Att 03_Specifications (250626).docx
DOCX document 85 KB Posted
- Attached to
- Summit Lake Dam Repairs and Safety Improvements
- Solicitation number
- 12445525Q0063
- Issued by
-
Department of Agriculture Forest Service
About this file
These are the technical specifications for the Summit Lake Dam Repairs and Safety Improvements project, prepared by the Department of Agriculture Forest Service. The comprehensive document covers multiple technical sections including earth moving, concrete work, seeding, fencing, and general construction requirements. Key technical specifications include concrete requirements with a minimum 28-day compressive strength of 4000 psi, detailed excavation and backfill procedures using crusher run limestone aggregate, specific seeding guidelines using native seed mixes, and chain-link fencing installation standards.
The specifications provide extensive details on construction methods, including work restrictions (normal business hours of 7 a.m. to 5 p.m., Monday through Friday), safety protocols, traffic control requirements, and environmental considerations such as weed and disease prevention. Contractors must submit various documents including a construction schedule, safety plan, traffic control plan, and comply with specific requirements for equipment washing, waste disposal, and site restoration. The project emphasizes precise technical execution, environmental protection, and adherence to federal regulations throughout the construction process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Att 02_SOW (250626).docx | DOCX document | |
| Sol_12445525Q0063.pdf | ||
| Att 01_Schedule of Items (250717).docx | DOCX document | |
| Att 04_Wage Rates (250606).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summit Lake Repairs Specifications
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.01 CONTRACTOR'S USE OF SITE AND PREMISES
A. Limits on Use of Site: Limit use of Project site to Work in areas indicated in this section, and other parts of the contract documents if applicable. Do not disturb portions of Project site beyond areas in which the Work is indicated.
a. Driveways, Walkways, and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
B. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.02 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
a. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, unless otherwise indicated. No work shall be allowed on weekends or Federal holidays without the written permission of the contracting officer (CO).
1.03 PROTECTION OF PUBLIC AND PROPERTY
A. Provide and maintain temporary barricades and warning signs to control access to protect the public and construction personnel from construction hazards. Temporary barricades shall be constructed around trenches that are left open overnight.
B. Comply with Federal, State, and local laws, rules, and regulations concerning construction safety and health standards. Do not expose the public to or require any workers to work under conditions that are unsanitary, hazardous, or dangerous to health and safety.
C. Repair damage to existing public and private improvements to original condition at no additional cost to the Government. Control dust and noise to protect adjacent property from damage.
1.04 TRAFFIC CONTROL
A. A traffic control plan shall be submitted to the government for review and approval prior to mobilization. The traffic control plan shall be in compliance with the MUTCD.
B. One lane must always be open to traffic. Flaggers or an alternate MUTCD approved method to control traffic shall be in place when there is only one available lane.
C. Barricades or traffic cones shall be placed along the road where an open trench is within 50’ of the road.
D. “Road Work Ahead” signs shall be placed in advance of the work area on both sides of the work area. Plates meeting the requirements of Section 321216 shall be installed when there is an open trench crossing a roadway or road shoulder. Ensure advance warning signs for plates are in place in addition to “road work ahead” signs.
1.05 SAFETY
A. The contractor shall prepare a safety plan to protect employees and the public during the duration of the work. The plan shall be submitted as an informational submittal to the CO and COR prior to the pre-work meeting.
B. Comply with all applicable OSHA Standards.
C. Comply with all FAR clauses in this contract to include FAR 52.236-13 and other applicable clauses.
D. The safety of the contractor’s employees is the sole responsibility of the contractor.
E. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
F. If hazardous materials are encountered, do not disturb and stop work if necessary; immediately notify Contracting Officer.
1.06 CONSTRUCTION SCHEDULE
A. Submit Construction Schedule to CO and COR prior to pre-work meeting. Include planned start and finish dates for each of the exercised items from the Schedule of Items.
1.07 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
a. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
b. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
END OF SECTION 011000
SECTION 012200 - UNIT PRICES
PART 1 - GENERAL
1.01 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
B. Measurement and Payment: See schedule of items. See specifications as applicable.
C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured documented by a government official or an independent inspector.
D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
| 3.01 | SCHEDULE OF UNIT PRICES | |
| A. | See Schedule of Items |
1. Actual Quantity (AQ) – Actual quality provided and installed under the contract. Shall be measured using the units given in the Schedule of Items. Measured Quantities shall be rounded up to the nearest whole unit (ex. .3 square feet would round up to 1 square foot).
2. Lump Sum Quantity (LSQ) – 1 complete unit of work. All work described under the item in the schedule of items and work incidental to the same item shall constitute 1 complete unit of work. There shall be no increase to the quantity in the Schedule of Items for Lump Sum Quantity items.
END OF SECTION 012200
SECTION 013300 SUBMITTAL PROCEDURES
PART 1 - GENERAL
| 1.01 | SUMMARY | |
| A. | Section Includes: |
1. Submittal schedule requirements.
2. Administrative and procedural requirements for submittals.
1.02 DEFINITIONS
A. Approval: Equivalent to “No Exception Taken”.
B. Approved or Approved Equivalent: To possess the same performance qualities and characteristics and fulfill the utilitarian function without any decrease in quality, durability or longevity. For equipment/products defined by the Contractor as "equivalent", substitution requests must be submitted to Contracting Officer’s Representative for consideration and be approved by the COR in writing. Approval shall constitute “No Exception Taken” and shall not be otherwise construed.
C. "No Exception Taken" constitutes that review is for general conformance with the design concept expressed in the Contract Documents for the limited purpose of checking for conformance with information given. Any action is subject to the requirements of the Contract Documents. Contractor is responsible for the dimensions and quantity and will confirm and correlate at the job site, fabrication processes and techniques of construction, coordination of the work with that of all other trades, and the satisfactory performance of the work.
D. Action Submittals: Written and graphic information and physical samples that require CO or COR’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
E. Informational Submittals: Written and graphic information and physical samples that do not require CO or COR’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
1.03 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Contract Name and Number.
2. Date.
3. Name of Contractor.
4. Name of firm or entity that prepared submittal.
5. Names of subcontractor, manufacturer, and supplier.
6. Category and type of submittal.
7. Submittal purpose and description.
8. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
9. Drawing number and detail references, as appropriate.
10. Indication of full or partial submittal.
11. Consecutive transmittal number.
12. Submittal and transmittal distribution record.
13. Other necessary identification.
14. Remarks.
B. Options: Identify options requiring selection by Contracting Officer/COR.
C. Deviations and Additional Information: On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Contracting Officer on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal. Include the Contracting Officer on all deviation requests.
| 1.04 | SUBMITTAL PROCEDURES | |
| A. | Prepare and submit submittals required by individual Specification Sections as PDF electronic files and as indicated for samples and other physical submittals. Types of submittals are indicated in individual Specification Sections. B. | Submittals shall be transmitted via email to the COR & CO. |
C. Identify and incorporate information in each electronic submittal file as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form acceptable to Government with links enabling navigation to each item.
2. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by COR.
D. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer or COR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
E. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's and COR’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Contracting Officer or COR will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process intermediate review in same manner as initial submittal.
3. Resubmittal Review: Allow 15 days for review of each resubmittal.
4. Sequential Review: Where sequential review of submittals by Contracting Officer's consultants, Government, or other parties is indicated, allow 21 days for initial review of each submittal.
F. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Indicate date and content of previous submittal.
2. Indicate date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are approved in writing by the CO or COR (in a method acceptable to the specifications or as otherwise described by the CO).
G. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
H. Use for Construction: Retain complete copies of submittals on Project site. Use only final action or material submittals that are approved in writing by the Contracting Officer or COR.
1.05 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.
2. Clearly mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.
5. Submit Product Data in PDF electronic file.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable: a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop Drawings on sheets at least 11 by 17 inches, but no larger than 30 by 42 inches (750 by 1067 mm).
3. Submit Shop Drawings in PDF electronic file.
C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of Contracting Officers and other information specified.
D. Design Data/Product Data/Materials Submittals: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal. E. Certificates:
1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide original paper copy where a notarized signature is required.
2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.
4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents. F. Test and Research Reports:
1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information: a. Name of evaluation organization.
b. Date of evaluation.
c. Time period when report is in effect.
d. Product and manufacturers' names.
e. Description of product.
f. Test procedures and results.
g. Limitations of use.
1.06 CONTRACTOR'S REVIEW
A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with contractor approval before submitting to Contracting Officer and COR.
B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform written approval method. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
1.07 GOVERNMENT REVIEW
A. Contracting Officer’s Representative (COR) may approve technical submittals, unless otherwise indicated by the contract documents or determined in writing by the Contracting Officer (CO). COR may review each submittal instead of the CO.
B. Action Submittals: Will be reviewed and their approval status will be documented in a project submittal review XLS spreadsheet returned to the contractor. The specific material items will be included in this review document and notes for approval, disapproval, and resubmittal and any questions on items.
1. All submittals reviewed will be approved in the material review spreadsheet only. This will be returned to contactor with each submittal group reviewed.
2. No marked up copies of material cut sheets will be returned to the contractor.
C. Informational Submittals: Contracting Officer or COR will review each submittal and will not return it, or may return it if it does not comply with requirements. Contracting Officer or COR may forward each submittal to appropriate party. Contractor is responsible for compliance with contract requirements and all applicable laws and regulations regardless of whether mistakes were discovered by CO or COR review of informational submittals.
D. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from COR or Contracting Officer.
E. Incomplete submittals are unacceptable, will be considered nonresponsive, and may be returned for resubmittal without review.
F. Submittals not required by the Contract Documents may be returned by Contracting Officer or COR without action.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 013300
SECTION 017100 WEED AND DISEASE PREVENTION
PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest System lands. PART 2 - PRODUCTS 1.2 WATER A. Free of debris, organic matter, and other objectionable substances. PART 3 - EXECUTION
1.3 GENERAL
A. Notify the COR in writing at least 10 calendar days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
B. Perform all work at a location designated on the plans or other locations approved in writing. Provide the COR with an opportunity to monitor the washing and inspection. C. Government approval required prior to offloading equipment at site.
1.4 EQUIPMENT
D. Use a high pressure washing system.
E. For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
F. For work at a commercial washing facility, use an approved facility.
1.5 WASHING
G. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
1.6 INSPECTION
H. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment. Rewash the construction equipment as necessary or as directed.
END OF SECTION 017100
SECTION 017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
1.1 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged or recycled, dispose of debris, waste soil, and all waste in a legal manner off Forest Service lands.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
END OF SECTION 017419
SECTION 024119 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
1.2 FIELD CONDITIONS
A. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.
1. If suspected hazardous materials are encountered, do not disturb; immediately notify Owner.
B. Storage or sale of removed items or materials on-site is not permitted.
C. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.
D. Arrange selective demolition schedule so as not to interfere with Owner's operations.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
PART 3 - EXECUTION
| 3.1 | EXAMINATION | |
| A. | Verify that utilities have been disconnected and capped before starting selective demolition operations. | |
| 3.2 | UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS |
A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.
3.3 PROTECTION
A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.
C. Remove temporary barricades and protections where hazards no longer exist.
3.4 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated.
B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities. C. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Protect items from damage during transport and storage.
3. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by COR, items may be removed to a suitable, protected storage location during selective demolition and reinstalled in their original locations after selective demolition operations are complete.
| 3.5 | CLEANING | |
| A. | Comply with requirements specified in Section 017419 "Construction Waste Management and Disposal." |
END OF SECTION 024119
SECTION 033000 - CAST-IN-PLACE CONCRETE
| 1.01 | SUMMARY | |
| A. | Section Includes: | |
| 1. | Cast-in-place concrete, including concrete materials, mixture design, placement procedures, and finishes. B. | Related Requirements: |
1. Reference Plans, Section 312000 "Earth Moving", and all contract specifications for subgrade requirements.
2. See 033020 – “Concrete From Packaged Dry Mix For Minor Structures” for bag mix concrete.
| 1.02 | PREINSTALLATION MEETINGS | |
| A. | Preinstallation Conference: Conduct conference at project site. | |
| 1.03 | ACTION SUBMITTALS |
A. Submit Design Mixtures for COR Approval: For each concrete mixture, include the following:
1. Mixture identification.
2. Minimum 28-day compressive strength.
3. Air content.
4. Indicate amounts of mixing water to be withheld for later addition at Project site if permitted.
5. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.
B. Construction Joint Layout: Indicate proposed construction joints required to construct the structure.
| a. | Location of construction joints is subject to approval of the COR. | |
| 1.04 | QUALITY ASSURANCE | |
| A. | Ready-Mixed Concrete Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C94/C94M requirements for production facilities and equipment. | |
| 1.05 | DELIVERY, STORAGE, AND HANDLING | |
| A. | Comply with ASTM C94/C94M and ACI 301 (ACI 301M). | |
| 1.06 | FIELD CONDITIONS |
A. Cold-Weather Placement: Do not place concrete when ground or air temperature is below 50 degrees Fahrenheit. Contractor shall maintain concrete at a temperature of 50 degrees or more for 5 days following placement.
| 1.07 | CONCRETE MIXTURES | |
| A. | Normal-weight Concrete: |
1. Minimum Compressive Strength: 4000 psi at 28 days.
2. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery.
1.08 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete in accordance with ASTM C94/C94M.
B. Furnish batch ticket information.
1.09 CONCRETE PLACEMENT
A. Do not place concrete when air or ground temperature is below 50 deg F.
B. Contractor shall protect the concrete from weather related damages and is responsible for the repair of weather damages occurring during construction or the curing period.
C. Before placing concrete, verify that installation of formwork, reinforcement and any embedded items is complete and that required inspections are completed.
D. Notify COR and testing and inspection agencies 24 hours prior to commencement of concrete placement.
E. Do not add water to concrete during delivery, at Project site, or during placement unless approved by COR in writing, but not to exceed the amount indicated on the concrete delivery ticket.
1. Do not add water to concrete after adding high-range water-reducing admixtures to mixture.
F. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete is placed on concrete that has hardened enough to cause seams or planes of weakness.
1. If a section cannot be placed continuously, provide construction joints as indicated.
2. Deposit concrete to avoid segregation.
3. Deposit concrete in horizontal layers of depth not to exceed formwork design pressures and in a manner to avoid inclined construction joints.
4. Consolidate placed concrete with mechanical vibrating equipment in accordance with ACI 301 (ACI 301M).
a. Do not use vibrators to transport concrete inside forms.
b. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches (150 mm) into preceding layer.
c. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity.
d. At each insertion, limit duration of vibration to time necessary to consolidate concrete, and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.
| 1.10 | INSTALLATION OF MISCELLANEOUS CONCRETE ITEMS | |
| A. | Filling In: |
1. Fill in holes and openings left in concrete structures after Work of other trades is in place unless otherwise indicated.
2. Mix, place, and cure concrete, as specified, to blend with in-place construction.
3. Provide other miscellaneous concrete filling indicated or required to complete the Work.
END OF SECTION 033000
SECTION 033020-CONCRETE FROM PACKAGED DRY MIX FOR MINOR STRUCTURES
PART 1 - GENERAL
| 1.01 | MEASUREMENT AND PAYMENT |
| A. | There will be no separate measurement or payment for work in this Section. Concrete from packaged dry mix is considered incidental to other items of work shown in the Schedule of Items. |
PART 2 - PRODUCTS
2.01 MATERIALS
A. Concrete Dry Mix:
1. Minimum 28-day Compressive Strength: 4000 psi
2. Product: Sakrete Concrete Mix, as manufactured by US Mix Products Company, or an approved equal.
B. All reinforcement bars shall be deformed billet steel conforming to the requirement of ASTM A615, Grade 60.
C. Water: Clean and free from alkali and other deleterious materials.
PART 3 - EXECUTION
3.01 CONCRETE INSTALLATION
A. Mixing:
1. Mix dry concrete and water thoroughly according to the manufacturer.
2. Mixing Equipment: Mechanical mixer or wheel barrow.
3. Place concrete while fresh; any concrete in which initial set has begun shall be wasted.
B. CONCRETE PLACEMENT
1. Do not place concrete when air or ground temperature is below 50 deg F.
2. Contractor shall protect the concrete from weather related damages and is responsible for the repair of weather damages occurring during construction or the curing period.
3. Before placing concrete, verify that installation of formwork, reinforcement and any embedded items is complete and that required inspections are completed.
4. Notify COR and testing and inspection agencies 24 hours prior to commencement of concrete placement.
5. Do not add water to concrete during delivery, at Project site, or during placement unless approved by COR in writing, but not to exceed the amount indicated on the concrete delivery ticket.
a. Do not add water to concrete after adding high-range water-reducing admixtures to mixture.
6. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete is placed on concrete that has hardened enough to cause seams or planes of weakness.
a. If a section cannot be placed continuously, provide construction joints as indicated.
b. Deposit concrete to avoid segregation.
c. Deposit concrete in horizontal layers of depth not to exceed formwork design pressures and in a manner to avoid inclined construction joints.
d. Consolidate placed concrete with mechanical vibrating equipment in accordance with ACI 301 (ACI 301M).
i. Do not use vibrators to transport concrete inside forms.
ii. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches (150 mm) into preceding layer. iii. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity.
iv. At each insertion, limit duration of vibration to time necessary to consolidate concrete, and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.
C. INSTALLATION OF MISCELLANEOUS CONCRETE ITEMS
1. Filling In:
a. Fill in holes and openings left in concrete structures after Work of other trades is in place unless otherwise indicated.
b. Mix, place, and cure concrete, as specified, to blend with in-place construction.
c. Provide other miscellaneous concrete filling indicated or required to complete the Work.
D. Finishing: Apply medium trowel finish to exposed concrete surfaces.
E. Protection From Cold: Keep the air temperature surrounding the fresh concrete above 50ºF for a period of five days after the concrete is placed.
F. Curing: If determined necessary by the COR, cover exposed surfaces with plastic sheeting after the concrete has taken its initial set.
END OF SECTION 033020
SECTION 312000 - EARTH MOVING
PART 1 - GENERAL
1.1 FIELD CONDITIONS
A. Utility Locator Service: Notify West Virginia 811 for area where Project is located at least 4 business days before beginning earth-moving operations.
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations.
B. Subbase Material: ¾” Crusher Run Limestone Aggregate.
C. Base Course: ¾” Crusher Run Limestone Aggregate.
D. Engineered Fill: ¾” Crusher Run Limestone Aggregate.
E. Bedding Course: Clean AASHTO 8s.
F. Drainage Course: Clean AASHTO 57s.
2.2 ACCESSORIES
A. Detectable Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, a minimum of 6 inches wide and 4 mils thick, continuously inscribed with a description of the utility, with metallic core encased in a protective jacket for corrosion protection, detectable by metal detector when tape is buried up to 30 inches deep; colored to comply with local practice or requirements of authorities having jurisdiction.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth-moving operations.
B. Protect and maintain erosion and sedimentation controls during earth-moving operations.
C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials.
3.2 EXCAVATION, GENERAL
A. Unclassified Excavation: Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.
| 3.3 | EXCAVATION FOR WALKS AND PAVEMENTS | |
| A. | Excavate surfaces under walks and pavements to indicated lines, cross sections, elevations, and subgrades. |
3.4 EXCAVATION FOR UTILITY TRENCHES
A. Excavate trenches to indicated gradients, lines, depths, and elevations.
B. Excavate trenches to uniform widths to provide the following clearance on each side of pipe or conduit.
1. Clearance: As indicated in the plans.
C. Trench Bottoms: Excavate and shape trench bottoms to provide uniform bearing and support of pipes and conduit. Shape subgrade to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits. Remove projecting stones and sharp objects along trench subgrade.
1. Excavate trenches as shown in the plans.
3.5 SUBGRADE INSPECTION
A. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by COR, without additional compensation.
3.6 UNAUTHORIZED EXCAVATION
A. Fill unauthorized excavation under foundations or wall footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation. Lean concrete fill, with 28-day compressive strength of 4000 psi, may be used when approved by COR.
| 1. | Fill unauthorized excavations under other construction, pipe, or conduit as directed by COR. | |
| 3.7 | STORAGE OF SOIL MATERIALS |
A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
1. Stockpile soil materials away from edge of excavations.
3.8 BACKFILL
A. Place and compact backfill in excavations promptly, but not before completing the following:
1. Construction below finish grade.
2. Testing and inspecting underground utilities.
3. Removing concrete formwork.
4. Removing trash and debris.
5. Removing temporary shoring, bracing, and sheeting.
B. Place backfill on subgrades free of mud, frost, snow, or ice.
3.9 UTILITY TRENCH BACKFILL
A. Place backfill on subgrades free of mud, frost, snow, or ice.
B. Place backfill in accordance with plans. Backfill top 6 inches with topsoil recovered from the excavation. Heap loose topsoil slightly higher than the trench prior to seeding and mulching.
C. Place and compact bedding course on trench bottoms and where indicated. Shape bedding course to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits.
D. Warning Tape: Install metallic warning tape directly above utilities, 12 inches below finished grade, except 6 inches below subgrade under pavements and slabs.
3.10 COMPACTION OF SOIL BACKFILLS AND FILLS
A. Place backfill and fill soil materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment and not more than 4 inches in loose depth for material compacted by hand-operated tampers.
B. Compact soil materials to not less than the following percentages of maximum dry unit weight.
1. Under walkways, scarify and recompact top 6 inches below subgrade and compact each layer of backfill or fill soil material at 90 percent.
2. Under turf or unpaved areas, scarify and recompact top 6 inches below subgrade and compact each layer of backfill or fill soil material at 85 percent.
3. For general utility trenches, compact each layer of backfill soil material at 85 percent.
4. For utility trenches under roadways (and utility patches), compact all backfill material in 6” loose lifts to 95 percent of the standard proctor per ASTM D698. Provide compaction testing documentation with at least 2 tests per layer.
| 3.11 | GRADING | |
| A. | General: Uniformly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated. |
3.12 SUBBASE AND BASE COURSES UNDER PAVEMENTS AND WALKS
A. Place backfill on subgrades free of mud, frost, snow, or ice.
B. On prepared subgrade, place subbase course and base course under pavements and walks as follows:
1. Place material that exceeds 6 inches in compacted thickness in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick.
2. Compact material at optimum moisture content to required grades, lines, cross sections, and thickness to not less than 95 percent of maximum dry unit weight.
3.13 DRAINAGE COURSE UNDER CONCRETE SLABS-ON-GRADE
A. Place drainage course on subgrades free of mud, frost, snow, or ice.
B. On prepared subgrade, place and compact drainage course under cast-in-place concrete slabs- on-grade as follows:
1. Place drainage course that exceeds 6 inches in compacted thickness in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick.
2. Compact each layer of drainage course to required cross sections and thicknesses to not less than 95 percent of maximum dry unit weight.
3.14 FIELD QUALITY CONTROL
A. Testing Agency: Owner reserves the right to engage a qualified testing agency to perform tests and inspections.
B. Allow testing agency to inspect and test subgrades and each fill or backfill layer if applicable. Government may reject work found to not comply with contract requirements.
3.15 PROTECTION
A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris.
B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.
C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing.
Summit Lake Dam Repairs and Safey Improvements Specifications
| 2 |
| 2 |
Page | 2
1. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible.
| 3.16 | DISPOSAL OF SURPLUS AND WASTE MATERIALS | |
| A. | Remove surplus satisfactory soil and waste materials, including unsatisfactory soil, trash, and debris, and legally dispose of them off Forest Service property. |
END OF SECTION 312000
SECTION 329000 SEEDING AND MULCHING
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes seeding, mulching, and fertilizing.
B. The areas to be seeded and mulched shall be all areas disturbed by contract operations, and as otherwise indicated.
1.2 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Product certificates.
1.3 QUALITY ASSURANCE
A. Installer's Field Supervision: Require Installer to maintain an experienced full-time supervisor on Project site when planting is in progress.
1.4 DELIVERY, STORAGE, AND HANDLING
A. Seed, Fertilizer: Deliver, store, and handle materials according to manufacturer’s recommendations. Materials must be kept dry until ready to use.
1.5 METHOD OF MEASUREMENT
A. Seeding and Mulching is incidental to the project work unless otherwise specified.
PART 2 – PRODUCTS
2.1 PLANTING MATERIALS
A. Topsoil Source: Reuse surface soil on-site or import where not available on site. Topsoil source must be approved by COR. B. Seed Mix:
1. Spring & Fall Planting:
Roundstone Native Seed - Mix 208 - Southern Quick Erosion Control Cover Mix Or COR Approved Equivalent
2. Summer Planting:
Roundstone Native Seed - Mix 209 - Southern Quick Erosion Control Cover Mix Or COR Approved Equivalent C. Mulches:
1. Straw Mulch: Provide air-dry, clean, mildew- and weed-free, threshed straw of wheat, rye, oats, or barley.
| 33 PART 3 – EXECUTION | |
| 3.1 | PREPARATION |
A. Finish Grading: Grade planting areas to a smooth, uniform surface plane with loose, uniformly fine texture. Grade to within plus or minus 1/2 inch of finish elevation.
Roll and rake, remove ridges, and fill depressions to meet finish grades. Limit fine grading to areas that can be planted in the immediate future.
B. Restore areas if eroded or otherwise disturbed after finish grading and before planting.
3.2 SEEDING
A. Sow seed at the rate of 15lb/acre. Apply Fertilizer at rate required by contract documents, if required by contract documents.
B. Rake seed lightly into top 1/8 inch of topsoil, roll lightly, and water with fine spray.
C. Protect seeded areas by spreading straw mulch. Spread uniformly at a minimum rate of 2 tons/acre to form a continuous blanket 1-1/2 inches in loose depth over seeded areas. Spread by hand, blower, or other suitable equipment. Straw mat netting shall be installed according to manufacturer’s recommendations. D. Hydro-seeding using the above seeding rates is also acceptable method of seeding.
E. Seeding shall be completed between April 1-June 1 for spring plantings and Sept.1- October 15 for fall planting.
F. Temporary seeding during winter months may be required and shall consist of winter wheat at 30lb/acre and straw mulch at one ton per acre.
END OF SECTION 329000
SECTION 02821
CHAIN-LINK FENCES AND GATES
PART 1 - GENERAL
This Section includes the following:
[Galvanized steel] [Zn-5-Al-MM alloy-coated steel] [PVC-coated steel] chain-link fabric.
[Galvanized steel] [Polymer-coated steel] framework.
Gate operator.
See Division 16 Sections for electrical service and connections for motor operators, controls, limit switches, and other powered devices and for system disconnect switches.
SUBMITTALS
Product Data: For each product indicated.
Shop Drawings: Show locations, components, materials, dimensions, sizes, weights, finishes of components, installation and operational clearances, gate swings, and details of post anchorage and attachment and bracing.
Samples: For [PVC-coated steel wire for fabric] [polymer coating on framing and accessories].
Maintenance Data: For [polymer finishes] [gate operator].
QUALITY ASSURANCE
PART 2 - PRODUCTS
2-1/8 inches (54mm) for residential use 2 inches (50 mm) or less for commercial or industrial use 1-3/4 inches (44 mm) for tennis courts 1 inch (25 mm) or less for higher-security installations Common wire sizes and uses range from the following:
0.113 or 0.120 inch (2.87 or 3.05mm) or more in diameter for residential use
0.148 inch (3.76mm) or more in diameter for commercial and light industrial use
0.192 inch (4.88 mm) or more in diameter for heavy industrial use and higher-security installation.
CHAIN-LINK FENCE FABRIC
Steel Chain-Link Fence Fabric: Comply with Chain Link Fence Manufacturers Institute's "Product Manual."
Mesh and Wire Size: [1-inch (25-mm) mesh, 0.148-inch (3.76-mm) diameter] [1-inch (25-mm) mesh, 0.120-inch (3.05-mm) diameter] [1-3/4-inch (44-mm) mesh, 0.120-inch (3.05-mm) diameter] [2-inch (50-mm) mesh, 0.120-inch (3.05-mm) diameter] [2-inch (50-mm) mesh, 0.192-inch (4.88-mm) diameter] [2-inch (50-mm) mesh, 0.148-inch (3.76-mm) diameter] [Color as indicated] <Insert requirements>.
Zinc-Coated Fabric: ASTM A 392, with zinc coating applied to steel wire mesh fabric after weaving with Class 1, 1.2-oz./sq. ft. (366-g/sq. m) minimum coating weight.
Zn-5-Al-MM Alloy-Coated Fabric: ASTM F 1345 with Class 1, 0.60-oz./sq. ft. (183-g/sq. m) minimum coating weight.
PVC-Coated Fabric: ASTM F 668, Class [1] [2a] [2b] over metallic-coated steel wire. Color as selected from manufacturer's full range complying with ASTM F 934.
Fabric Selvage: [Knuckled at both selvages] [Twisted at top selvage and knuckled at bottom].
RESIDENTIAL FENCE AND GATE FRAMING
Round Posts and Rail: ASTM F 761.
Fence Height: [4 feet (1.22 m) high or less] [More than 4 feet (1.22 m) high and not exceeding 6 feet (1.83 m) high] [As indicated].
Line, End, Corner, and Pull Posts and Top Rail: As required for [Light-Duty] [Medium-Duty] [Heavy-Duty] fence.
Gate Posts, Gates, and Accessories: Comply with ASTM F 654, gate type as indicated, made from [galvanized steel] [aluminum] metal pipe and tubing for individual gate widths [48 inches (1.219 m) or less] [more than 48 inches (1.219 m) and not exceeding 84 inches (2.134 m)], complete with hardware.
Protective Coating for Steel: Posts, rails, and frames protected with an external coating of not less than 0.6 oz. of zinc/sq. ft. (183 g of zinc/sq. m), a chromate conversion coating, and a clear, verifiable polymer film; and an internal protective coating of not less than 0.6 oz. of zinc/sq. ft. (183 g of zinc/sq. m) or 81 percent, not less than 0.3-mil- (0.0076-mm-) thick, zinc pigmented coating.
INDUSTRIAL FENCE FRAMING
Round Steel Pipe: Standard weight, Schedule 40, galvanized steel pipe complying with ASTM F 1083. ASTM F 1043, Material Design Group IA, external and internal coating Type A, consisting of not less than 1.8-oz./sq. ft. (0.55-kg/sq. m) zinc; and line, end, corner, and pull posts and top rail as required for [Heavy] [Light] Industrial Fence.
Round Aluminum Pipe: ASTM F 1043, Material Design Group IB, and line, end, corner, and pull posts and top rail as required for Heavy Industrial Fence.
Round Steel Pipe: Cold-formed, electric-resistance-welded steel pipe. ASTM F 1043, Material Design Group IC, with external and internal coatings; and line, end, corner, and pull posts and top rail as required for [Heavy] [Light] Industrial Fence.
Post Brace Rails: Match top rail for coating and strength and stiffness requirements. Provide brace rail with truss rod assembly for each gate, end, and pull post. Provide two brace rails extending in opposing directions, each with truss rod assembly, for each corner post and for pull posts. Provide rail ends and clamps for attaching rails to posts.
Top Rails: With swedged-end or fabricated for expansion-type coupling.
Intermediate Rails: Match top rail for coating and strength and stiffness requirements.
Bottom Rails: Match top rail for coating and strength and stiffness requirements.
GATES
Swing Gates: Comply with ASTM F 900 for [single] [double] gates, made from pipe and tubing complying with ASTM F 1043, complete with hardware.
Frames and Bracing: For gate fabric height [6 feet (1.83 m) or less]…