Atch 8 San Luis Valley HQ Complex Bid Schedule.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- CO-SAN LUIS VALLEY COMPLEX HQ OFC BLDG Federal contract opportunity
- Solicitation number
- 140F0620R0025
About this file
This document includes a bidding schedule and line item cost breakdown for the construction of the San Luis Valley Complex HQ and Visitor Center building project. The scope of work involves constructing a 4,221 square foot facility to serve as the new headquarters for the Alamosa National Wildlife Refuge and other Fish and Wildlife Service functions in the area. Specific work includes a parking lot, access road, water well system, propane and dumpster enclosures, septic system, and exterior electrical work. The cost breakdown separates costs into line items for site work, substructure, superstructure, exterior closure, interior construction, mechanical, electrical, equipment, and identified lines of accounting for the entrance road, parking lot, building, and well. General conditions, overhead and profit are included as percentage based line items. The total project cost is estimated between $1 million to $5 million. The solicitation will be offered as a total small business set-aside with the contracting agency being the Department of the Interior Fish and Wildlife Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch 9 FWS San Luis-Alamosa Welcome Center-HQ - Geotechnical Report_0002.pdf | ||
| Sol_140F0620R0025_Amd_0002.pdf | ||
| Sol_140F0620R0025_Amd_0001.pdf | ||
| Atch 1 San Luis-Alamosa HQ Specifications.pdf | ||
| Atch 2 San Luis-Alamosa HQ Plans.pdf | ||
| Atch 5 san Luis-Alamosa HQ Submittal Schedule.pdf | ||
| Atch 4 San Luis-Alamosa HQ Finish Board.pdf | ||
| Atch 7 San Luis Valley Alamosa HQ Past Perf Quest.doc | DOC document | |
| Sol_140F0620R0025.pdf | ||
| Atch 3 San Luis-Alamosa HQ REV 1 Replacement Pages Plans.pdf | ||
| Atch 6 San Luis Valley Alamosa HQ DBA Wage Det.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| PROJECT DESCRIPTION: |
| The scope of this project is to construct the new San Luis Valley Complex HQ Building at Alamosa NWildlife Refuge. Work will include construction of: Parking Lot/Sidewalks, Access Road, new domestic Water Supply Well system to include the enclosure, Liquid Propane and Garbage Dumpster enclosures, mounded Leach field/Septic system, and Exterior Electrical power supply system. |
| A. GENERAL CONDITIONS: | |||||
| Mobilization and demobilization | $ | ||||
| Bond | $ | ||||
| Total | $ | - 0 |
B. SUMMARY OF COST BREAKDOWN FOR MATERIALS, LABOR AND EQUIPMENT
| 01 Site Work | ||||
| Site Preparation & Earthwork | $ | |||
| Site Improvements exterior to building | $ | |||
| Site Mechanical (septic, water well, propane) | $ | |||
| Site Electrical | $ | |||
| Total | $ | - 0 |
| 02 - Substructure | ||||
| Foundation | $ | |||
| Slab on Grade | $ | |||
| Total | $ | - 0 |
| 03 - Superstructure | ||||
| Roof Construction | $ | |||
| Roofing System | $ | |||
| Total | $ | - 0 |
| 04 - Exterior Closure | ||||
| Exterior Walls | $ | |||
| Exterior Doors & Windows | $ | |||
| Total | $ | - 0 |
| 06 - Interior Construction | ||||
| Partitions and Doors | $ | |||
| Interior Finishes | $ | |||
| Specialties | $ | |||
| Total | $ | - 0 |
| 08 - Mechanical | ||||
| Interior Plumbing | $ | |||
| HVAC | $ | |||
| Special Systems (radon, RO, arsenic filter) | $ | |||
| Total | $ | - 0 |
| 09 - Electical | ||||
| Service and Distribution | $ | |||
| Lighting and Power | $ | |||
| Special Sys. (fire alarm/data/telecom/security) | $ | |||
| Total | $ | - 0 |
| 10 - Equipment | ||||
| Fixed & Movable Equipment | $ | |||
| Furnishings | $ | |||
| Total | $ | - 0 |
BASE TOTAL $ - 0
OVERHEAD AND PROFIT (percentage) % $ - 0
BASE TOTAL PLUS OVERHEAD AND PROFIT $ - 0
| LINE OF ACCOUNTING BREAKDOWN: |
| Contractor to translate cost breakdown from above into identified Lines of Accounting. Loaded costs to include General Conditions and Overhead & Profit. Spreadsheet lines 63 above and 80 below totals should match. |
| LINES OF ACCOUNTING | ||
| 010 HQ Entrance Road | $ |
| 020 HQ Parking Lot | $ |
| 030 HQ Building | $ |
| 040 HQ Well | $ |
TOTAL PLUS GENERAL RQMTS & OVERHEAD AND PROFIT $ - 0
&"Times New Roman,Regular"&12BIDDING SCHEDULE
San Luis Valley Complex HQ Building (20-017)
Alamosa NWR
Alamosa, CO