This is a Performance Work Statement (PWS) for the replacement and installation of integrated physical security and life safety systems at Washita Battlefield National Historic Site in Cheyenne, Oklahoma.
The National Park Service seeks a qualified contractor to provide complete design, equipment, installation, testing, training, and documentation for four integrated systems: (1) a non-proprietary, code-compliant fire alarm system designed by a licensed Fire Protection Engineer, NICET Level III Fire Alarm Systems Technician, or Fire Code Official-approved individual, compliant with NFPA 72, IFC 2024, and IBC 2024; (2) a non-proprietary intrusion alarm system with specified components including one control panel, two keypads, 16 wall-mounted motion detectors, five ceiling-mounted motion detectors, two glass break devices, six door contacts, three siren alarms, and three silent panic buttons; (3) a modern non-proprietary CCTV system with Milestone-compatible, NDAA-compliant Axis Communications cameras capable of supporting up to 20 cameras, with approximately nine indoor and six outdoor cameras installed, a network video recorder with minimum seven-day storage capability, and two dedicated 22-24" viewing monitors at staffed desks; and (4) a non-proprietary electronic door access control system for four doors with prox card readers, card encoding capability, and a standalone workstation supporting up to 50 users with local-only administration. All systems must operate on a physically and logically isolated network separate from the NPS-DOI internal network and comply with DOI/NPS security, privacy, and records management requirements. Work must occur between 8:00 AM and 4:30 PM Monday through Friday while maintaining daily Visitor Center operations. The contractor is responsible for site survey and verification, obtaining permits, coordinating with NPS IT and Regional Fire Marshal, protecting park visitors and property, providing all necessary equipment including a man lift for 30-foot ceiling access, maintaining a clean worksite, complete testing and commissioning per NFPA 72 standards, on-site training for NPS personnel, one-year warranties on equipment and labor with 48-hour service response for non-emergency issues, and removal and disposal of all existing and new system debris in compliance with federal, state, and local requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P1226Q0018_Amd_0003.pdf | ||
| Atch_11_Questions_and_Answers_0003.docx | DOCX document | |
| Sol_140P1226Q0018_Amd_0002.pdf | ||
| Atch_10_FAR_Clause_52_222-90_0002.docx | DOCX document | |
| Sol_140P1226Q0018_Amd_0001.pdf | ||
| Atch_8_WABA_VC_Drawings_0001.pdf | ||
| Atch_5_Questions_and_Answers_0001.docx | DOCX document | |
| Atch_9_Motion_and_Glass_Zones_0001.pdf | ||
| Atch_6_Washita_Battlefield_Center_FA_Inspection_-_8_25_25-Redacted_0001.pdf | ||
| Atch_7_Site_Visit_Sign_In_0001.pdf | ||
| Atch_4_DOL_WD_2015-5327__Rev_29.pdf | ||
| Atch_2_Technical-Experience_Questionnaire.xls | XLS spreadsheet | |
| Sol_140P1226Q0018.pdf | ||
| Atch_3_Price_Schedule.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Washita Battlefield National Historic Site
Cheyenne, Oklahoma
Performance Work Statement (PWS)
Fire Alarm System Replacement, Intrusion Alarm System Replacement, CCTV System Replacement, and Installation of a Door Access Control System
P a g e | 2
1. Background
Washita Battlefield National Historic Site (WABA) operates a combined Visitor Center and Administrative Building that contains the park’s public interface, staff offices, collections storage areas, and critical infrastructure. The existing fire alarm system, intrusion alarm system, and closed-circuit television (CCTV) surveillance system are outdated, no longer meet current standards, and require replacement. Additionally, the site requires installation of a new electronic door access control system to ensure controlled access to building entrances.
The National Park Service (NPS) seeks a qualified contractor to provide design, equipment, installation, testing, training, and documentation for integrated physical security and life safety systems. All work shall comply with NPS, DOI, NFPA, and applicable codes.
2. Scope
The contractor shall furnish all labor, equipment, materials, testing instruments, software, programming, and services necessary to:
1. Replace the existing fire alarm system with a code-compliant, fully functional system that is non-proprietary.
2. Replace the existing intrusion alarm system with a fully operational system that is non-proprietary.
3. Replace the existing CCTV surveillance system with a modern digital system that is non-proprietary, including indoor/outdoor fixed cameras and a network video recorder (NVR) capable of retaining a minimum of 7 days of footage.
4. Provide and install a door access control system that is non-proprietary, with four controlled doors, appropriate card readers, card encoding capability, a standalone workstation with access control software, and training.
5. Ensure all systems are installed according to code, tested, commissioned, and fully operational.
6. Ensure all systems operate on a separate, isolated network not connected to the NPS-DOI internal network.
P a g e | 3
7. Maintain daily continuous Visitor Center operations during normal business hours (8:00 a.m. – 4:30 p.m. CST). The Visitor Center must remain open and accessible to the public during these hours.
3. General Requirements
3.1 Codes and Standards
The contractor shall comply with all applicable regulations including, but not limited to:
• NFPA 70 (National Electrical Code)
• NFPA 72 (National Fire Alarm and Signaling Code)
• International Building Code (IBC) 2024 edition
• International Fire Code (IFC) 2024 edition
• NPS Director’s Orders and Reference Manuals (including DO/RM-58)
• DOI IT Security Standards (performance-based compliance)
• Americans with Disabilities Act (ADA)
• UL compliance for all fire/intrusion components
• National Defense Authorization Act of FY 2019, Section 889(a)(1)(A)
• All hardware and software shall comply with all applicable National Park Service policies, standards, directives, and security requirements, and must be reviewed and approved by the National Park Service prior to procurement, installation, and use.
3.2 Contractor Responsibilities
The contractor shall:
• Provide site survey and verification of existing conditions.
• Provide all required permits.
• Coordinate with NPS IT, NPS Regional Fire Marshal, and Facility Management.
• Protect park visitors and NPS property during all work.
• Provide all equipment needed for installation.
P a g e | 4 o A man lift will be needed to reach 30-foot ceiling in the Visitor Center gallery.
See Appendix A.
• Maintain a clean worksite and restore disturbed areas.
3.3 Work Hours
All work shall occur between 8:00 AM and 4:30 PM, Monday through Friday.
The Visitor Center must remain open during installation. Additional work hours and weekend work may be approved by the COR.
4. Fire Alarm System Requirements
4.1 Overview
The contractor shall be responsible for conducting a complete site visit, system evaluation, and design, and for providing full replacement of the existing fire alarm system. The fire alarm system shall be designed and installed as a standalone life-safety system in accordance with NFPA 72.
System design shall be performed by an individual meeting the requirements of NPS Reference Manual 58 (RM-58), Section 2.11.3, specifically one of the following:
• A licensed Fire Protection Engineer;
• A NICET Level III (or higher) Fire Alarm Systems Technician; or
• An individual approved by the Fire Code Official (FCO), NPS IMR Regional Fire Marshal.
The contractor shall assess existing conditions and develop a code-compliant system design that reflects current technology, life-safety requirements, and building conditions, and that provides the best overall performance, reliability, and value to the Government.
Replacement in kind is not presumed and shall only be proposed if supported by the site assessment and approved by the Contracting Officer’s Representative (COR) and the FCO.
See Appendix B for photographs of existing fire alarm system components.
4.2 System Components
The fire alarm system shall include all devices, equipment, and interfaces required to provide a complete, fully code-compliant fire alarm and signaling system for the facility in accordance with NFPA 72, the International Fire Code (IFC) 2024 edition, the International Building Code (IBC) 2024 edition, and RM-58.
P a g e | 5
Components shall be determined through the contractor’s site assessment and design and may include, but are not limited to:
• Fire alarm control and power supplies
• Initiating devices appropriate to the building use and sprinklered condition
• Notification appliances (audible and visual)
• Supervisory devices, including sprinkler system flow and tamper switches
• Monitoring interfaces and communication equipment
• Addressable modules and control devices as required
• Backup power and batteries
• All required wiring, conduit, and ancillary materials
Specific device quantities shall not be presumed and shall be determined by code analysis, building conditions, and AHJ-approved design.
4.3 Installation Requirements
Installation shall be performed by personnel meeting the qualifications identified in RM-58, Table 1, and applicable NFPA requirements.
The contractor shall prepare and submit complete shop drawings, calculations, and system documentation for review and approval by the Fire Code Official (FCO) prior to installation. No installation work shall begin until written approval of shop drawings is received.
Additional requirements include:
• Existing wiring may be reused only if verified as serviceable, code-compliant, and approved by the FCO.
• Wireless devices may be used where permitted by code and approved by the FCO.
• All devices shall be clearly labeled, mapped, and programmed consistent with approved shop drawings.
4.4 Testing, Acceptance, and Commissioning
The contractor shall perform complete system testing in accordance with NFPA 72, including 100 percent testing of all initiating devices, notification appliances, control functions, and supervisory signals.
P a g e | 6
Upon completion of preliminary testing, the contractor shall:
• Complete and submit the NFPA 72 Record of Completion and all required test documentation.
• Coordinate and support formal system acceptance testing conducted by the Fire Code Official (FCO).
• Provide updated as-built drawings, final device lists, and a complete zone list reflecting the installed system.
Final acceptance of the fire alarm system shall occur only after successful FCO acceptance testing and approval.
5. Intrusion Alarm System Requirements
5.1 Overview
Design and replace the existing intrusion detection system. The Contractor shall assess existing conditions and recommend either replacement in kind or an alternate system design utilizing current technology to provide the best overall performance, reliability, and value to the Government. See Appendix C. for pictures of current hardware.
5.2 Component
The system shall include the following components, or other components recommended by the Contractor and approved by the COR:
• One integrated intrusion control panel
• Two keypads
• Sixteen (16) wall mounted motion detectors
• Five (5) ceiling mounted motion detectors
• Two (2) glass break detection devices
• Three (3) double door contacts
• Three (3) single door contacts
• Two (2) siren alarms
• One (1) outside siren alarm
P a g e | 7
• Three (3) silent panic alarm buttons (1 at the USFS Visitor Services desk, 1 at the bookstore counter and 1 at the NPS Visitor Center desk)
• Alarm communicator that is non-proprietary.
5.3 Testing
• Verification of detection zones
• Alarm communication tests
• All programming parameters documented and provided to NPS
• Contractor must provide a complete zone list and updated as-built drawings
6. CCTV System Requirements
6.1 Overview
The Contractor shall design and replace the existing CCTV system with a surveillance system consisting of indoor and outdoor fixed cameras, network storage, and user viewing interfaces. The system shall include real-time viewing monitors located at two staffed public-facing desks to support situational awareness and visitor safety. The system must be capable of supporting up to twenty (20) cameras. The Contractor shall supply and install approximately nine (9) indoor cameras and approximately six (6) outdoor cameras. Up to four (4) additional cameras may be installed at a later date and are not included under this contract.
All cameras, recording platforms, and associated system components shall be Milestone compatible, NDAA Compliant, non-banned IP brand name Axis Communication cameras, and compliant with U.S. Department of the Interior (DOI) approved CCTV equipment requirements.
The Contractor shall assess existing conditions and recommend either replacement in kind or an alternate system design utilizing current technology that provides the best overall performance, reliability, cybersecurity posture, and value to the Government. See Appendix E for a list of existing CCTV system components and photographs.
6.2 Components
The system shall include the following components, or other components recommended
P a g e | 8 by the Contractor and approved by the COR, provided they are within the DOI-approved vendor/model list identified in Section 6.1:
• System capacity supporting up to twenty (20) cameras
• Nine (9) indoor cameras to be supplied and installed
• Six (6) outdoor cameras to be supplied and installed
• Network Video Recorder (NVR) or approved video management/storage platform capable of a minimum of seven (7) days of continuous storage
• Time/date stamping, search, export, and playback functions
• Uninterruptible Power Supply (UPS)
• PoE switches as required
• Cabling and networking components to support all CCTV devices
• Two (2) dedicated CCTV viewing monitors (see Section 6.3)
6.3 View Monitors
The Contractor shall provide and install two (2) dedicated CCTV viewing monitors to allow authorized staff to observe real-time camera output of the lower entrance for security and situational awareness. Viewing monitors are not currently installed with the existing system.
Monitor Locations:
1. NPS Visitor Center Front Desk
2. U.S. Forest Service (USFS) Customer Service Desk
Monitor Requirements:
• Minimum 22–24" commercial-grade display suitable for continuous operation
• Fully compatible with the selected DOI-approved CCTV system live-view output
• Default display of the lower entrance camera feed
• Capability to switch to other camera views if permitted by system functionality
• Secure power and cabling with all necessary video, network (if applicable), and power connections
• Mounted using low-profile, visitor-safe hardware appropriate for public-facing areas
P a g e | 9
• Concealed or protected cable routing to meet NPS aesthetic standards and prevent visitor interference
• Final placement and mounting method coordinated with and approved by the COR prior to installation
6.4 Wiring Options
The Contractor shall propose the best-value wiring solution, which may include hardwired, wireless, or hybrid configurations, based on signal performance, reliability, security, and life-cycle cost.
6.5 Coverage and Functional Requirements
• Cameras must cover building entry and exit points, sales area, front desk, administrative hallways, and exterior perimeter
• No remote access or offsite viewing capability is required
• System shall comply with DOI and NPS security, privacy, and records management requirements
7. Door Access Control System Requirements
7.1 Overview
Install an electronic access control system for four (4) doors, including prox card readers and card encoding capability. A workstation (computer) will need to be sourced and supplied by the contractor that can operate the system software. See Appendix D for pictures of existing system. Note: The front entrance sliding doors will be replaced with double doors under a future project. Although door replacement is not part of this contract, the contractor shall design and install the door lock system so that it fully supports and aligns with the planned double-door configuration.
7.2 Hardware
Contractor shall:
• Survey each door
• Propose appropriate electrified hardware (strike or mag lock)
• Install door controllers
P a g e | 10
• Install prox card readers
• Ensure safe egress consistent with life safety codes
7.3 Software and Workstation
Contractor shall provide:
• Access control software capable of managing up to 50 users
• A standalone workstation meeting DOI/NPS IT compatibility standards
• Local-only administration (no remote management)
• Card printing/encoding device
7.4 System Features
• Scheduled lock/unlock
• Log all entries/exits
• No integration with CCTV required
• Integration with intrusion system only where necessary
8. Network and IT Security Requirements
8.1 Separate Network
All systems (fire, intrusion, CCTV, door access) shall operate on a physically and logically isolated network.
8.2 IT Compliance
• All components must meet DOI/NPS security requirements.
• No direct or indirect connections to the NPS-DOI internal network.
• Contractor must coordinate with NPS IT staff to ensure compliance.
9. Submittals
Contractor shall provide the following:
9.1 Pre-Installation
P a g e | 11
• Product data sheets
• Wiring diagrams
• Network diagrams
• Door hardware survey report
• Cut sheets for all hardware
• Implementation schedule
9.2 Post-Installation
• As-built drawings
• System programming files
• Equipment lists with serial numbers
• O&M manuals
• Warranty documentation
10. System Testing and Acceptance
The contractor shall perform and document:
• Acceptance testing of all fire alarm devices per NFPA 72
• Intrusion alarm test verification
• CCTV system functionality and playback validation
• Door access credentialing, scheduling, and logging verification
• Backup power system test
• End-to-end system demonstration with NPS staff
Acceptance requires full functionality of all systems.
11. Training
Contractor shall provide on-site training for designated NPS personnel, including:
• Operation of each system
P a g e | 12
• Programming (as authorized)
• Troubleshooting basics
• Badge encoding (for access control)
Training shall be hands-on and include job aids.
12. Warranty
Contractor shall provide:
• One-year minimum warranty on all equipment
• One-year warranty on labor and installation
• Warranty service within 48 hours of notification for non-emergency issues
13. Removal and Disposal of Existing Systems
Contractor shall remove and dispose of all debris generated from the removal and installation of the systems, including all existing and new system components, at an off-site location in accordance with applicable federal, state, and local requirements.
P a g e | 13
14. Appendices
Appendix A Special Equipment…………………………………………..14
Appendix B Fire Alarm System……………………………………………15
Appendix C Intrusion Alarm System…………………………………….17
Appendix D Access Control System……………………………………..20
Appendix E CCTV System……………………………………………………22
P a g e | 14
Appendix A
Special Equipment
Smoke alarms (3 ea.) are located on ceiling. Approximate ceiling height is thirty (30) feet.
P a g e | 15
Appendix B
Fire Alarm System
Existing Control Panel
Existing Heat Alarm/Smoke Alarm
P a g e | 16
Existing Strobe Alarm
Existing Horn/Strobe Alarm Existing Pull Station
P a g e | 17
Appendix C
Intrusion Alarm System
Number Location Device
MD -1 First Floor – Office 1 Dual Tech Wall Mounted Motion Detector
MD - 2 First Floor – Office 2 Dual Tech Wall Mounted Motion Detector
MD - 3 First Floor – Office 3 Dual Tech Wall Mounted Motion Detector
MD - 4 First Floor – Office 4 Dual Tech Wall Mounted Motion Detector
MD - 5 First Floor – Office 5 Dual Tech Wall Mounted Motion Detector
MD - 6 First Floor – Office 6 Dual Tech Wall Mounted Motion Detector
MD - 7 First Floor – Office 7 Dual Tech Wall Mounted Motion Detector
MD - 8 First Floor – Office 8 Dual Tech Wall Mounted Motion Detector
DC -1 First Floor – Open Office Single Door Contact
360MD -1 First Floor – Open Office Ceiling Mount Motion Detector
360MD - 2 First Floor – Near 6,7,8 Ceiling Mount Motion Detector
360MD - 3 First Floor - Receptionist Ceiling Mount Motion Detector
DDC – 2A First Floor – Receptionist Double Door Contact
MD - 9 First Floor – Break Room Dual Tech Wall Mounted Motion Detector
MD – 10 First Floor – Conference Room Dual Tech Wall Mounted Motion Detector
DC -3 Communication Room Single Door Contact
CP Communication Room Vista 128 BP Control Panel
IS – 1 First Floor – Receptionist Inside Siren
HU-1 First Floor – Receptionist Silent Panic Alarm Button
OS -1 First Floor – Outside Outside Siren with Light
KP-1 First Floor – Main Entry Alphanumeric Keypad
DDC – 2 First Floor – Exterior Doors Double Door Contacts
P a g e | 18
MD – 11 First Floor – Main Entry Dual Tech Wall Mounted Motion Detector
GBD – 1 First Floor – Main Entry Glass Breakage Device
360MD – 4 Second Floor – Exhibit Hall Ceiling Mount Motion Detector
MD -15 Second Floor - Auditorium Dual Tech Wall Mounted Motion Detector
DDC – 5 Second Floor – East Entrance Double Door Contact
MD – 14 Second Floor – Main Hall Dual Tech Wall Mounted Motion Detector
MD – 13 Second Floor – Main Hall Dual Tech Wall Mounted Motion Detector
MD – 12 Second Floor – Book Room Dual Tech Wall Mounted Motion Detector
DC – 6 Second Floor – Bookstore Single Door Contact
KP – 2 Second Floor – Bookstore Alphanumeric Keypad
360MD – 5 Second Floor – Office Ceiling Mount Motion Detector
MD – 16 Second Floor – Store Room Dual Tech Wall Mounted Motion Detector
IS – 2 Second Floor – Bookstore Inside Siren
HU – 2 Second Floor – Bookstore Silent Panic Alarm Button
GBD – 2 Second Floor – Bookstore Glass Breakage Device
Existing Keypad
P a g e | 19
Existing Wall Mounted Motion Detector Existing Wall Mount Glass Breakage Detector
Existing Ceiling Motion Detector
P a g e | 20
Appendix D
Access Control System
Existing Access Control Panel
Front Sliding Door Entrance
Note: The front entrance sliding doors will be replaced with double doors under a future project.
P a g e | 21
Lower Main Entrance
USFS Back Entrance
NPS Back Entrance
P a g e | 22
Appendix E
CCTV System
Existing CCTV System Components
Number Location – Look @ Device
C – 1 First Floor – Main Entrance 5 – 50 mm Wall Mount – Outdoor
C – 2 First Floor – Parking Lots PTZ – Outdoor
C – 3 First Floor – Side Door 3.8 – 9 mm Wall Mount - Outdoor
C – 4 First Floor – Office Windows
5 – 50 mm Wall Mount – Outdoor
C – 5 First Floor – Back of Building
Parapet Mount 5 – 50 mm - Outdoor
C – 6 First Floor – Open Office Door
3.8 – 9 mm – Wide Dynamic Dome - Indoor
C – 7 First Floor – Stairs/Rest Room
3.8 – 9 mm – Wide Dynamic Dome - Indoor
C – 8 First Floor – Main Entrance 3.8 – 9 mm – Wide Dynamic Dome - Indoor
C – 9 Maintenance Building – West to East
5 – 50 mm Pole Mount – Outdoor
C – 10 Maintenance Building – East to SW
5 – 50 mm Pole Mount – Outdoor
C – 11 Maintenance Building – South to North
5 – 50 mm Pole Mount – Outdoor
C – 12 Second Floor – Exhibits 3.8 – 9 mm – Wide Dynamic Dome - Indoor
P a g e | 23
C – 13 Second Floor – Stairs/Rest Rooms
3.8 – 9 mm – Wide Dynamic Dome - Indoor
C – 14 Second Floor – Great Hall 3.8 – 9 mm – Wide Dynamic Dome - Indoor
C – 15 Second Floor – Great Hall 3.8 – 9 mm – Wide Dynamic Dome - Indoor
C – 16 Second Floor – Cash Register
3.8 – 9 mm – Wide Dynamic Dome - Indoor
C – 17 Second Floor – Bookstore 3.8 – 9 mm – Wide Dynamic Dome - Indoor
C - 18 Second Floor – West to East PTZ – Outdoor
DVR First Floor – Communication
PS – 1 First Floor – Communications
Camera Power Supply
PS – 2 Second Floor - Office Camera Power Supply
Existing DVR, monitor, and control for CCTV system
P a g e | 24
Examples of existing outdoor cameras
P a g e | 25
Examples of existing indoor cameras
P a g e | 26
Blank