Performance Work Statement Summary
This is a Performance Work Statement (PWS) for the purchase and installation of a nitrogen generation system in five dormitory buildings (222, 223, 226, 244, and 248) at F.E. Warren Air Force Base, Wyoming, with a completion deadline of 45 calendar days from the award date. The contractor must design, install, test, calibrate, and commission a turnkey nitrogen generation and maintenance panel to replace the existing air-compressor-based dry pipe fire suppression system in compliance with NFPA 13 and NFPA 70 standards.
The core technical requirements specify that the nitrogen generator plant must pressurize the dry-pipe sprinkler system to designated operating pressure within 30 minutes, maintain a minimum of 98% nitrogen concentration throughout the entire piping network to mitigate internal pipe corrosion, and wire high/low pressure switches directly to the existing Fire Alarm Control Panel for abnormal pressure monitoring. On-site installation technicians must hold active NICET Level II (minimum) or Level III/IV (preferred) certification in Water-Based Systems Layout and be factory-trained and authorized installers for the specific nitrogen generator brand and model. The contractor must submit an Impairment Plan at least seven business days prior to system shutdown, conduct pneumatic leakage and trip testing in the presence of the Contracting Officer's Representative or Base Fire Marshal, and deliver manufacturer product data sheets, signed and stamped shop drawings, operation and maintenance manuals, and as-built schematics prior to final acceptance. Additionally, the contractor must provide up to two hours of on-site operations and maintenance training to facility personnel and safely remove and dispose of legacy air compressor equipment, piping, and air maintenance devices in accordance with EPA, Federal, and Base Environmental Compliance Regulations. The contract includes extensive security, OPSEC, environmental, safety, and records management requirements typical of Department of the Air Force installations.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1
PERFORMANCE WORK STATEMENT
FOR
PURCHASE AND INSTALL NITROGEN
SYSTEM IN MULTIPLE FACILITIES
(Buildings 222, 223, 226, 244 & 248)
F.E. Warren Air Force Base, Wyoming
2 June 2026
Table of Contents
1. Description of Services
1.1. Basic Services
1.2. Equipment & Technical Requirements
1.3. Contractor Qualifications
1.4. Outages and Impairment Coordination
1.5. Testing, Commissioning, and Deliverables
1.6. Demolition and Environmental Disposal
2. Services Summary
3. Government Furnished Property and/or Services
3.1. Government Furnished Property
3.2. Government Furnished Services
3.3. Government Property Incidental to the Place of Performance
4. General Information
4.1. Quality Control
4.2. Quality Assurance
4.3. Security Requirements
4.4. Physical Security
4.5. Operational Security (OPSEC)
4.6. Anti-Terrorism
4.7. Location/Hours of Operation
4.8. Conservation of Utilities
4.9. Environmental Controls
4.10. Safety Requirements
4.11. Privatized Utility Systems
4.12. Contractor Personnel
4.13. Records
5. Appendices
APPENDIX A – Publications/Instructions
APPENDIX B – Deliverables
1. Description of Services.
The Contractor shall provide all labor, tools, equipment, materials, and supervision necessary to design, install, test, calibrate, and commission a turnkey Nitrogen Generation and Maintenance Panel to replace the existing air-compressor-based system on the Dry Pipe Fire Suppression System in five (5) dormitories at F.E. Warren Air Force Base, Wyoming, in accordance with all applicable federal, state, local laws and regulations and this performance work statement (PWS).
1.1. Basic Services. The contractor shall Install and calibrate Nitrogen Panel for Dry Pipe Fire Suppression
System. They will adhere to NFPA regulations and Fire Codes. Contractors will test and confirm that Nitrogen is stabilized to a minimum of 98% full in all piping. Contractors will be required to dispose of old Air Compressors, Piping, and Air Maintenance Devices.
1.2. Equipment & Technical Requirements.
1.2.1. Performance: The Nitrogen Generator Plant shall be sized to pressurize the dry-pipe sprinkler system to its designated operating pressure within 30 minutes in accordance with NFPA 13.
1.2.2. Purity: The system must utilize a listed nitrogen generator capable of providing and maintaining at least 98% nitrogen concentration throughout the entire dry-pipe piping network to mitigate internal pipe corrosion.
1.2.3. Monitoring & Alarms: The contractor shall wire the nitrogen panel's high/low pressure switches and system trouble contacts directly to the existing Fire Alarm Control Panel (FACP) to monitor abnormal pressures or system faults.
1.2.4. Electrical: All electrical work and connections must conform to NFPA 70 (National Electrical Code).
1.3. Contractor Qualifications.
1.3.1. Certifications: On-site installation technicians must possess active National Institute for Certification in Engineering Technologies (NICET) Level II (minimum) or Level III/IV (preferred) certification in Water-Based Systems Layout.
1.3.2. Manufacturer Authorized: The contractor must be a factory-trained and authorized installer for the specific brand and model of the nitrogen generator being installed.
1.4. Outages and Impairment Coordination.
1.4.1. The contractor shall keep system outages to an absolute minimum.
1.4.2. The contractor must submit an Impairment Plan in writing to the Contracting Officer’s Representative (COR) at least seven (7) business days prior to shutting down the sprinkler system.
1.4.3. No fire protection system may be left non-functional overnight without an approved interim fire watch plan in place.
1.5. Testing, Commissioning, and Deliverables.
1.5.1. Purity Verification: Upon installation, the contractor must manually demonstrate and document that the nitrogen concentration inside the dry-pipe system has reached a minimum of 98%.
1.5.2. Pressure/Trip Testing: The contractor shall perform a pneumatic leakage test and system trip test in the presence of the COR or designated Base Fire Marshal.
1.5.3. Submittals: The contractor must deliver the following documents prior to final acceptance:
1.5.3.1. Manufacturer Product Data Sheets (Cut Sheets).
1.5.3.2. Signed and Stamped Shop Drawings.
1.5.3.3. Manufacturer's Operation & Maintenance (O&M) Manuals.
1.5.3.4. "As-Built" Schematics.
1.5.4. Training: The contractor shall provide up to two (2) hours of on-site operations and maintenance training to facility personnel covering the operation, routine maintenance, and troubleshooting of the new Nitrogen
Panel.
1.6. Demolition and Environmental Disposal.
1.6.1. The contractor shall safely disconnect, dematerialize, and dispose of the legacy air compressor, legacy piping, and legacy air maintenance devices.
1.6.2. All removed equipment, piping, and debris become the property of the contractor and must be disposed of off-base in accordance with EPA, Federal, and Base Environmental Compliance Regulations.
1.6.3. Any oils or hazardous fluids drained from the legacy air compressor must be handled, logged, and recycled/disposed of in strict compliance with the EPA, Federal, and Base Environmental Compliance
Regulations.
2. Services Summary.
The contractor service delivery requirements are summarized into performance objectives that relate directly to standards of performance required to meet mission essential needs. For the Performance Objective to be met, service delivery must be in substantial compliance with applicable performance standards. The Performance Threshold describes the minimum overall levels of service delivery required for acceptable quality control. Failure to meet these Performance Thresholds means that contractor Quality Control is unacceptable. The following is a list of the key performance objectives that will be verified as contractually compliant by Government personnel; however, inspection of any contract requirement is authorized.
Performance Objective
PWS
Para.
Performance Threshold Method of Surveillance
SS-1: Install, calibrate, and integrate the nitrogen generator plant in compliance with NFPA codes.
1.1.
1.2.
Zero defects/violations.
System must reach operating pressure within 30 minutes, maintain 98% purity, and correctly transmit alarms to the FACP.
- 100% Inspection (final walkthrough)
- Periodic Surveillance
- Customer Feedback
SS-2: Provide qualified personnel authorized and certified to perform the work.
1.3. 100% Compliance.
All lead on-site technicians must hold NICET II (or higher) and manufacturer certifications prior to starting work.
- 100% Inspection
SS-3: Minimize risk to life safety during system downtime.
1.4. Zero unauthorized outages.
Impairment Plan submitted 7+ days prior. Zero instances of the building left unprotected overnight without an approved fire watch.
- Periodic Surveillance
- Customer Feedback
SS-4: Verify system functionality and transition knowledge/documentation to the Government.
1.5. 100% Completion.
Successful manual demonstration of 98% purity, successful trip test, delivery of all 4 required submittals.
- 100% Inspection
SS-5: Provide comprehensive on-site training to designated facility personnel covering the operation, routine maintenance, and troubleshooting of the new Nitrogen Panel.
1.5.4. 100% Completion.
Up to two (2) hours of on-site training successfully delivered prior to final system acceptance.
- 100% Inspection
SS-6: Safely remove and dispose of legacy equipment, piping, and hazardous fluids.
1.6. Zero environmental violations.
100% of legacy equipment removed off-base. Proper handling and logged disposal of hazardous fluids/oils in accordance with EPA and Base regulations.
- Periodic Surveillance
3. Government Furnished Property and/or Services
3.1. Government Furnished Property.
3.1.1. None
3.2. Government Furnished Services.
3.2.1. Utilities. The Government will furnish the electricity, water, and sewage services (as necessary) for the accomplishment of service IAW this PWS.
3.3. Government Property Incidental to the Place of Performance.
3.3.1. None
4. General Information.
4.1. Quality Control.
The contractor is required to control the quality-of-service delivery and offer to the Government for acceptance only services which conform to contract requirements. The overall control of quality must meet the specified performance thresholds for each requirement in the Services Summary.
4.2. Quality Assurance
The Government will evaluate the contractor’s performance to ensure services are received. The Government will evaluate the contractor’s performance through on-site inspections and receipt of customer complaints.
The Government will inspect each task as completed. The Government will investigate complaints received from customers. The Government shall make final determination of the validity of customer complaint(s) in cases of disagreement with customer(s). Remedies for non-conforming services will be resolved IAW the applicable Inspection/Acceptance clause attached within the contract.
4.2.1. Any matter concerning a change to the scope, prices, terms, or conditions of this contract shall be referred to the Contracting Officer.
4.2.2. The services to be performed by the contractor during the period of this contract shall (at all times and places) be subject to review by the Contracting Officer or subject matter export/inspector.
4.3. Security Requirements.
The contractor shall be responsible for all passes issued to their employees under this contract. Applications shall be coordinated by the Contracting Officer or designated representative. At the time of application, Security Forces will conduct a background check on employees. Upon termination of employment or contract completion, the contractor shall be responsible for returning identification cards/base passes to Security Forces within 24 hours.
4.3.1. REAL ID-Compliant Identification.
IAW DoDM 5200.08V3_DAFMAN 31-101V3_DAFGM 2024-01, Installation Perimeter Access Control. Base access and Common Access Cards (CAC) requests will require REAL ID-Compliant identification for Base access and CAC creation. Failure of the vendor to ensure personnel have REAL ID-compliant identification will result in denial of Base access and CAC requests.
4.3.1.1. Contractor Access to Department of the Air Force Installations.
• The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
• The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, and valid vehicle insurance certificate to obtain a vehicle pass.
• During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
• When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [insert any additional requirements to comply with DAFI 31-101, Base Defense Operations, and DODMAN5200.02_DAFMAN 16-1405 , Department of the Air Force Personnel Security Program] citing the appropriate paragraphs as applicable.
• Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
• The contractor shall provide an after-hours contact number or after-hours email in the Emergency Mass Notification System (EMNS) for each of their personnel, whose normal place of duty is on a DoD installation or within a DoD facility. The contractor shall comply with any additional requirements in AFMAN 10-206 for emergency operational reporting. Foreign Nationals may participate and may remove themselves from the Emergency Mass Notification System at any time.
To update information, personnel can access the globe icon on their system desktop screens and choose the “Access Self-Service” option.
• Failure to comply with these requirements may result in withholding of final payment.
4.4. Physical Security.
The contractor shall be responsible for safeguarding all Government property provided for contractor use. At the close of each work period, Government facilities, property, and materials shall be secured.
4.4.1. Key Control.
The contractor shall establish and implement methods of ensuring that all keys/key cards issued to the contractor by the government are not lost or misplaced and are not used by unauthorized persons. The contractor shall not duplicate any keys issued by the government.
NOTE: all references to keys also include key cards. No keys issued to the contractor by the government shall be duplicated. The contractor shall develop procedures covering key control. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas.
4.4.1.1. The contractor shall immediately report the occurrences of a lost or duplicate key to the contracting officer.
4.4.1.2. In the event keys, other than master keys, are lost or duplicated, the contractor shall, upon written direction of the contracting officer, rekey or replace the affected lock or locks; however, the government, at its option, may replace the affected lock or locks or perform rekeying. When the replacement of locks or rekeying is performed by the government, the total cost of rekeying or the replacement of the lock or locks shall be deducted from the monthly payment due the contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the government and the total cost deducted from the monthly payment due the contractor.
4.4.1.3. The contractor shall prohibit the use of keys issued by the government by any persons other than the contractor’s employees. The contractor shall prohibit the opening of locked areas by contractor employees to permit entrance of persons other than contractor’s employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
https://static.e-publishing.af.mil/production/1/af_a4/publication/dafi31-101/controlled_unclassified_information.pdf https://static.e-publishing.af.mil/production/1/saf_aa/publication/dodman5200.02_dafman16-1405/dodm5200.02_afman16-1405.pdf https://static.e-publishing.af.mil/production/1/saf_aa/publication/dodman5200.02_dafman16-1405/dodm5200.02_afman16-1405.pdf
4.5. Operational Security (OPSEC).
The contractor shall adhere to the following minimum requirements in support of this requirement:
4.5.1. All contractors, subcontractors, their employees, associates, and consultants who have access to critical information and indicators must comply with the Air Force-sponsored Operations Security (OPSEC) program.
4.5.2. OPSEC is an information-related capability that preserves friendly essential secrecy by using a process to identify, control, and protect critical information and indicators. If critical information and indicators are disclosed, it could allow adversaries or potential adversaries to identify and exploit friendly vulnerabilities leading to increased risk to mission failure or the loss of life. The desired effect of OPSEC is to influence the adversary’s behavior and actions by reducing the adversary’s ability to collect and exploit critical information and indicators about friendly activities.
4.5.3. Responsibilities:
4.5.3.1. Contractors must ensure employees receive OPSEC education that includes an overview of the OPSEC process, the definition of OPSEC, its purpose, what is critical information, the individual’s role in protecting critical information, and the general adversary threat to the AF’s critical information. Additionally, OPSEC education must include updated threat information, changes to critical information and indicators, new procedures and/or OPSEC measures implemented, altered, or deleted by the organization.
4.5.3.2. DoD Contractors with OPSEC requirements or that have access to critical information and indicators shall complete initial and annually-recurring refresher training. Accomplishment of initial OPSEC training must not exceed 90 days from initial assignment to a contract with OPSEC requirements. Access to mission-critical information will not be allowed until OPSEC education has been completed and documented.
4.5.3.3. OPSEC education is a continuous requirement. The host unit OPSEC coordinator must track OPSEC training statistics to include the personnel working on the contract, when each individual received the required initial OPSEC training, and when refresher training is due and/or completed.
4.5.4. Contractor personnel shall not discuss government operations in public or over unprotected or unencrypted communications. Controlled unclassified information (CUI) may only be transmitted as directed in this PWS.
4.5.5. The Contractor shall not post to company websites, publications, newsletters, or other media any images, data, or information that reveal sensitive government operations, personnel, equipment, and/or classified or controlled unclassified information. When in doubt, company press releases related to this contract should be coordinated through the COR or CO, as applicable.
4.5.6. Prior to seeking approval through the F. E. Warren AFB Public Affairs, any information to be released outside of official U.S. Government channels, via any media (to include electronic communications), must be approved through an OPSEC review. All personnel must promptly report OPSEC-related incidents, issues, and concerns to the host-unit OPSEC coordinator.
4.5.7. Contractors shall restrict access to those individuals with a valid need-to-know who are actually providing services under the contract. Further dissemination to other contractors, subcontractors, or other government agencies and private individuals or organizations is prohibited unless authorized in writing.
4.5.8. Because observation of events, operations, physical changes, etc., may reveal National Security information, specific restrictions are needed to preclude unintentional release of this information to unauthorized parties. Unauthorized disclosure and transfer of National Security Information is punishable under 18 USC § 793. Therefore, contractor personnel shall not disclose to unauthorized third parties, post to unofficial sites (including Social Networking sites) any images, data/information, or observed events that reveal sensitive government operations, personnel, equipment, including, but not limited to:
4.5.8.1. Tactics, techniques, and procedures, production, or work schedules, any visible or concealed modifications, upgrades, additions to vessels, aircraft, or weapons or equipment; increases, change, or decreases in work/deployment frequency or government personnel, vehicle, vessel, or aircraft movements;
specialized equipment orders, deliveries, shipments, etc. Unauthorized disclosures and attempts to solicit this type of information by unauthorized third parties or others not affiliated with this contract shall be reported to the COR or CO, as applicable.
4.5.8.2. Government issued badges, identification shall be removed and/or concealed from plain sight when off base and shall not be left in vehicles or unprotected areas. Badges and passes may not be duplicated, copied, or loaned to others. Lost or stolen identification badges, vehicle passes, etc., will be immediately reported to the COR, CO, and/or Installation Security Office.
4.6. Anti-Terrorism
4.6.1. Notification: If the Contractor (contract employees/subcontractors) identify any suspicious activity, they shall contact the Base Defense Operations Center (BDOC) at 307-773-3501 (On-installation)/Missile Security Control (MSC) at 307-773-2701 (Off-installation) and notify the CO and COR (if appointed) that they contacted the BDOC and/or MSC.
4.7. Location/Hours of Operation.
4.7.1. Location. Place of performance is FE Warren AFB WY. Telework shall not be permitted for this task order/contract.
4.7.2. Normal Hours of Operation. The contractor shall perform the services required under this contract during the hours listed within Table 1, Location and Hours of Work. The contractor may work (with prior approval of the CO) extended hours to ensure timely completion of work at no additional cost to the Government. The Contractor has 45 calendar days from the date of award to complete the installation.
4.7.3. Recognized Holidays. The contractor is not required to provide service on the following days, unless otherwise noted:
• New Year's Day (January 1).
• Birthday of Martin Luther King, Jr. (Third Monday in January).
• Washington's Birthday (Third Monday in February).
• Memorial Day (Last Monday in May).
• Juneteenth National Independence Day (June 19).
• Independence Day (July 4).
• Labor Day (First Monday in September).
• Columbus Day (Second Monday in October).
• Veterans Day (November 11).
• Thanksgiving Day (Fourth Thursday in November).
• Christmas Day (December 25).
If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.
Table 1. Location and Hours of Work
Building No. Name of Facility Days Time
222 Dorm Monday – Friday 0800 – 1600 hrs
223 Dorm Monday – Friday 0800 – 1600 hrs
226 Dorm Monday – Friday 0800 – 1600 hrs
244 Dorm Monday – Friday 0800 – 1600 hrs
248 Dorm Monday – Friday 0800 – 1600 hrs
4.8. Conservation of Utilities.
The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions which prevent the waste of utilities which include the following:
4.8.1. Lights shall be used only in areas where and when work is being performed.
4.8.2. Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor or by contractor employees unless authorized.
4.8.3. Water faucets or valves shall be turned off after the required use has been accomplished.
4.8.4. Government telephones shall be used only for official Government business.
4.9. Environmental Controls.
4.9.1. Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Interstate, federal, state, and local laws, regulations, and requirements regarding environmental protection, to include Section 01 57 19.05 32, Environmental Protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost because of the change, the contractor shall inform the CO pursuant to notice requirements and negotiate a modification to the contract.
4.9.2. Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to the F.E. Warren AFB Fire Dept at 911 (landline) or 307-773-2931 (cell phone). The liability for the spill or release of such substance(s) rests solely with the contractor and its agent.
4.9.3. Hazardous Material (HM). If hazardous materials will be used in the execution of this contract, the contractor shall comply with all federal, state and local regulations concerning the use, storage, and reporting of HM in accordance with DAFMAN 32-7002, Environmental Compliance and Pollution Prevention. The contractor shall be required to obtain authorization per the Installation Hazardous Materials Management Program before ordering or purchasing any hazardous product and may not bring a HM onto F.E. Warren AFB property, nor use a HM, until the contractor receives all required authorizations. This authorization process may take up to three weeks. The contractor shall provide the information listed in Attachment 1 of Section 01 57 19.05 32 to request authorization for all hazardous materials proposed for use on FE Warren AFB or the missile field.
4.9.4. Green Procurement Program (GPP). In performance of this contract, contractors shall use Environmental Protection Agency (EPA) designated recycled content products, Information Technology (IT) Energy Star products/appliances, Federal Energy Management Program (FEMP) Designated Energy Efficient Low Stand By Power products/appliances, U.S. Department of Agriculture (USDA) Bio based/Bio preferred products, Environmentally preferable products, Electronic Product Environmental Assessment Tool (EPEAT) registered products, Water Sense or other water efficient products, non- or Low Ozone depleting substances under the Significant New Alternatives Policy (SNAP), non or Low toxic or hazardous constituents (e.g. non- VOC paint) and any other environmentally sustainable product/method, to the greatest extent possible.
4.9.5. Elimination of Use of Class I Ozone Depleting Substances (ODS).
4.9.5.1. Contractors shall not:
4.9.5.1.1. Provide any service or product with any specification, standard, drawing, or other document that requires the use of a Class I ODS in the test, operation, or maintenance of any system, subsystem, item, component, or process; or
4.9.5.1.2. Provide any specification, standard, drawing, or other document that establishes a test, operation, or maintenance requirement that can only be met by use of a Class I ODS as part of this contract/order.
4.9.5.2. For the purposes of Department of the Air Force policy, the following products that are pure (i.e., they meet the relevant product specification identified in DAFMAN 32-7002) are Class I ODSs:
4.9.5.2.1. Halons: 1011, 1202, 1211, 1301, and 2402;
4.9.5.2.2. Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC- 115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the blends R-500, R-501, R- 502, and R-503; and
4.9.5.2.3. Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide.
4.10. Safety Requirements.
4.10.1. In performing work under this contract, the contractor shall:
4.10.1.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.
4.10.1.2. Record and report promptly (within one hour), to the contracting officer or designated COR, all available facts relating to each instance of damage to Government property or injury to either contractor or Government personnel.
4.10.1.3. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the CO.
4.10.2. Health and Safety on Government Installations. In performing work under this contract on a Government installation, the contractor shall:
4.10.2.1. Take all reasonable steps and precautions to prevent accidents and preserve the health and safety of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
4.10.2.1.1. Take such additional immediate precautions as the contracting officer may reasonably require for health and safety purposes.
4.10.2.2. The contracting officer may, by written order, direct Department of the Air Force Occupational Safety and Health (AFOSH) Standards and/or health/safety standards as may be required in the performance of this contract and any adjustments resulting from such direction will be in accordance with the Changes clause of this contract.
4.10.2.3. Any violation of these health and safety rules and requirements, unless promptly corrected as directed by the contracting officer, shall be grounds for termination of this contract in accordance with the Default clause of this contract.
4.11. Privatized Utility Systems.
4.11.1. The electrical distribution utility system at F.E. Warren Air Force Base has been sold to High West Energy (“System Owner”) as part of the USAF Utilities Privatization (UP) effort. Therefore, the System Owner is the sole provider of these utility services to the installation and should be viewed just like any other local utility Contractor.
4.11.2. Newly installed system infrastructure and modifications of (or connections to) existing system infrastructure identified in the specifications and drawings must be coordinated with the System Owner prior to the contract start date. The System Owner must be integrated into the design, inspection of construction, tie-in to existing utilities, and conveyance of any exterior utilities. The preferred process for connecting facilities is to request that the System Owner install the required connecting facilities, up to a point of demarcation to be identified by the Government, as a connection charge. However, if a connection charge cannot be negotiated, work may be accomplished by the Prime Construction Contractor and later connected to the System Owner’s system, provided that the System Owner’s connection criteria, as set forth in its utility services contract with the Government, are met. Any fees associated with connecting Contractor constructed infrastructure to the System Owner’s system must be negotiated with the System Owner. All work on the system or facilities expected to connect to the system shall comply with the System Owner’s specifications and construction standards.
In no event shall the Contractor cap, connect to, or otherwise touch the System Owner’s infrastructure without the System Owner’s express written permission. This also applies in the event of a utility strike involving the System Owner’s infrastructure.
4.11.3. System Owner Office Hours:
• Monday thru Thursday, 7:30am – 5:00pm MT
4.11.4. If the Contractor requests the System Owner’s efforts outside of the above identified business hours, additional costs may be incurred by the Contractor due to the scheduling of the request.
For a non-emergency, the System Owner may be contacted at:
• Project Manager o 307-365-6458
• HWE Main Office o 6270 CR 212, PO Box 519
Pine Bluffs, WY 82082 o 307-245-3261
For emergencies or utility strikes involving the System Owner’s infrastructure, please follow standard procedures identified on the Dig Permit Request Checklist.
4.12. Contractor Personnel.
4.12.1. Contract Manager: the contractor shall provide a contract manager who shall be responsible for the performance of the services. The name of the contract manager shall be provided to the CO in writing prior to the beginning of the first performance period. The contract manager must be able to read, write, speak, and understand English.
4.12.1.1 The contract manager shall have full authority to act for the contractor on all contract matters relating to daily operations of this contract.
4.12.2. Contractor Employees: the contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the CO as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population.
4.12.2.1. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges, which contain the company name and employee name in English.
4.13. Records. The contractor shall be responsible for creating, maintaining, and disposing of only those government required records that are specifically cited in this PWS or required by the provisions of a mandatory directive listed in Applicable Publications and Forms. If requested by the Government, the contractor shall provide the original record, or a reproducible copy of any such record within five working days of receipt of the request.
4.13.7. Disposition.
4.13.7.1. Contractors shall follow CUI disposition requirements in accordance with DoDI 5200.48 and DoDI
5200.48_DAFI 16-1403.
4.13.7.2. Record and non-record copies of CUI documents will be disposed of in accordance with Chapter 33 of Title 44, U.S.C. and the DoD Components’ records management directives. When destroying CUI, including in electronic form, agencies must do so in a manner making it unreadable, indecipherable, and irrecoverable. If the law, regulation, or government-wide policy specifies a method of destruction, agencies must use the method prescribed.
4.13.7.3. Record and non-record CUI documents may be destroyed by means approved for destroying classified information or by any other means making it unreadable, indecipherable, and unrecoverable the original information such as those identified in NIST SP 800-88 and in accordance with Section 2002.14 of Title
32, CFR.
4.13.8. Disclosure.
4.13.8.1. Contractors shall follow CUI disclosure requirements in accordance with DoDI 5200.48 and DoDI
5200.48_DAFI 16-1403.
4.13.8.2. Contractor shall immediately notify the Contracting Officer and servicing Information Protection Office of unauthorized disclosure of CUI.
5. Appendices
A. Publications/Instructions B. Deliverables
APPENDIX A – Publications/Instructions
Publication/Instruction /Name
Date Applicable
Paragraph/Chapter PWS Paragraph
NFPA 13, Standard for the Installation of Sprinkler Systems
2025 Entire Document Applicable
1.2.1
NFPA 70, National Electrical Code
2026 Entire Document Applicable
1.2.4
DoDM 5200.08V3_DAFMAN 31-
101V3_DAFGM 2024-01
2024 Installation Perimeter Access Control
4.3.1
DAFI 31-101, Base Defense Operations
09 Sept 2024 Entire Document Applicable
4.3.1.1
DODMAN5200.02_DAFMAN 16-
28 Nov 2023 Department of the Air Force Personnel Security Program
4.3.1.1
Section 01 57 19.05 32, Environmental Protection
April 2026 Entire Document Applicable
4.9.1
DAFMAN 32-7002,
Environmental Compliance and Pollution Prevention
12 Jun 2025 Entire Document Applicable
4.9.3, 4.9.5.2
DoDI 5200.48 and DoDI
5200.48_DAFI 16-1403
04 Oct 2021 Controlled Unclassified Information (CUI)
4.15.7.1, 4.15.8.1
32 CFR 2002.14 09 June 2026 Methods of destruction for CUI
4.15.7.3
APPENDIX B – Deliverables
All deliverables must meet professional standards and the requirements set forth in the applicable contractual documents. The Contractor shall be responsible for delivering all specified end items. The end items listed in the table below are outputs, which fall within the scope of this effort and are illustrative of the type of work the Government expects to require.
Title Submission Date Distribution Copies Impairment Plan (PWS Para.
1.4.2)
At least 7 business days prior to system shutdown
CO 1 each
Manufacturer Product Data Sheets (Cut Sheets) (PWS Para.
1.5.3.1)
Prior to final acceptance CO 1 each
Signed and Stamped Shop Drawings (PWS Para. 1.5.3.2)
Prior to final acceptance CO 1 each
Manufacturer's Operation & Maintenance (O&M) Manuals (PWS Para. 1.5.3.3)
Prior to final acceptance CO 1 each
"As-Built" Schematics (PWS Para. 1.5.3.4)
Prior to final acceptance CO 1 each
Contract Manager Designation (PWS Para. 4.12.1)
Prior to the beginning of the first performance period
CO 1 each
OPSEC Training Certificates (PWS Para. 4.5.3.2)
Within 90 days of assignment and annually thereafter, if applicable
CO 1 each
Hazardous Materials Authorization Request and SDS (PWS Para. 4.9.3)
Three weeks prior to planned use CO 1 each