This document includes a bidding schedule and line item cost breakdown for the construction of the San Luis Valley Complex HQ and Visitor Center building project. The scope of work involves constructing a 4,221 square foot facility to serve as the new headquarters for the Alamosa National Wildlife Refuge and other Fish and Wildlife Service functions in the area. Specific work includes a parking lot, access road, water well system, propane and dumpster enclosures, septic system, and exterior electrical work. The cost breakdown separates costs into line items for site work, substructure, superstructure, exterior closure, interior construction, mechanical, electrical, equipment, and identified lines of accounting for the entrance road, parking lot, building, and well. General conditions, overhead and profit are included as percentage based line items. The total project cost is estimated between $1 million to $5 million. The solicitation will be offered as a total small business set-aside with the contracting agency being the Department of the Interior Fish and Wildlife Service.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

PROJECT DESCRIPTION:
The scope of this project is to construct the new San Luis Valley Complex HQ Building at Alamosa NWildlife Refuge. Work will include construction of: Parking Lot/Sidewalks, Access Road, new domestic Water Supply Well system to include the enclosure, Liquid Propane and Garbage Dumpster enclosures, mounded Leach field/Septic system, and Exterior Electrical power supply system.
A. GENERAL CONDITIONS:
Mobilization and demobilization$
Bond$
Total$- 0

B. SUMMARY OF COST BREAKDOWN FOR MATERIALS, LABOR AND EQUIPMENT

01 Site Work
Site Preparation & Earthwork$
Site Improvements exterior to building$
Site Mechanical (septic, water well, propane)$
Site Electrical$
Total$- 0
02 - Substructure
Foundation$
Slab on Grade$
Total$- 0
03 - Superstructure
Roof Construction$
Roofing System$
Total$- 0
04 - Exterior Closure
Exterior Walls$
Exterior Doors & Windows$
Total$- 0
06 - Interior Construction
Partitions and Doors$
Interior Finishes$
Specialties$
Total$- 0
08 - Mechanical
Interior Plumbing$
HVAC$
Special Systems (radon, RO, arsenic filter)$
Total$- 0
09 - Electical
Service and Distribution$
Lighting and Power$
Special Sys. (fire alarm/data/telecom/security)$
Total$- 0
10 - Equipment
Fixed & Movable Equipment$
Furnishings$
Total$- 0

BASE TOTAL $ - 0

OVERHEAD AND PROFIT (percentage) % $ - 0

BASE TOTAL PLUS OVERHEAD AND PROFIT $ - 0

LINE OF ACCOUNTING BREAKDOWN:
Contractor to translate cost breakdown from above into identified Lines of Accounting. Loaded costs to include General Conditions and Overhead & Profit. Spreadsheet lines 63 above and 80 below totals should match.
LINES OF ACCOUNTING
010 HQ Entrance Road$
020 HQ Parking Lot$
030 HQ Building$
040 HQ Well$

TOTAL PLUS GENERAL RQMTS & OVERHEAD AND PROFIT $ - 0