Att_02-_Specifications.pdf

PDF 565 KB Posted

Attached to
RE-ROOFING OF MULTIPLE BUILDINGS Federal contract opportunity
Solicitation number
140P8421R0010
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This federal solicitation seeks competitive proposals for a roof replacement project at multiple historic buildings within Channel Islands National Park in Ventura County, California. The National Park Service requires removal and replacement of the clay tile roofs on five structures at the Anacapa Light Station located on Anacapa Island. The contractor will provide all labor, materials, equipment, supervision and services necessary to complete new tile roofing matching the original appearance of the buildings. The project range is estimated between $500,000 to $1 million. The North American Industry Classification System code is 238160 for roofing contractors with an annual revenue size standard of $16.5 million. This is a total small business set-aside requiring offers only from small businesses. Proposals are due by the scheduled closing date listed in the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to RE-ROOFING OF MULTIPLE BUILDINGS, newest first.
File Type Posted
Sol_140P8421R0010_Amd_0003.pdf PDF
Att_09-_Updated_Specifications_0002.pdf PDF
Att_10-_Questions_and_Answers_0002.pdf PDF
Sol_140P8421R0010_Amd_0002.pdf PDF
Attachment_08-_Figures_1_thru_9_0001.pdf PDF
Sol_140P8421R0010_Amd_0001.pdf PDF
Att_03-_Wage_Determination.pdf PDF
Att_01-_Contract_Price_Schedule.pdf PDF
Sol_140P8421R0010.pdf PDF
Att_06-_PP_Questionnaire.pdf PDF
Att_07-_Standard_Form-24_Bid_Bond.pdf PDF
Att_05-_Key_Personnel_Form.pdf PDF
Att_04-_Technical_Information_Form.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A N A C A P A L I G H T S T A T I O N C H A N N E L I S L A N D S N A T I O N A L P A R K

REROOFING OF FIVE BUILDINGS

Solicitation #: 140P8421R0010

Attachment 02

Specifications

NATIONAL PARK SERVICE

REGIONS 8, 9 10 AND 12

Page Intentionally Blank

MAY 2021 TABLE OF CONTENTS

A N A C A P A L I G H T S T A T I O N C H A N N E L I S L A N D S N A T I O N A L P A R K

REROOFING OF FIVE BUILDINGS

PMIS 266688

SCOPE OF WORK

TABLE OF CONTENTS

Area and Vicinity Maps ................................................................. 2 pages

Section 01 10 00 – General Requirements .................................. 26 pages

Section 07 31 30 – Clay Tile Roofing Replacement ................... 20 pages

LIST OF FIGURES

Figure 1: Aerial View of Anacapa Island

Figure 2: Detail A - Aerial View of Fog Signal Building

Figure 3: Detail B - Aerial View of Light Station

Figure 4: Photo of Keepers Residence - 2019

Figure 5: Photo of General Service Building (Visitor Center) - 2019

Figure 6: Photo of Powerhouse (Maintenance Shop) - 2019

Figure 7: Photo of Tank House – 2019

Figure 8: Photo of Fog Signal Building - 2019

Figure 9: Drawing of Original Gutter Detail

MAY 2021 TABLE OF CONTENTS

Page Intentionally Blank

ANACAPA LIGHT STATION REROOFING PMIS #266688A

CHANNEL ISLANDS NATIONAL PARK

01 10 00 - Page 5 of 50

MAY 2021 GENERAL REQUIREMENTS

SECTION 01 10 00 – GENERAL REQUIREMENTS

PART 1 – GENERAL

1.1 CONTENTS

A. PART 1 sets forth general administrative and procedural requirements for the accomplishment of the Work of this contract and includes the following:

1.1 Contents

1.2 Project Information

1.3 Summary of Work

1.4 Contract Price Schedule Contract Line Item Definition

1.5 Special Factors Applicable to Contract

1.6 Project Safety

1.7 Site Examination and Field Verification

1.8 Definitions

1.9 Contractors Quality Control

1.10 Codes and Reference Standards

1.11 Permits

1.12 Contractor’s Use of Premise and Temporary Facilities

1.13 Hot Work

1.14 Hazardous Materials

B. See PART 1 of individual technical specification sections of this SOW for additional general requirements specific to the work of that section.

C. See PART II of this section for Product Requirements, including, but not limited to product and materials submittal requirements.

D. See PART III of this section for Execution Requirements, construction submittal requirements.

1.2 PROJECT INFORMATION

A. Project Authority: The United States Government, Department of the Interior, National Park Service is the Owner of this property and is referred to throughout the Contract Documents as “the Government”. Representatives of the Government are as follows and lines of communication and responsibilities will be further clarified at a Preconstruction Conference following Contract Award and prior to Notice to Proceed:

1. Contracting Officer (CO) is the official Government Representative and Authority for the Project. The CO will be assigned by the Government and made known to the Contractor at the time of Award or before;

2. The CO will designate a Contracting Officer’s Representative (COR) to assist with the day to day operations of the Contract. The COR will be made known to the Contractor at the time of the Preconstruction Conference or before;

3. Contractor shall not take direction from any Government Representative other than the CO or the COR;

4. Only the CO can change any contract requirement. If a contract requirement is changed by the CO, is will be done in writing.

01 10 00 - Page 6 of 50

MAY 2021 GENERAL REQUIREMENTS

B. Project Address/Location: Anacapa Light Station Historic District, Anacapa Island, Channel Islands National Park, California.

C. Offers: Provide offers/price proposals on form provided by the Government as outlined below.

D. All Work will be performed under a single prime base contract.

E. Work shall not commence until written Notice to Proceed is issued by the Government.

1.3 SUMMARY OF WORK

A. The Contractor shall provide all labor, materials, equipment and services necessary to complete the Work as specified herein and as indicated on the figures/drawings included herein; and as required by referenced and industry standards, applicable codes and existing field conditions.

B. Summary of Work: The following brief summary of the work is for the convenience of the Contractor. All work required by the contract shall be performed by the Contractor, whether listed below or not.

1. Removal and replacement of existing clay tile roofing at five (5) historic buildings at the Anacapa Light Station in the Anacapa Island Historic District on Anacapa Island at Channel Islands National Park. Reroofed structures shall be weather tight and shall match the original appearance of the buildings. The following buildings shall be reroofed:

a. Keepers Residence;

b. General Service Building (Visitor Center);

c. Power House (Maintenance Shop);

d. Tank House;

e. Fog Signal Building.

C. Estimated Quantities: Certain portions of the Work of this SOW are inaccessible and/or concealed and the Government will not know the full extent of that work until those areas are exposed in the course of the Work. Estimated Quantities of this work are included in this SOW for pricing purposes.

1. See individual technical sections of the SOW for estimated quantities.

2. Contractor shall provide proof of actual quantities of work completed in a manner acceptable to the Government;

3. Variation in Quantities:

a. If actual quantities significantly exceed the quantities estimated herein, the Contractor may seek a Contract Modification for additional payment as allowed under the Contract;

b. If quantities are significantly less than the quantities estimated herein, the Government may seek a Contract Modification for a credit as allowed under the Contract.

1.4 CONTRACT PRICE SCHEDULE - CONTRACT LINE ITEM DEFINITION

A. A Contract Price Schedule will be provided by the Government as part of the Solicitation for this acquisition. Complete and submit the Contract Price Schedule as required by the Solicitation.

01 10 00 - Page 7 of 50

MAY 2021 GENERAL REQUIREMENTS

B. Lump Sum Pricing: Lump Sum pricing shall reflect the total price for direct costs including all required labor and supervision, materials, products, tools, equipment, plant, transportation, services, incidentals and contractor’s mark-ups including general conditions, overhead and profit; bonding, required permits, etc. as required to complete that portion of the Work as indicated on the drawings, as specified herein and as required by field conditions and applicable regulatory requirements.

C. Item Numbers on the Contract Price Schedule are shown as follows:

1. CLIN 01 – BASE PRICE: Provide Lumps Sum price for all of the Work of this contract, except for work described in CLIN 02 -OPTION 1. The BASE PRICE shall be based on Government provided housing on the island (see Article 1.5.F below regarding requirements). CLIN 01 shall be broken down by sub-CLIN’s 01A through 01E. The sum of sub-CLIN’s 1A through 1E is the BASE PRICE and shall be shown on the CLIN 01 line of the Contract Price Schedule.

a. CLIN 01A: Provide a Lump Sum price to complete the demolition of all existing roofing as specified;

b. CLIN 01B: Provide a Lump Sum price to complete all carpentry repairs as specified;

c. CLIN 01C: Provide a Lump Sum price to complete the installation of new roof systems as specified;

d. CLIN 01D: Provide a Lump Sum price to complete the installation of new sheet metal and flashing as specified;

e. CLIN 01E: Provide a Lump Sum price to complete stucco repairs and painting as specified.

2. CLIN 02 - OPTION 1: All costs associated with setting up, maintaining and breaking down a construction camp on Anacortes Island as specified.

1.5 SPECIAL FACTORS APPLICABLE TO CONTRACT

A. Historic Nature of Work Site: Contractor shall note the historical significance of the site and buildings at which the Work will be performed. The Work of this contract will take place within a nationally designated Historic District.

1. Due to the historic nature of the site and buildings, certain aspects of the Work may not be carried out with the materials and/or methods commonplace in the modern construction industry.

a. It is incumbent upon the Contractor to furnish mechanics who can and will execute first-class workmanship in the materials and methods specified, and who will take the necessary precautions to protect the elements of the historic buildings and site not scheduled for Work under this contract;

2. Cultural and Natural Resources, including the built structures, natural features of the landscape and subsurface archeological resources are present and shall be protected throughout the course of the Work;

3. The Contractor shall provide a written Historic Preservation Quality Assurance (HPQA) Plan addressing the following:

a. How Cultural Resources not scheduled for Work under this contract will be protected from disturbance and/or damage throughout the course of the Work;

b. How roofs will be accessed without damage to existing, historic features of the buildings and site not scheduled for Work;

c. How buildings will be protected from water intrusion and damage throughout the course of the work.

d. How finished roofs will be protected from bird droppings until Final Acceptance.

01 10 00 - Page 8 of 50

MAY 2021 GENERAL REQUIREMENTS

B. Natural Resources to be Protected:

1. Vegetation adjacent to Buildings: Contractor shall make every effort to protect all vegetation on the site and surrounding the buildings. Locate equipment and materials storage as directed by the Government. The HPQA shall specifically address protection of vegetation.

2. Gull Nesting Season: Anacapa Island hosts the largest protected breeding colony of western gulls in the world with over 10,000 gulls gathering during nesting season from May through July.

C. Biosecurity: NPS requires the conformance to specific procedures to protect the unique flora and fauna of the Channel Islands. Contractor shall strictly comply with the following:

1. Footwear, clothing, and personal packs must be inspected and cleaned prior to leaving the mainland. Footwear cleaning can be done with the boot brushes provided at the NPS boatyard dock. Laces, shoelace holes, socks, pant cuffs, zippers, and all small crevices on clothing and packs can be hiding small insects or weed seeds. All insects and seeds must be removed before leaving the mainland.

a. It may be necessary to inspect and clean footwear, clothing, and personal packs while on island, when moving between sensitive sites. Requirements will be made known to the Contractor.

2. Single-use plastic bags and corrugated cardboard packing is not permitted, unless the cardboard is factory-sealed and has not been opened prior to transport to the island(s).

Tightly sealed containers, such as Action Packers, are an acceptable alternative.

a. All contracting and sub-contracting personnel must provide trash can with a secure-fitting lid at on-site work area(s) and construction camps. The purpose of the secure lid is to keep out wildlife, including ravens and foxes.

b. Feeding of wildlife, including ravens and foxes, is not permitted at any time.

3. Single-use plastic water bottles are not permitted. All personnel must bring reusable water bottles and Igloo (or alternative brand) beverage coolers for refilling.

4. Equipment and Machinery: Prior to transport to the island, the Contractor shall be responsible for ensuring that their equipment is clean and free of dirt, mud, straw, or other material which could bring weed seeds or other invasive species to the island.

a. The Contracting Officer shall be notified a minimum of 72 hours prior to entry of vehicles and or equipment to the Park.

b. All vehicles and equipment (including shovels, wheelbarrows, hand tools, etc.)

entering the project area must be clean of plant seeds, mud, and soil and free from oil leaks. Pressure wash all construction equipment and heavy machinery to thoroughly remove all dirt, plant, and other foreign material prior to loading equipment on park boats or landing craft. Particular attention must be shown to the under carriage, wheels, tracks, and any other surface where soil containing non-native plant seeds or aquatic organisms such as the New Zealand mud snail or zebra mussel may reside.

c. Arrange for the Contracting Officer’s Representative (COR) to inspect each piece of equipment, or alert the Biosecurity Manager to do so, before loading on the mainland. Equipment that has not been adequately cleaned will be turned away.

Equipment found operating on the project that has not been inspected or has oil leaks will be shut down and subject to citation and removal from the premises.

d. Any equipment leaving the park shall be power washed and steam cleaned again prior to each reentry to the park.

01 10 00 - Page 9 of 50

MAY 2021 GENERAL REQUIREMENTS

5. Decontamination of Equipment: These efforts are critical to prevent the introduction and establishment of non-native plant or animal species into the project area.

a. Drain and flush all pumps, tanks, live wells, buckets and other containers that might carry water contaminated with exotic animals, such as the New Zealand mud snail or zebra mussel, prior to bringing equipment into the park.

Thoroughly wash all hauling tanks and equipment using a hard spray from a garden hose. If equipment was used in infested waters, use the following steps to clean the equipment:

b. Wash with hot water (140 F or 40 C) or a high-pressure washer (250 pounds per square inch).

c. Remove all aquatic weeds -- they can carry non-native snails and mussels.

6. Disinfect Equipment: Recent research shows that disinfection of nets and equipment with benzalkonium chloride at typical treatment rates (10 milligrams per liter for 24 hours, 100 milligrams per liter for 3 hours, or 250 milligrams per liter for 15 minutes) will effectively eliminate most exotic animals. Two other commonly used disinfectants, calcium hypochlorite and iodine, are ineffective against zebra mussels.

a. Many adult snails and mussels can live more than a week out of water in moist, shaded areas. Dry pumps, nets and other equipment used in infested waters in the sun for two to four days after cleaning. If adult snails or mussels are present, equipment must be dried for two weeks.

b. No imported earth materials will be allowed without the written permission of the Government.

c. All material must be free of animals and/or animal evidence, including, but not limited to: rodents/small mammals, rodent/small mammal droppings, chew marks, insects, spider webs, insect holes in boxes.

D. Occupied Site: The Government and the public may occupy the site throughout the Contract Period:

1. Cooperate with Government during construction operations to minimize conflicts with day-to-day operations and facilitate Government usage.

2. The Park will remain open to the public throughout the Contract Period. Park hours are

7 am 5:00 p.m., unless otherwise noted.

3. Contractor shall at all times conduct his operations to ensure the safety of and least inconvenience to the Government and the public.

E. Weather Protection: Throughout the duration of the Work the Contractor shall be fully responsible for maintaining the weather-tightness of all portions of the roofs of each building.

1. Contractor or his authorized representative shall be available on four (4) hours’ notice, twenty-four hours a day for the duration of this contract, to repair and prevent any and all leaks related to the Work.

a. Contractor shall furnish the Government with the name (s) and personal telephone number(s) of person(s) that will respond in the event of an emergency.

2. Damage by water intrusion to any interior features and/or contents of the building(s) shall be restored/replaced as approved by the Government, at no additional cost to the Government.

E. Fire Protection: These are important historic building on a historic site, and shall be protected against fire throughout the performance of the Work.

1. Provide fire extinguishers, of appropriate type, at each building throughout course of

Work.

01 10 00 - Page 10 of 50

MAY 2021 GENERAL REQUIREMENTS

2. See PART 1 article in this section regarding “Hot Work”;

F. Other Factors Affecting the Contract:

1. Access to Project Site: The Project Site is located on the topside of Anacapa Island, which is approximately nine (9) mile offshore from mainland California and twelve

(12) miles from the nearest port in Oxnard:

a. Materials can be delivered to Anacapa wharf by boat or barge.

i. Materials can be lifted from the watercraft to the wharf using the Government’s Lower Crane, which has a maximum capacity of 3,000 (three thousand) pounds.

ii. Materials can be lifted from the wharf to the topside of island with the Government’s Upper Crane, which has maximum capacity of 9,000 (nine thousand) pounds.

iii. The use of Government cranes is allowed at Contractor’s own risk and subject to meeting all Government safety requirements.

b. At Contractor’s option, materials may be delivered to the island by helicopter at no additional cost to the Government beyond the Contract Amount.

2. Concurrent Construction Contracts: From approximately October 2021 through April 2022, Channel Islands National Park will be conducting dock repairs on Anacortes Island. It is anticipated that this contract and that contract will run concurrently.

a. Accommodations will be made for watercraft landing and off-loading of materials using Government cranes.

3. Housing - BASE PRICE: The Government may provide housing for Contractor’s personnel on the island. If that is the case:

a. Housing is limited to a maximum of four (4) people with shared bathrooms at the time of this writing due to the pandemic.

b. Housing limitations may change as pandemic restrictions are eased, allowing for a maximum of eight (8) people in shared rooms.

i. Contractor shall be fully responsible for maintaining and cleaning park housing throughout use.

ii. Housing will be inspected prior to Final Acceptance for cleanliness and/or any damage. If housing is not in the same condition it was in before Contractor’s occupation, it shall be cleaned/repaired to original condition at no additional cost to the Government.

4. Construction Camp - OPTION 1: If government housing is not available, Contractor shall be responsible for setting up, maintaining and breaking down a construction camp on the island.

a. The Construction Camp will be in the proximity of the work and shall be located as directed by the Government.

b. Contractor shall be fully responsible for maintaining and cleaning the

Construction Camp and surrounding area throughout use.

c. After breakdown the Construction Camp area shall be cleaned and returned to its original condition. The area will be inspected prior to Final Acceptance for cleanliness and/or any damage. If the area is not in the same condition it was in before Contractor’s occupation, it shall be cleaned/restored to original condition at no additional cost to the Government.

5. Food Service: There are no food services or stores on Anacapa Island.

a. All food to be used by Contractor’s personnel and subcontractors shall be brought to the island by the Contractor.

b. There is potable water on the island, that will be made available to the

Contractor.

01 10 00 - Page 11 of 50

MAY 2021 GENERAL REQUIREMENTS

6. Medical Facilities: There are no medical facilities or trained medical staff on Anacapa Island.

a. In case of serious injury helicopter removal would be necessary, at the

Contractor’s expense.

7. Information about Anacapa Island is available at www.nps.gov/chis.

1.6 PROJECT SAFETY

A. Contractor shall ensure the safety of all Contractor personnel, Government personnel, and the public within and adjacent to the work areas at all times throughout the course of the Work.

B. All work, personnel, tools and equipment at the Project Site shall comply with all applicable Occupational Health and Safety Act (OSHA) requirements and other governing regulations, including those of any federal, state and local bodies having jurisdiction.

C. Contractor Personnel Safety:

1. All personnel shall be physically qualified and able to perform their assigned duties in a safe manner;

2. Contractor shall ensure that personnel whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves, others or the historic features of the site to injury and/or damage shall not perform Work;

3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully trained and capable of operating such equipment.

a. Provide operating instructions for all equipment on site.

D. Reportable Accidents: A project reportable accident is defined as death, occupational disease and/or traumatic injury to Contractor personnel, Government employees or the public, fires, and/or property damage in excess of $100.

1. Notify Government immediately in the event of a Reportable Accident;

2. Within seven (7) days of a Reportable Accident, fill out and forward to

Government an Accident/Property Damage Report (Form CM-22).

a. Form may be obtained from the Government.

E. Emergencies: Report any accidents, injuries, or other emergencies to NPS Sequoia/Kings Canyon Dispatch 559-565-4221.

1.7 SITE EXAMINATION AND FIELD VERIFICATION

A. Site Examination Prior to Submitting an Offer: Prospective Offerers and Subcontractors are strongly encouraged to visit and examine the existing conditions of the Project prior to submission of an offer for this Solicitation.

1. The purpose of the Site Examination is for prospective offerors to better understand the

Work required, the existing conditions of the site and aid in forming any questions the Contractor may have prior to the submission of offer.

2. Failure to visit the site shall not alleviate Contractors’ responsibility to provide an accurate proposal to accomplish the Work specified in the contract.

3. Solicitation Documents will clarify Site Examination logistics.

01 10 00 - Page 12 of 50

MAY 2021 GENERAL REQUIREMENTS

B. Field Verification Following Award of Contract: The Contractor shall verify all existing conditions and new and existing dimensions prior to the commencement of Work and/or ordering of products and materials:

1. Discrepancies between existing conditions and the Contract Documents shall be brought to the Government’s attention in writing for clarification prior to the commencement of work.

a. Any work performed prior to receiving clarification from the Government, particularly work that may require correction, shall be corrected by the Contractor with no additional cost to the Government.

1.8 DEFINITIONS

A. Contract Documents:

1. The documents forming the basis of the contract include, but may not be limited to the following:

a. Applicable clauses of the Federal Acquisition Regulations (FAR);

b. Solicitation Documents;

c. The Government Contract;

d. General and Supplemental Clauses of the Contract;

e. The Scope of Work (SOW) – General Conditions, Technical Specifications and

Figures/Drawings specific to the Work of this contract:

2. In case of a discrepancy between any contract requirements, the matter shall be promptly submitted to the Government for resolution.

a. Any work performed prior to receiving clarification from the Government, particularly work that may require correction, shall be corrected by the Contractor with no additional cost to the Government.

B. Contractor: The company or individual that holds the Contract for the Work with the Government:

1. Contractor is used throughout these documents to mean the Contractor and all applicable personnel and subcontractors performing the Work;

2. When Work is defined herein, even without the words “Contractor shall” attached to it;

the Work is the responsibility of the Contractor.

C. Contract Period: The time period designated in the Contract, in calendar days, during which the Work of the Contract shall be performed. The Contract Period runs from the date of Notice to Proceed through the date of Final Acceptance of the project, unless otherwise noted.

D. Days: Days, when used herein, refers to calendar days, unless otherwise noted.

E. Execution Related Definitions:

1. Historic Materials: Materials used in the original construction, or subsequent rehabilitation and/or restoration of a structure, which have been deemed historical by the Government.

a. Contractor shall not replace historic materials without Government direction to do so.

2. Replace to Match Existing and/or In-Kind: If historical materials and/or items are too deteriorated to perform their original function, the Contract Documents may call for these materials to be replaced to match existing and/or in kind.

01 10 00 - Page 13 of 50

MAY 2021 GENERAL REQUIREMENTS

a. This shall mean that the new item/material shall match the existing in type and/or species of material; size; profile; visual characteristics e.g. texture, color etc.; and function;

b. The Government has the right to review and approve all “match existing and/or in kind” materials. The final determination of “match/in kind” will be made by the Government.

3. Remove and Salvage: Existing and historical materials and/or items that are removed due to possible impact from the Work, or as requested by the Government; and are then conveyed to the Government as stipulated by the Contract Documents.

4. Remove and Reinstall: Existing and historical materials and/or items that are removed due to possible impact from the Work, stored, protected and maintained by the Contractor, unless otherwise noted, throughout the course of the Work and reinstalled to their original location and function within the appropriate sequence of the Work.

F. Project Site: The defined physical limits within the Park for the Work.

1. The Government will define the project site at the Preconstruction Conference.

G. Provide: The purchase, supply and installation of all materials, products, equipment, systems and the like required by the Contract for the completion of the Work.

H. Work shall mean all Work required by the Contract.

1. When Work is defined herein, even without the words “Contractor shall” attached to it;

that Work is the responsibility of the Contractor.

1.9 CONTRACTOR’S QUALITY CONTROL

A. The Contractor shall be responsible for Quality Control (QC) and ensuring that the Work is performed in a good workmanlike manner and meets all requirements of the Contract.

1. Ensure all personnel and subcontractors receive all pertinent information and perform the Work in compliance with the contract requirements;

2. Coordinate all construction operations as required to complete the Work;

3. Inspect all Work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable contract requirements:

a. Promptly correct any deficient item(s), feature(s) or materials of the Work identified by the Contractor and/or the Government.

B. Quality Control Supervisor: Contractor shall assign experienced, senior staff members to monitor and ensure quality control throughout the Contract Period, and shall designate, and make known to the Government the individual(s) assigned as the Quality Control Supervisor.

Any of the following may act as Quality Control Personnel:

1. Project Manager: The Contractor shall designate a single individual to represent the project and interface with the Government for the duration of the project.

a. The Project Manager may also perform the role of On-site Superintendent and/or Quality Control Supervisor for the Work.

b. Submit evidence of Project Manager’s qualifications and experience as required by PART 3 Article “Construction Submittal Requirements” herein.

01 10 00 - Page 14 of 50

MAY 2021 GENERAL REQUIREMENTS

c. Once approved by the Government, the Project Manager shall not be changed without approval of the Government.

2. On-Site Superintendent: The Contractor shall designate an experienced individual to represent the Contractor on site for the duration of the project.

a. The Superintendent may also perform the role of Project Manager and/or

Quality Control Supervisor for the Work;

b. The designated Superintendent shall be on site at all times that the Work is underway to ensure safety, coordination, quality control and continuity.

c. Submit evidence of Superintendent’s qualifications and experience as required by PART 3 Article “Construction Submittal Requirements” herein.

d. Once approved by the Government, the Superintendent shall not be changed without approval of the Government.

C. Contractor’s Quality Control (CQC) Plan:

1. The Contractor shall provide a written Contractor Quality Control (CQC) Plan to the

Government for approval prior to mobilization:

a. The Government reserves the right to require changes in the plan prior to approval;

b. The Government reserves the right to require changes in the plan during the

Contract Period as required to ensure the specified quality of Work;

c. Following approval, no change in the CQC Plan may be made by the Contractor without written concurrence by the Government.

2. At a minimum the CQC plan shall include, but may not be limited to, the following:

a. A list of personnel responsible for QC and their assigned duties;

b. Methods of performing, documenting, and enforcing QC of all Work;

c. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

D. Contractor's Quality Control Daily Reports (CQCR): Contractor shall submit CRCR daily:

1. At a minimum CQCR shall include the following:

a. Daily weather conditions;

b. Personnel and subcontractors on site each day;

c. Tasks undertaken and/or completed each day;

d. Off-site fabrication (where applicable);

e. Inspections;

f. Testing.

2. Use form acceptable to the Government;

3. Include a minimum of five (5) photos of each day’s work with each CQCR. See PART

3 Article “Photo Documentation” herein for further requirements.

E. Off-Site Fabrications CQC Reporting: Items that are fabricated or assembled off-site shall be inspected by the Contractor for quality control at the place of fabrication.

1. Submit an Off-site CQC report, in a form approved by the Government, following each inspection. Submit a final Off-Site Inspection Report prior to shipment.

F. If the CQC Plan and CQCR’s are not submitted as specified herein, the Government may retain all or a portion of payments until such time as a plan is accepted and implemented and/or all outstanding CQCR are received.

01 10 00 - Page 15 of 50

MAY 2021 GENERAL REQUIREMENTS

G. Progress Meetings: Contractor shall meet with the Government on a regular basis, at times mutually agreed upon by the Contractor and the Government, to review the progress of the Work.

1. It is assumed the meetings will be conducted as conference calls.

a. The Contractor shall arrange conference lines for use for these meetings.

2. Contractor shall prepare and distribute meeting minutes from each meeting, within five

(5) days of the meeting date.

1.10 CODES AND REFERENCE STANDARDS

A. Prevailing Code: The work shall comply with the requirements of the International Building Code (IBC), all applicable volumes, divisions and sections, latest adopted edition and including all state and local amendments, unless otherwise noted.

1. Other pertinent codes and regulation adopted by the jurisdiction(s) having authority may apply:

2. The Contractor’s is responsible for verifying all applicable codes.

C. Comply with all applicable industry standards:

1. Comply with general standards applicable to each trade and industry standards noted in individual Technical specification sections of this SOW.

D. In order for the Government to fulfill its mission regarding protection of natural and cultural resources, the Government may direct the Contractor not to follow prevailing codes and industry standards if doing so would have a detrimental effect on the resource.

1. All such direction from the government will be given in writing.

1.11 PERMITS

A. City and County Building Permits are not required for projects on Federal Government-owned property.

B. Other Permits: Contractor shall verify any and all other permits applicable to the Work of this Contract required by all jurisdiction(s) having authority. Contractor shall obtain and pay for all Other Permits.

1.12 CONTRACTOR'S USE OF PREMISES

A. Contractor shall have limited use of areas within the Light Station for performance of the Work.

B. Existing Public Ways: Maintain public ways serving premises including entrances, driveways, pathways, pedestrian areas, sidewalks, parking areas and loading areas.

1. These areas shall be kept clear and available to the Government, park visitors and emergency vehicles at all times, unless otherwise agreed to in advance by the Government.

2. Do not use these areas for staging, parking of vehicles or equipment, or storage of materials without prior Government approval.

C. Emergencies: Report any accidents, injuries, or other emergencies to NPS Sequoia/Kings Canyon Dispatch 559-565-4221.

01 10 00 - Page 16 of 50

MAY 2021 GENERAL REQUIREMENTS

D. Work Hour Restrictions: On-site work and/or deliveries will be seven (7) days a week during daylight hours, unless otherwise approved by the Government.

E. Prohibited Items: The following items are prohibited:

1. Firearms / weapons / ammunition;

2. Alcohol and Illicit Drugs;

3. Pets.

F. Smoking Policy: Smoking is prohibited inside buildings and all outside areas except for designated smoking areas.

1. The only designated smoking area on Anacapa Island is the concrete landing at the top of the stairway from the dock.

G Confine storage of materials to areas designated by Government.

1. Storage areas will be in the general area of the buildings where Work will be performed and will be clarified at the Preconstruction Conference.

H. Protection of Adjacent Features:

1. Throughout all Phases of the Work, confine all operations to Project Site limits and protect adjacent historic and natural features not scheduled to be impacted by the Work.

2. In the event that damage occurs, Contractor shall restore damaged areas, repairing or replacing damaged features to their original condition, at no additional expense to the Government.

I. Existing Utilities:

1. Disturbance of Existing Utilities: Notify Government and utility companies (here applicable) of any proposed disturbances to existing utilities.

2. Contractor shall be responsible for verifying location of and preventing damage to known utilities.

a. If damage to a known utility occurs, Contractor shall repair utility at no additional cost to the Government.

b. If damage to an unknown utility occurs, Contractor shall promptly repair utility and an equitable adjustment will be made in accordance with applicable Contract requirements.

c. Interruption of Existing Utility Service: Interruption of utility service will only be permitted with prior consent of the Government.

i. Maximum Duration: Four (4) hours, unless otherwise approved by the

Government.

ii. Notify Government not less than two (2) days in advance of proposed utility interruptions.

iii. Do not proceed with utility interruptions prior to receiving Government’s approval.

3. Water: Potable water is available on the island. Contractor may use reasonable amounts of water at no charge.

4. Electric Power Service: There is existing electrical power at the Project Site.

a. Use of existing electric power will be permitted, as long as equipment is maintained in a condition acceptable to the NPS.

b. Contractor may access existing building power with extension cords rated for the equipment being powered;

c. When temporary connections are removed, restore existing utility services to their original condition;

01 10 00 - Page 17 of 50

MAY 2021 GENERAL REQUIREMENTS

d. Lighting: Where applicable, provide temporary lighting with adequate illumination for construction operations, observations, inspections, and traffic conditions.

e. Fire protection: Contractor shall take all precautions necessary to ensure that provisions for electrical service do not constitute a fire hazard to the site or buildings.

5. Telephone Service:

1. No landline telephone service is available on site for Contractor's use.

2. Limited cell phone connectivity is available on Anacapa Island.

J. Lifts and Hoists:

1. If lifts, hoists or other heavy equipment are used, protect all cultural and natural resources from damage.

K. Vehicle Restrictions: Vehicles, except those owned by the Government, are not allowed on Anacapa Island without prior, written approval of the Government.

L. Environmental Protection: Provide environmental protection as required by applicable local, state and federal laws, codes and standards.

1. The Contractor shall not dispose of volatile or unstable waste or oils in storm or sanitary drains nor allow such materials to reach natural bodies of water.

2. The Contractor shall take all necessary and reasonable measures to reduce air pollution by any materials or equipment used in the Work.

M. Waste Disposal Facilities: The Contractor is fully responsible for containing all waste generated by the Work, removing all waste from the Project Site and the park, and disposing of it in a legal manner outside of the park.

1. The location of waste and trash container(s) larger than one cubic yard shall be proposed by the Contractor for review and approval by the Government.

a. No containers shall be delivered to the site until their location is approved by the

Government.

2. No Government waste containers shall be used for collection or disposal of construction waste and/or trash resulting from the Work and/or Contractor’s personnel.

3. No burning will be allowed within park boundaries.

N. Temporary Facilities:

1. Temporary materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

2. Locate temporary facilities as directed by Government.

3. If necessary, relocate and modify facilities as required by progress of the Work and as approved by Government.

3. Support Facilities:

a. Field Office: At Contractor’s option a small, temporary Field Office / Storage Container may be placed on site.

i. Locate field office as directed by the Government;

b. Toilets Facilities: Contractor may use toilet facilities in park housing throughout the course of the work.

i. Toilet facilities shall be kept neat and clean at all times;

01 10 00 - Page 18 of 50

MAY 2021 GENERAL REQUIREMENTS

ii. Toilet facilities will be inspected prior to Final Acceptance for cleanliness and/or damage. If not clean or damaged, Contractor shall restore toilet facilities to the condition they were in prior to occupancy, at no additional cost to the Government.

4. Maintenance: Maintain temporary facilities in clean, good operating condition until removal.

5. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion.

a. Repair Work damaged by temporary facilities, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired;

b. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility;

c. Materials and facilities that constitute temporary facilities are property of

Contractor and shall be completely removed from the Project Site and park prior to Substantial Completion.

O. Signage:

1. Signage identifying the Contractor or any subcontractor performing the Work is not allowed within the park.

2. Provide temporary, directional signs for construction personnel, Government personnel and visitors as required to safely perform the Work.

1.13 HOT WORK

A. In the event Hot Work must be performed to accomplish the Work, the Contractor shall obtain a Hot Work Permit from the Government.

1. Hot Work shall only be performed in “designated” and/or “permit-required” areas.

2. A Hot Work Permit is required for Work in a “designated” area.

3. A Hot Work Permit is required for Work in a “permit-required” area.

a. The Contractor shall obtained a signed Hot Work Permit, issued by the Park Structural Fire Coordinator or his/her designee, for Work performed in a “permit-required” area.

b. A separate permit will be required for each Hot Work event.

c. Apply for Hot Work Permits a minimum of seventy-two (72) hours prior to the hot work event.

B. Definitions:

1. Designated Area: An area specifically designated for, or approved by the Park

Structural Fire Coordinator or his/her designee, for Hot Work.

a. A designated area can be a maintenance shop or a detached outside location that is of noncombustible or fire-resistive construction, essentially free of combustible and flammable contents, and suitably segregated from adjacent areas. All designated areas shall have been inspected and approved by the Park Structural Fire Coordinator or his/her designee.

2. Permit-Required Area: A permit-required area shall be an area that is made fire safe and authorized by the issuance of a signed NPS Hot Work Permit.

3. Non-permissible Areas: Hot work shall not be allowed in the following areas:

a. Areas not authorized by the Park Structural Fire Coordinator or his/her designee;

01 10 00 - Page 19 of 50

MAY 2021 GENERAL REQUIREMENTS

b. Sprinklered buildings while such protection is impaired;

c. Areas with explosive atmospheres (that is, where mixtures of flammable gases, vapors, liquids, or dusts with air exist);

d. Areas with explosive atmospheres that can develop inside unclean or improperly prepared drums, tanks, or other containers and equipment that have previously contained such materials;

e. Areas with explosive atmospheres that can develop in areas with an accumulation of combustible dusts.

1.14 HAZARDOUS MATERIALS

A. The buildings have not been surveyed for hazardous materials including lead, asbestos and/or PCB’s.

1. Due to the age of the buildings it is assumed that the under layers of paint contain lead.

a. It is not the Government’s intention to abate lead-based paint under this contract.

b. Contractor is fully responsible for the safety of all Contractor’s personnel, Government personnel and the public when Work impacts lead-based paint;

c. Lead-based paint waste shall be disposed of in a legal manner meeting all federal, state and local regulations and laws;

d. Waste shall be disposed of outside of the park.

2. In the event that the Contractor should encounter substances, other than lead-based paint, that are suspected of being hazardous materials that will be impacted by the performance of the Work, stop work in that area and notify the Government immediately for resolution of the issue.

a. Work shall continue in areas not impacted by suspected hazardous materials.

B. There are many birds on Anacapa Island and a significant amount of bird guano (droppings) on structures included in the Work. The Contractor shall take all precautions required by local, state and federal laws and regulations and as necessary to protect workers against contamination and exposure to pathogens that could be released while performing the Work.

1. Contractor shall be responsible for disposing of demolition materials contaminated with bird droppings in a legal manner meeting all federal, state and local regulations and laws.

a. Waste shall be disposed of outside of the park.

PART 2 PRODUCTS

2.1 CONTENTS

A. PART 2 sets forth administrative and procedural requirements for selection of products and their use in the Work, as well as product submittals, delivery, storage, handling and warranties on products and includes the following:

2.1 Contents

2.2 General Requirements

2.3 Product Definitions

2.4 Product Selection Procedures

2.5 Product Submittal Requirements

2.6 Product Delivery, Handling and Storage

2.7 Product Warranties

01 10 00 - Page 20 of 50

MAY 2021 GENERAL REQUIREMENTS

B. See PART 2 of individual specifications sections of this SOW for Product Requirements for the Work of that section.

2.2 GENERAL REQUIREMENTS

A. Contractor shall provide new products for incorporation into the Work, unless otherwise directed or authorized by the Government.

B. Contractor shall comply with the "Buy American Act - Subpart 25.2 Construction Materials", unless otherwise authorized by the Government.

C. Environmentally Preferable Products

1. To the greatest extent possible, provide products and materials that have a lesser or reduced effect on the environment considering raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, and/or disposal of the product.

2. Use of environmentally preferred products shall not override this contract’s requirements to match historic construction and appearance.

3. Packaging: Contractor is encouraged to obtain materials in biodegradable or recyclable/reusable packaging and, where practicable, to use the minimum amount of packaging possible.

a. Where Contractor has the option to provide one of the listed products or equal, preference shall be given to products with minimal and/or easily recyclable packaging as defined in ASTM D5834.

2.3 DEFINITIONS

A. Products: Items provided for incorporation into the Work by the Contractor, whether purchased specifically for the Work or taken from previously purchased stock.

1. The term "product" includes and applies to the terms "material," "equipment,"

"system," and all terms of similar intent.

B. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise.

1. Products salvaged or recycled from other projects are not considered New

Products.

2. All New Products shall be incorporated into the work within applicable expiration dates.

C. Salient Characteristics: The characteristics for a specified product are listed in the individual sections of this SOW to establish significant qualities related to type, function, sizes and/or dimension, in-service performance, physical properties, appearance, and other characteristics required by the Contract. Salient Characteristics shall be used for purposes of evaluating comparable products of diverse manufacturers required by the Government.

01 10 00 - Page 21 of 50

MAY 2021 GENERAL REQUIREMENTS

D. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's current, published product literature.

E. Comparable Product: An alternative to a named product specified in individual sections of this SOW that meets the salient characteristics specified and is demonstrated and approved through the submittal process as meeting those requirements.

F. Compatibility of Options: If Contractor is given options of selecting between two or more products for use in the Work, product selected shall be compatible with products previously selected, even if previously selected products were also options.

1. Contractor shall be responsible for verifying compatibility.

G. As Selected: Where specified products are accompanied by the term "as selected", Government will make selection.

H. Match Sample: Where specified products are accompanied by the term "match sample", sample to be matched will be provided by the Government and final approval of “match” will be made by the Government.

I. Match Existing: Where specified products are accompanied by the term "match existing", this shall mean match material, composition, size, color, texture, profile and all other functional and sensual features.

1. The government will identify existing materials to be matched;

2. Approval of “match” will be made by the Government.

2.4 PRODUCT SELECTION PROCEDURES

A. Provide products that comply with the requirements of this SOW, which are undamaged and, unless otherwise indicated, new at time of installation.

B. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation for indicated use and effect.

C. Protect all products provided from damage until final acceptance by the Government.

D. Standard Products: If available, provide standard products of types that have been produced and used successfully in similar situations on other projects, unless custom products or nonstandard options are specified.

D. Government reserves the right to limit selection of products to those with warranties that meet the requirements of the contract.

E. The intent of this SOW is to convey the salient characteristics and properties of all products / materials to be used in the Work.

01 10 00 - Page 22 of 50

MAY 2021 GENERAL REQUIREMENTS

1. Salient Characteristics: Where products / materials are described by their salient characteristics in the technical specification sections of this SOW, contractor shall provide products / materials that meet the salient characteristics specified.

2. Named Product: Where a product / material is cited by manufacturer, product name and/or product number it is for clarification purposes only in order to delineate the minimum requirements based on the salient characteristics of the product and/or material, which will also be provided in the product description in the requirement.

a. Contractor may use the named product; or

b. Contractor may use another product that has the salient characteristics specified, with Government approval.

3. Basis of Design: Where a Named Product is used to set the Basis for Design

Contractor may use the Basis for Design Product named, or a comparable product meeting the salient characteristics for the Basis for Design Product with Government approval.

4. Comparable Products: Contractor may propose a Comparable Product under any of the selection criteria listed above and meeting the following requirements:

a. The Contractor shall bear the responsibility for demonstrating to the

Government that proposed Comparable Products are comparable to those specified;