documents for the limited purpose of checking for conformance with information given. Any action is subject to the requirements of the Contract Documents. Contractor is responsible for the dimensions and quantity and will confirm and correlate at the job site, fabrication processes and techniques of construction, coordination of the work with that of all other trades, and the satisfactory performance of the work.
D. Action Submittals: Written and graphic information and physical samples that require CO or COR’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
E. Informational Submittals: Written and graphic information and physical samples that do not require CO or COR’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
1.3 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Contract Name and Number.
2. Date.
3. Name of Contractor.
4. Name of firm or entity that prepared the submittal
5. Names of subcontractor, manufacturer, and supplier.
6. Category and type of submittal.
7. Submittal Purpose and description.
8. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
9. Drawing number and detail references, as appropriate.
10. Indication of full or partial completion.
11. Consecutive transmittal number.
12. Submittal and transmittal distribution record.
13. Other necessary identification.
14. Remarks.
1.4 SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections as PDF electronic files and as indicated for samples and other physical submittals. Types of submittals are indicated in individual Specification Sections.
B. Submittals shall be transmitted via email to the COR & CO.
C. Identify and incorporate information in each electronic submittal file as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form acceptable to Government with links enabling navigation to each item.
2. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by COR.
D. Coordination: Coordinate preparation and processing of submittals with performance of construction activities
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer or COR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
E. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's and COR’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals
1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
Contracting Officer or COR will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process intermediate review in same manner as initial submittal.
3. Resubmittal Review: Allow 15 days for review of each resubmittal.
4. Sequential Review: Where sequential review of submittals by Contracting Officer's consultants, Government, or other parties is indicated, allow 21 days for initial review of each submittal.
F. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Indicate date and content of previous submittal.
2. Indicate date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are approved in writing by the CO or COR (in a method acceptable to the specifications or as otherwise described by the CO).
G. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
H. Use for Construction: Retain complete copies of submittals on Project site. Use only final action or material submittals that are approved in writing by the Contracting Officer or
COR.
1.5 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.
2. Clearly mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.
5. Submit Product Data in PDF electronic file.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated
2. Submit Shop Drawings in PDF Electronic Format.
C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.
D. Design Data/Product Data/Materials Submittals: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.
E. Certificates:
1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide original paper copy where a notarized signature is required.
2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.
4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents
F. Test and Research Reports:
1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:
7. Name of evaluation organization.
8. Date of evaluation.
9. Time period when report is in effect.
10. Product and manufacturers' names.
11. Description of product.
12. Test procedures and results.
13. Limitations of use.
1.6 CONTRACTOR'S REVIEW
A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with contractor approval before submitting to Contracting Officer and COR.
B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform written approval method. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents
1.7 GOVERNMENT REVIEW
A. Contracting Officer’s Representative (COR) may approve technical submittals, unless otherwise indicated by the contract documents or determined in writing by the Contracting Officer (CO). COR may review each submittal instead of the CO.
B. Action Submittals: Will be reviewed and their approval status will be documented in a project submittal review XLS spreadsheet returned to the contractor. The specific material items will be included in this review document and notes for approval, disapproval, and resubmittal and any questions on items.
C. All submittals reviewed will be approved in the material review spreadsheet only. This will be returned to contactor with each submittal group reviewed.
D. No marked up copies of material cut sheets will be returned to the contractor.
E. Informational Submittals: Contracting Officer or COR will review each submittal and will not return it, or may return it if it does not comply with requirements. Contracting Officer or COR may forward each submittal to appropriate party. Contractor is responsible for compliance with contract requirements and all applicable laws and regulations regardless of whether mistakes were discovered by CO or COR review of informational submittals.
F. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from COR or Contracting Officer.
G. Incomplete submittals are unacceptable, will be considered nonresponsive, and may be returned for resubmittal without review.
H. Submittals not required by the Contract Documents may be returned by Contracting Officer or COR without action.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013300
SECTION 017100 WEED AND DISEASE PREVENTION
PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest System lands.
PART 2 - PRODUCTS
2.1 WATER
A. Free of debris, organic matter, and other objectionable substances.
PART 3 - EXECUTION
3.1 GENERAL
A. Notify the COR in writing at least 10 calendar days before moving any construction equipment onto National Forest lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest lands.
B. Perform all work at a location designated on the plans or other locations approved in writing. Provide the COR with an opportunity for inspection.
3.2 EQUIPMENT
A. Use a high-pressure washing system.
B. For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
C. For work at a commercial washing facility, use an approved facility.
3.3 WASHING
A. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
3.4 INSPECTION
A. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment.
Rewash the construction equipment as necessary or as directed.
END OF SECTION 017100
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Disposing of nonhazardous construction waste.
1.2 DEFINITIONS
A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations.
Construction waste includes packaging.
B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.
C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Owner’s property.
PART 2 - EXECUTION
2.1 DISPOSAL OF WASTE
A. General: Remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
END OF SECTION 017419
SECTION 024119 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. The Work of this Section Includes:
1. Demolition and removal of selected portions of exterior or interior of building or structure and site elements.
1.2 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
1.3 FIELD CONDITIONS
A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.
B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
C. Notify COR of discrepancies between existing conditions and Drawings before proceeding with selective demolition.
D. Hazardous Materials:
1. It is not expected that hazardous materials will be encountered in the Work.
2. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify CO and COR. Hazardous materials will be removed by Owner under a separate contract.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI/ASSP A10.6 and NFPA 241.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting selective demolition operations.
B. Photograph any existing building damage prior to beginning selective demolition operations. Notify the CO and COR of any discovered damage.
3.2 PREPARATION
A. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.
B. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by COR, items may be removed to a suitable, protected storage location and reinstalled in their original locations after selective demolition operations are complete.
3.3 UTILITY SERVICES AND BUILDING SYSTEMS
A. Existing Services/Systems to Remain: Maintain utilities and building systems and equipment to remain and protect against damage during selective demolition operations.
3.4 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
B. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.
C. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
D. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.
E. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
F. Any damage caused during the selective damage must be repaired by the contractor.
G. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
3.5 DISPOSAL OF DEMOLISHED MATERIALS
A. Remove demolition waste materials from Project site and recycle or dispose of them in accordance with Section 017419 "Construction Waste Management and Disposal."
B. Do not allow demolished materials to accumulate on-site.
C. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
D. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.
E. Comply with requirements specified in Section 017419 "Construction Waste Management and Disposal."
F. Burning: Do not burn demolished materials.
3.6 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
END OF SECTION 024119
SECTION 061600 - SHEATHING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Subflooring.
1.2 ACTION SUBMITTALS
A. Product Data: For each product.
PART 2 - PRODUCTS
2.1 PRESERVATIVE-TREATED PLYWOOD
A. Preservative Treatment by Pressure Process: AWPA U1; Use Category UC2
B. Mark plywood with appropriate classification marking of an inspection agency acceptable to authorities having jurisdiction.
2.2 FASTENERS
A. For sheathing, provide fasteners with hot-dip zinc coating complying with ASTM A153/A153M or of Type 304 stainless steel.
B. Size Fasteners to Match Original Construction
2.3 MISCELLANEOUS MATERIALS
A. Adhesives for Field Gluing Panels to Wood Framing: Formulation complying with ASTM D3498 that is approved for use with type of construction panel indicated by manufacturers of both adhesives and panels.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Do not use materials with defects that impair quality of sheathing or pieces that are too small to use with minimum number of joints or optimum joint arrangement. Arrange joints so that pieces do not span between fewer than three support members.
B. Cut panels at penetrations, edges, and other obstructions of work; fit tightly against abutting construction unless otherwise indicated.
C. Securely attach to substrate by fastening as completed per original construction.
D. Do not bridge building expansion joints; cut and space edges of panels to match spacing of structural support elements.
END OF SECTION 061600
SECTION 085313 - VINYL WINDOWS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Vinyl windows.
1.2 ACTION SUBMITTALS
A. Product data.
B Shop Drawings:
1. Plans, elevations, sections, hardware, accessories, insect screens, operational clearances, and details of installation, including anchor, flashing, and sealant installation.
2 Samples: Manufacturer's standard color sheets, showing full range of available colors for each type of exposed finish.
1.3 CLOSEOUT SUBMITTALS
A. Warranty documentation.
B. Product Installation and Maintenance Manuals
1.4 QUALITY ASSURANCE
A. Installer Qualifications: Authorized representative who is trained and approved by vinyl window manufacturer.
1.5 WARRANTY
A. Special Warranty: Manufacturer agrees to repair or replace vinyl windows that fail in materials or workmanship within specified warranty period.
B. Verify warranty periods for vinyl windows.
C. Warranty Period:
1. Window: 10 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Product Standard: Comply with AAMA/WDMA/CSA 101/I.S.2/A440 for definitions and minimum standards of performance, materials, components, accessories, and fabrication unless more stringent requirements are indicated.
B. Window Certification: FGIA or WDMA certified with label attached to each window.
C. Performance Class: AAMA/WDMA/CSA 101/I.S.2/A440 as follows:
1. Minimum Performance Class: LC
D. Energy Performance: Certified and labeled by manufacturer for energy performance as follows:
1. Thermal Transmittance (U-factor): As determined in accordance with NFRC 100:
a. Operable Windows: Not more than 0.3
2. Solar Heat-Gain Coefficient (SHGC): As determined in accordance with
NFRC 200.
b. Operable Windows: Not more than 0.5
E. Outdoor-Indoor Transmission Class (OITC): Rated for not less than 26 when tested for laboratory sound transmission loss in accordance with ASTM E90 and determined by
ASTM E1332.
F. Windborne-Debris Impact Resistance: Passes ASTM E1886 missile-impact and cyclic-pressure tests in accordance with ASTM E1996 for Wind Zone 2 for basic protection.
2.2 VINYL WINDOWS
A. Provide manufacturer's standard vinyl window assemblies consisting of frames, sashes, glass, hardware, fasteners, and all components and accessories as required for a complete installation.
B. Operating Types: Provide the following operating types in locations indicated on Drawings:
1. Casement: Project out.
C. Frames and Sashes: Impact-resistant, UV-stabilized PVC complying with
AAMA/WDMA/CSA 101/I.S.2/A440.
1. Finish: Integral color, white.
D. Windborne-Debris-Impact-Resistant Insulating-Glass Units: ASTM E2190, with two lites and complying with impact-resistance requirements in "Performance Requirements" Article.
E. Hardware, General: Provide manufacturer's standard hardware fabricated from aluminum, stainless steel, carbon steel complying with AAMA 907, or other corrosion-resistant material compatible with adjacent materials; designed to smoothly operate, tightly close, and securely lock windows, and sized to accommodate sash weight and dimensions.
1. Exposed Hardware Color and Finish: White
F. Projected Window Hardware:
1. Gear-Type Rotary Operators: Complying with AAMA 901 when tested in accordance with ASTM E405, Method A. Provide operators that function without requiring the removal of interior screens or using screen wickets.
2. Single-Handle Locking System: Operates positive-acting arms that pull sash into locked position. Provide one arm on sashes up to 29 inches (735 mm) tall and two arms on taller sashes.
G. Weather Stripping: Provide full-perimeter weather stripping for each operable sash unless otherwise indicated.
H. Fasteners: Noncorrosive and compatible with window members, trim, hardware, anchors, and other components.
I. Exposed Fasteners: Avoid exposed fasteners to greatest extent possible. For application of hardware, use fasteners that match finish hardware being fastened.
2.3 INSECT SCREENS
A. General: Fabricate insect screens to integrate with window frame. Provide screen for each operable exterior sash. Screen wickets are not permitted.
B. Aluminum Frames: Manufacturer's standard aluminum alloy complying with SMA 1201.
Fabricate frames with mitered or coped joints or corner extrusions, concealed fasteners, and removable PVC spline/anchor concealing edge of frame.
C. Glass-Fiber Mesh Fabric: mesh of PVC-coated, glass-fiber threads; woven and fused to form a fabric mesh resistant to corrosion, shrinkage, stretch, impact damage, and weather deterioration. Comply with ASTM D3656/D3656M.
D. Aluminum Wire Fabric: 18-by-16 (1.1-by-1.3-mm) mesh of 0.011-inch- (0.28-mm-) diameter, coated aluminum wire.
2.4 FABRICATION
A. Fabricate vinyl windows in sizes indicated. Include a complete system for installing and anchoring windows.
B. Glaze vinyl windows in the factory.
C. Weather strip each operable sash to provide weathertight installation.
D. Hardware: Mount hardware through double walls of vinyl extrusions or provide corrosion-resistant reinforcement.
E. Complete fabrication, assembly, finishing, hardware application, and other work in the factory to greatest extent possible. Disassemble components only as necessary for shipment and installation. Allow for scribing, trimming, and fitting at Project site.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine openings, substrates, structural support, anchorage, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.
B. Verify rough opening dimensions, levelness of sill plate, and operational clearances.
C. Examine wall flashings, air and weather barriers, and other built-in components to ensure weathertight window installation.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Comply with manufacturer's written instructions for installing windows, hardware, accessories, and other components. For installation procedures and requirements not addressed in manufacturer's written instructions, comply with installation requirements in ASTM E2112.
B. Install windows level, plumb, square, true to line, without distortion, anchored securely in place to structural support, and in proper relation to wall flashing and other adjacent construction to produce weathertight construction.
3.3 CLEANING AND PROTECTION
A. Clean exposed surfaces immediately after installing windows using manufacturer's written instructions. Remove excess sealants, glazing materials, dirt, and other substances.
B. Remove and replace sashes if glass has been broken, chipped, cracked, abraded, or damaged during construction period.
C. Protect window surfaces from contact with contaminating substances resulting from construction operations. If contaminating substances do contact window surfaces, remove contaminants immediately in accordance with manufacturer's written instructions.
END OF SECTION 085313
SECTION 096813 - TILE CARPETING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Carpet tile.
1.2 ACTION SUBMITTALS
A. Product data.
B. Samples: Manufacturer's standard color sheets, showing full range of available colors for each type of carpet tile.
1.3 CLOSEOUT SUBMITTALS
A. Maintenance data.
B. Warranty Information
1.4 QUALITY ASSURANCE
A. Installer Qualifications: An authorized representative who is certified by the manufacturer.
1.5 WARRANTY
A. Special Warranty for Carpet Tiles: Manufacturer agrees to repair or replace components of carpet tile installation that fail in materials or workmanship within specified warranty period.
1. Warranty Period: 10 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 CARPET TILE
A. Color: Provide COR color options with submittals for approval.
B. Size: 24 by 24 inches (610 by 610 mm)
C. Design: Commercial Use
D. Pattern: Provide COR pattern options with submittals for approval.
E. Applied Treatments:
1. Soil-Resistance Treatment
2. Antimicrobial Treatment
a. Antimicrobial Activity: Not less than 2 mm halo of inhibition for gram-positive bacteria, not less than 1 mm halo of inhibition for gram-negative bacteria, and no fungal growth, in accordance with AATCC 174.
F. Performance Characteristics:
1. Texture Appearance Retention Rating (TARR): 3.0 minimum in accordance with
ASTM D7330.
2. Critical Radiant Flux Classification: Not less than 0.45 W/sq. cm in accordance with NFPA 253.
3. Dry Breaking Strength: Not less than 100 lbf (445 N) in accordance with
ASTM D2646.
4. Tuft Bind: Not less than 5 lbf (22 N) in accordance with ASTM D1335.
5. Delamination: Not less than 3.5 lbf/in. (0.6 N/mm) in accordance with
ASTM D3936.
6. Dimensional Tolerance: Within 1/32 inch (0.8 mm) of specified size dimensions, as determined by physical measurement.
7. Noise Reduction Coefficient (NRC): minimum of 0.35 in accordance with
ASTM C423.
8. Colorfastness to Crocking: Not less than 4, wet and dry, in accordance with
AATCC 165.
9. Colorfastness to Light: Not less than 4 after 40 AFU (AATCC fading units) in accordance with AATCC 16.3 Option 3.
10. Electrostatic Propensity: Less than 3.5 kV in accordance with AATCC 134.
2.2 INSTALLATION ACCESSORIES
A. Trowelable Leveling and Patching Compounds: Latex-modified, hydraulic-cement-based formulation provided or recommended in writing by carpet tile manufacturer.
B. Adhesives: Water-resistant, mildew-resistant, nonstaining, pressure-sensitive types to suit products and subfloor conditions indicated, that comply with flammability requirements for installed carpet tile, and that are recommended in writing by carpet tile manufacturer for releasable installation.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for maximum moisture content, alkalinity range, installation tolerances, and other conditions affecting carpet tile performance.
B. Examine carpet tile for type, color, pattern, and potential defects.
C. Wood Subfloors: Verify the following:
1. Underlayment over subfloor complies with requirements specified in Section 061600 "Sheathing."
2. Underlayment surface is free of irregularities and substances that may interfere with adhesive bond or show through surface.
D. Painted Subfloors: Perform bond test recommended in writing by adhesive manufacturer. Verify the following:
1. Underlayment surface is flat, smooth, evenly planed, tightly jointed, and free of irregularities, gaps greater than 1/8 inch (3 mm) protrusions more than /32 inch (0.8 mm), and substances that may interfere with adhesive bond or show through surface.
E. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. General: Comply with CRI 104 and with carpet tile manufacturer's written installation instructions for preparing substrates.
B. Use trowelable leveling and patching compounds, in accordance with manufacturer's written instructions, to fill cracks, holes, depressions, and protrusions in substrates. Fill or level cracks, holes and depressions 1/8 inch (3 mm) wide or wider, and protrusions more than 1/32 inch (0.8 mm) unless more stringent requirements are required by manufacturer's written instructions.
C. Broom and vacuum clean substrates to be covered immediately before installing carpet tile.
3.3 INSTALLATION
A. General: Comply with CRI 104, Section 10, "Carpet Tile," and with carpet tile manufacturer's written installation instructions.
B. Installation Method: As recommended in writing by carpet tile manufacturer
C. Maintain dye-lot integrity. Do not mix dye lots in same area.
D. Maintain pile-direction patterns as recommended in writing by carpet tile manufacturer.
E. Cut and fit carpet tile to butt tightly to vertical surfaces, permanent fixtures, and built-in furniture including cabinets, pipes, outlets, edgings, thresholds, and nosings. Bind or seal cut edges as recommended in writing by carpet tile manufacturer.
F. Extend carpet tile into toe spaces, door reveals, closets, open-bottomed obstructions, removable flanges, alcoves, and similar openings.
G. Maintain reference markers, holes, and openings that are in place or marked for future cutting by repeating on carpet tile as marked on subfloor. Use nonpermanent, nonstaining marking device.
H. Install pattern parallel to walls and borders.
3.4 CLEANING AND PROTECTION
A. Perform the following operations immediately after installing carpet tile:
1. Remove excess adhesive and other surface blemishes using cleaner recommended by carpet tile manufacturer.
2. Remove yarns that protrude from carpet tile surface.
3. Vacuum carpet tile using commercial machine with face-beater element.
END OF SECTION 096813
SECTION 099113 - EXTERIOR PAINTING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Primers.
2. Finish coatings.
1.2 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Samples: For each type of topcoat product.
1.3 QUALITY ASSURANCE
A. Mockups: Apply mockups of each paint system indicated and each color and finish selected to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for materials and execution.
PART 2 - PRODUCTS
2.1 PAINT PRODUCTS, GENERAL
A. Material Compatibility:
1. Provide materials for use within each paint system that are compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer based on testing and field experience.
2. For each coat in a paint system, provide products recommended in writing by topcoat manufacturer for use in paint system and on substrate indicated.
B. Colors and finish: Color and finish match to existing, color and finish matching to be approved by COR.
2.2 PRIMERS
A. Exterior, Alkali-Resistant, Water-Based Primer: Pigmented, water-based primer formulated for use on alkaline surfaces, such as exterior plaster, vertical concrete, and masonry.
B. Exterior Wood Preservative: Solvent-based, zinc or copper napthenate, penetrating antifungal treatment for exterior wood.
C. Exterior, Latex Wood Primer: White, waterborne-emulsion primer formulated for resistance to extractive bleeding, mold, and microbials; for hiding stains; and for use on exterior wood subject to extractive bleeding.
D. Exterior, Alkyd/Oil Wood Primer: Alkyd/oil-based primer that is resistant to extractive bleeding when applied to wood substrates with less than 15 percent moisture content;
formulated for sag, mold, and microbial resistance; for hiding stains; and for use on exterior wood subject to extractive bleeding.
E. Exterior, Latex Block Filler: Water-based, pigmented, high-solids, emulsion coating formulated to bridge and fill porous surfaces of exterior concrete masonry units in preparation for specified subsequent coatings.
F. Water-Based Bonding Primer: Pigmented, water-based-emulsion primer formulated for exterior use and to promote adhesion of subsequent specified coatings.
G. Solvent-Based Bonding Primer: Pigmented, solvent-based primer formulated for exterior use and to seal substrates and promote adhesion of specified subsequent coatings.
H. Zinc-Rich, Inorganic Primer: Corrosion-resistant, inorganic-based, zinc-rich primer formulated for use on prepared steel subject to severe industrial or marine environments.
I. Surface-Tolerant Metal Primer: Corrosion-resistant, solvent-based metal primer formulated for use on structural steel and metal fabrications that have been minimally prepared.
J. Quick-Drying, Alkyd Metal Primer: Corrosion-resistant, solvent-based, modified-alkyd primer; lead and chromate free; formulated for quick-drying capabilities and for use on cleaned, exterior steel surfaces.
K. Alkyd Metal Primer: Corrosion-resistant, solvent-based, alkyd primer formulated for use on prepared ferrous metals subject to industrial and light marine environments.
L. Water-Based, Galvanized-Metal Primer: Corrosion-resistant, pigmented, acrylic primer;
formulated for use on cleaned/etched, exterior, galvanized metal to prepare it for subsequent water-based coatings.
M. Epoxy Metal Primer: Corrosion-resistant, solvent-based, two-component epoxy primer formulated for use on prepared, exterior ferrous- and galvanized-metal surfaces.
N. Vinyl Wash Primer: Two-component, vinyl butyral/phosphoric acid, wash primer formulated for use over cleaned metal surfaces and zinc-rich primers as a tie coat for subsequent corrosion-resistant primers or finish coatings.
O. Quick-Drying Aluminum Primer: Corrosion-resistant, solvent-based, alkyd or modified-alkyd primer formulated for quick-drying capabilities and for use on prepared exterior aluminum.
2.3 FINISH COATINGS
A. Exterior Latex Paint, Flat: Water-based, pigmented coating; formulated for alkali, mold, microbial, and water resistance and for use on exterior surfaces, such as portland cement plaster, concrete, and primed wood.
B. Exterior Latex Paint, Low Sheen: Water-based, pigmented coating; formulated for alkali, mold, microbial, and water resistance and for use on exterior surfaces, such as portland cement plaster, concrete, and primed wood.
C. Exterior Latex Paint, Semigloss: Water-based, pigmented emulsion coating formulated for alkali, mold, microbial, and water resistance and for use on exterior surfaces, such as masonry, portland cement plaster, and primed wood and metal.
D. Exterior Latex Paint, Gloss: Water-based, pigmented, acrylic-copolymer-emulsion coating formulated for alkali, mold, microbial, scrub, blocking (sticking of two painted surfaces), and water resistance and for use on exterior, primed, wood and metal trim, sashes, frames, and doors.
E. Exterior, High-Build Latex Paint: Water-based, high-build, pigmented, emulsion coating;
high-solids content improves filling, uniformity, and film build on concrete masonry surfaces. Formulated for abrasion, mold, microbial, and wind-driven rain resistance and for use on exterior masonry, concrete masonry unit, and concrete surfaces.
F. Textured Latex Coating, Flat: Water-based, pigmented coating that contains sand or other hard aggregate and is formulated for use on exterior masonry, concrete masonry unit, and concrete surfaces.
G. Textured Latex Coating, Low Sheen: Water-based, pigmented coating that contains sand or other hard aggregate and is formulated for use on exterior masonry, concrete masonry unit, and concrete surfaces.
H. Exterior Alkyd Enamel, Flat: Solvent-based, pigmented, alkyd enamel formulated for mold, microbial, and water resistance and for use on exterior, primed, wood and metal surfaces.
I. Exterior Alkyd Enamel, Semigloss: Solvent-based, pigmented, alkyd enamel formulated for mold, microbial, and water resistance and for use on exterior, primed, wood and metal surfaces.
J. Exterior Alkyd Enamel, Gloss: Solvent-based, pigmented, alkyd enamel formulated for mold, microbial, and water resistance and for use on exterior, primed, wood and metal surfaces.
K. Quick-Drying Alkyd Enamel, Semigloss: Solvent-based, alkyd or modified-alkyd enamel formulated for quick-drying capabilities and for use on exterior, primed, metal and dimensionally stable wood surfaces.
L. Quick-Drying Alkyd Enamel, Gloss: Solvent-based, alkyd or modified-alkyd enamel formulated for quick-drying capabilities and for use on exterior, primed, metal and dimensionally stable wood surfaces.
M. High-Build Epoxy Paint, Low Gloss: High-solids, two-component epoxy; formulated for use on exterior concrete, masonry, and primed-metal surfaces.
N. Exterior, Water-Based, Light Industrial Coating, Low Sheen: Corrosion-resistant, water-based, pigmented, emulsion coating formulated for resistance to blocking (sticking of two painted surfaces), water, alkalis, moderate abrasion, and mild chemical exposure and for use on exterior, primed, wood and metal surfaces.
O. Exterior, Water-Based, Light Industrial Coating, Semigloss: Corrosion-resistant, water-based, pigmented, emulsion coating formulated for resistance to blocking (sticking of two painted surfaces), water, alkalis, moderate abrasion, and mild chemical exposure and for use on exterior, primed, wood and metal surfaces.
P. Exterior, Water-Based, Light Industrial Coating, Gloss: Corrosion-resistant, water-based, pigmented, emulsion coating formulated for resistance to blocking (sticking of two painted surfaces), water, alkalis, moderate abrasion, and mild chemical exposure and for use on exterior, primed, wood and metal surfaces.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify suitability of substrates, including surface conditions and compatibility, with finishes and primers.
B. Proceed with coating application only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Comply with manufacturer's written instructions applicable to substrates and paint systems indicated.
B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.
C. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection.
D. Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease, and incompatible paints…