This document contains a submittal list and project details for the Houghton Dam demolition project at Sand Lake National Wildlife Refuge. The project will remove a 110-foot long service spillway and excavate a trapezoidal channel through the dam at elevation 1282.5, install rip-rap along the excavation slopes and crest, and install a new 20 foot wide guardrail on the dam crest. Submittals will include schedules of values, subcontractor lists, construction schedules, erosion control and waste management plans, and progress photos. The related federal contract opportunity is solicitation number 140F0121R0033 issued by the U.S. Fish and Wildlife Service for the removal of Houghton Dam at Sand Lake National Wildlife Refuge.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHEET 1 OF 3
PROJECT NAME: Houghton Dam Demo - Construction ENGR. PROJECT NO.: 21-045
LOCATION: Sand Lake NWR CONTRACT NO.:
CONTRACTOR: TBD
Spec.
Section
Number
Spec.
Paragraph
No. Comments
012900 1.2.A.1
013100 1.3
013200 1.2 / 1.4
013233 1.2
013300 1.3
013500 1.2
015000 1.3
017419 1.3
017419 1.4
017700 1.3
022100 1.5
310500 1.3
014100 1.3
015200 1.2
015700 1.2
024100 1.4
312500 1.2
Construction Facilities - Site Layout Plan
Temporary Controls
Waste Records
Errosion and Sedimentaiton Controls
Waste records
Site survey confirming limits of excavation
Material source and properties (Riprap)
Permit Submittals
Closeout documents
PROJECTED SUBMITTAL LIST
Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)
Schedule of Values
Subcontract list and information
Construction schedule
Safety Procedures
Erosion control plan
Waste management plan
Digital photos
Submittal schedule
A - Approved as Submitted.
B - Approved, Except as Noted. No Resubmission Required.
C - Approved, Except as Noted. Resubmission Required.
D - No Action Taken. See Comments. Resubmission Required.
E - disapproved. See Comments. Resubmission Required.
SHEET 2 OF 3
LOCATION: Sand Lake NWR CONTRACT NO.:
CONTRACTOR: TBD
Spec.
Section
Number
Spec.
Paragraph
No. Comments
PROJECTED SUBMITTAL LIST
Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)
Schedule of Values
A - Approved as Submitted.
B - Approved, Except as Noted. No Resubmission Required.
C - Approved, Except as Noted. Resubmission Required.
SHEET 3 OF 3
LOCATION: Sand Lake NWR CONTRACT NO.:
CONTRACTOR: TBD
Spec.
Section
Number
Spec.
Paragraph
No. Comments
PROJECTED SUBMITTAL LIST
Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)
Schedule of Values
A - Approved as Submitted.
B - Approved, Except as Noted. No Resubmission Required.
C - Approved, Except as Noted. Resubmission Required.
File details come from the government source that posted it. Updated .