About this file

This document outlines the scope of work for a federal solicitation to upgrade electrical utility power at a Department of Veterans Affairs medical facility. The solicitation seeks a contractor to provide all labor, materials, equipment, testing, and construction services necessary to add additional utility feeders and reconfigure the existing switchgear into a split bus configuration to meet increased electrical demands. The contractor will also install a new 15kV generator gear lineup, 15kV-480V transformer, secondary distribution system, and make other improvements to integrate a future secondary electrical generation source. The contractor must develop safety and quality control plans, provide as-built drawings and O&M manuals, and conduct training. The base performance period is 365 calendar days from notice to proceed. The solicitation requires payment and performance bonds, proof of insurance, and adherence to VA supplemental COVID-19 requirements for contractor employees.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--549-19-190 Correct Electrical Deficiencies Phase I, newest first.
File Type Posted
36C25722B0011 0008.docx DOCX document
Provision 52.211-6 Brand Name or Equal.pdf PDF
OSHA - EMR requirement.pdf PDF
SELF-PERFORMED CALCULATIONS.pdf PDF
Answer no. 15 Clarification - 36C25722B0011 Dallas VA MC.pdf PDF
36C25722B0011 0007.docx DOCX document
36C25722B0011 0006.docx DOCX document
Answer no. 15 Clarification - 36C25722B0011 Dallas VAMC RFI Questions.pdf PDF
36C25722B0011 0005.docx DOCX document
Answers to RFIs-Questions 36C25722B0011 Dallas VAMC.pdf PDF
36C25722B0011 0004.docx DOCX document
Pre-Bid Site Visit Sign in 01-19-2022.pdf PDF
Site Visit Sign in 01-25-2022.pdf PDF
36C25722B0011 0003.docx DOCX document
36C25722B0011 0002.docx DOCX document
36C25722B0011 0001.docx DOCX document
261316 MEDIUM-VOLTAGE FUSIBLE INTERRUPTER SWITCHES.pdf PDF
36C25722B0011_1.docx DOCX document
Specs Combined 07-15-2021.pdf PDF
As Built 87.pdf PDF
549-19-190 Dallas Correct Elec Deficiencies 15July2021.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

X1

GENERATOR

ROOM

1A002

SWITCHGEAR

ROOM

1A001 EMERGENCY

ELECTRICAL

ROOM

1A003

GEAR PLC

CONTROLS

AND

BATTERIES

1A004

/ 90 SF

FIRE RISER

1A005

ELECTRICAL

NEW WORK

KEYNOTES - POWER:

(ALL NOTES MAY NOT APPLY TO THIS SHEET)

Architecture Engineering Design-Build paradigm

Dwg. of

GENERAL NOTES

(ALL NOTES MAY NOT APPLY TO THIS SHEET)

- POWER:

C:

\U se rs

\K ei th 3\

O ne

D riv e\ En gi ne er in g\

\2

D al la s V

A

CE

D \E le c\

D al la s V A

CE

D

E le c Ph as e

1.

dw g, /1 2/

2:

:1

PM

, A ut oC

AD

P D

F (G en er al D oc um en ta tio n)

.p c3

AutoCAD SHX Text

CAT 5

AutoCAD SHX Text

#4/0 BARE COPPER

AutoCAD SHX Text

(TYPICAL)

AutoCAD SHX Text

GROUND BUS (TYPICAL)

AutoCAD SHX Text J

AutoCAD SHX Text J

AutoCAD SHX Text J

AutoCAD SHX Text J

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

OC

AutoCAD SHX Text

OC

AutoCAD SHX Text

OC

AutoCAD SHX Text

OC

AutoCAD SHX Text

OC

AutoCAD SHX Text

OC

AutoCAD SHX Text

OC

AutoCAD SHX Text oc

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

OC

AutoCAD SHX Text

OC

AutoCAD SHX Text

HM81501 (1H) CH-NP

AutoCAD SHX Text

HM81502 (2H)

AutoCAD SHX Text

HM81503 (3H)

AutoCAD SHX Text

HM81504 (4H)

AutoCAD SHX Text

HM81506 (6H)

AutoCAD SHX Text

HM81507 (7H)

AutoCAD SHX Text

HM81508 (8H)

AutoCAD SHX Text

HM81509 (9H)

AutoCAD SHX Text

HM81510 (10H)

AutoCAD SHX Text

HM81511 (11H)

AutoCAD SHX Text

HM81512 (12H)

AutoCAD SHX Text

HM81513 (13H)

AutoCAD SHX Text

HM81514 (14H)

AutoCAD SHX Text

HM81515 (15H)

AutoCAD SHX Text

HM81516 (16H)

AutoCAD SHX Text

HM81517 (17H)

AutoCAD SHX Text

HM81518 (18H)

AutoCAD SHX Text

HM81519 (19H) SPARE

AutoCAD SHX Text

HM81505 (5H)

AutoCAD SHX Text

SECTION 08 - M1

AutoCAD SHX Text

SECTION 07 - F1

AutoCAD SHX Text

SECTION 06 - F2

AutoCAD SHX Text

SECTION 05 - F3

AutoCAD SHX Text

SECTION 04 - F4

AutoCAD SHX Text

SECTION 03 - F5

AutoCAD SHX Text

SECTION 02 - F6

AutoCAD SHX Text

SECTION 18 - F13

AutoCAD SHX Text

SECTION 17 - F12

AutoCAD SHX Text

SECTION 16 - F11

AutoCAD SHX Text

SECTION 15 - F10

AutoCAD SHX Text

SECTION 14 - F9

AutoCAD SHX Text

SECTION 13 - F8

AutoCAD SHX Text

SECTION 12 - M2

AutoCAD SHX Text

SECTION 10 - G

AutoCAD SHX Text

SECTION 09 - T1

AutoCAD SHX Text

SECTION 11 - T2

AutoCAD SHX Text

SEC G2-0 G2A

AutoCAD SHX Text

SEC G2-1 G2T1A

AutoCAD SHX Text

SEC G2-2 G2T2A

AutoCAD SHX Text

SEC G2-3 ATS871CHP

AutoCAD SHX Text

SECTION 01 - F7

AutoCAD SHX Text

SECTION 19 - F14

AutoCAD SHX Text

SECTION 00 - G2T1A

AutoCAD SHX Text

SECTION 20 - G2T2A

AutoCAD SHX Text

"GT-B"

AutoCAD SHX Text

MAIN SWITCHGEAR - "MVSE2" 1200A,13,200V, 3 , 4W GROUND, NEMA 1, 25 KAIC

AutoCAD SHX Text

EXISTING ATS-871CHP 800A, 480V 4 POLE (BUILDING 87)

AutoCAD SHX Text

AutoCAD SHX Text

ATS-871CHP

AutoCAD SHX Text

AutoCAD SHX Text

MAIN GEAR

AutoCAD SHX Text

AutoCAD SHX Text

TIE SWITCH G2T1A

AutoCAD SHX Text

AutoCAD SHX Text

EXISTING RTAC CONTROLLER

AutoCAD SHX Text

AutoCAD SHX Text

TIE SWITCH G2T1A

AutoCAD SHX Text

AutoCAD SHX Text

GT-B

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

MV-G2T1A

AutoCAD SHX Text RTAC-01a,b,c

AutoCAD SHX Text

MV-G2T2A

AutoCAD SHX Text

EXISTING POWER CABLE TRAY

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

CTRL-G2T2A

AutoCAD SHX Text

CTRL-G2T1A

AutoCAD SHX Text

MV

AutoCAD SHX Text

MV

AutoCAD SHX Text

MV

AutoCAD SHX Text

MV

AutoCAD SHX Text

MV

AutoCAD SHX Text

MV

AutoCAD SHX Text

CONTROLS

AutoCAD SHX Text

MV

AutoCAD SHX Text

CONTROLS

AutoCAD SHX Text

CONTROLS

AutoCAD SHX Text

AutoCAD SHX Text FROM NEW NEUTRAL RESISTOR TO TO THE EXISTING COUNTERPOISE GROUNDING SYSTEM IN BUILDING

AutoCAD SHX Text

MV

AutoCAD SHX Text

MV-G2

AutoCAD SHX Text

CONTROLS

AutoCAD SHX Text

(3) 1"C

AutoCAD SHX Text

(2) 1" C

AutoCAD SHX Text (3)

AutoCAD SHX Text

AutoCAD SHX Text CTRL-G2a,b

AutoCAD SHX Text

EXISTING GROUND BAR

AutoCAD SHX Text M

AutoCAD SHX Text F

AutoCAD SHX Text

AutoCAD SHX Text

NEW 15KV GENERATOR GEAR LINE-UP "MVSE3"

AutoCAD SHX Text FROM NEW NEUTRAL RESISTOR TO NEUTRAL OF SEC G2-0 IN GENERATOR GEAR LINE-UP "MVSE3" "MVSE3"

AutoCAD SHX Text

MV-G2NGR

AutoCAD SHX Text P

AutoCAD SHX Text P

AutoCAD SHX Text

AutoCAD SHX Text

MV

AutoCAD SHX Text

MV-GTB

AutoCAD SHX Text

HV

AutoCAD SHX Text

"FDSW-G"

AutoCAD SHX Text

AutoCAD SHX Text

HV-ATS871CHP

AutoCAD SHX Text P

AutoCAD SHX Text

HV

AutoCAD SHX Text

HV

AutoCAD SHX Text

HV

AutoCAD SHX Text

HV

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

DIKE

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

EXISTING ETHERNET SWITCH

AutoCAD SHX Text

SCALE: 1/4" = 1'-0"

AutoCAD SHX Text Drawing Title

AutoCAD SHX Text

ARCHITECT/ENGINEERS:

AutoCAD SHX Text Project Title

AutoCAD SHX Text Date

AutoCAD SHX Text Location

AutoCAD SHX Text Checked

AutoCAD SHX Text Building Number

AutoCAD SHX Text Project Number

AutoCAD SHX Text Drawing Number

AutoCAD SHX Text Drawn

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text one quarter inch = one foot

AutoCAD SHX Text

VA FORM 08-6231

AutoCAD SHX Text Office of Construction and Facilities Management

AutoCAD SHX Text Revisions:

AutoCAD SHX Text Date

AutoCAD SHX Text

CONSULTANTS:

AutoCAD SHX Text Approved Project Director

AutoCAD SHX Text 200 Envoy Circle #201, Louisville KY 40299 - PH: 502.339.8511 - www.paradigmusa.com

AutoCAD SHX Text

CORRECT ELECTRICAL DEFICIENCIES BID DOCUMENTS FOR CONSTRUCTION

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text F

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text C

AutoCAD SHX Text B

AutoCAD SHX Text A

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 549-19-190

AutoCAD SHX Text

DALLAS VAMC CORRECT ELECTRICAL DEFICIENCIES

AutoCAD SHX Text 06-08-2021

AutoCAD SHX Text

DALLAS VA MEDICAL CENTER

AutoCAD SHX Text 4500 S Lancaster Rd, Dallas, TX 75216

AutoCAD SHX Text

KAP

AutoCAD SHX Text

KAP

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 129731

AutoCAD SHX Text

KEITH A. PHARIS

AutoCAD SHX Text 07/12/2021

AutoCAD SHX Text

EP101

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

ELECTRICAL NEW WORK

AutoCAD SHX Text

1. EXISTING VACUUM CIRCUIT BREAKER TYPE MAIN SWITCHGEAR TO REMAIN. REVISE EXISTING GEAR FROM SINGLE BUS MAIN-TIE-SYNCH-TIE-MAIN ARRANGEMENT (SIZED EXISTING VACUUM CIRCUIT BREAKER TYPE MAIN SWITCHGEAR TO REMAIN. REVISE EXISTING GEAR FROM SINGLE BUS MAIN-TIE-SYNCH-TIE-MAIN ARRANGEMENT (SIZED AT 12MW TO SUPPLY 100% FROM EITHER EXISTING ONCOR PRIMARY FEEDER) TO A SPLIT BUS SYSTEM CAPABLE OF BEING FED FROM EITHER DIRECTION WITH NEW SWITCHES ADDED (SEE KEYNOTE #5) FOR TIE INTO NEW SECONDARY GENERATOR SYNCH POWER SOURCE SYSTEM. THE EXISTING UTIL 1, UTIL 2, TIE 1 AND TIE 2 AND EXISTING CHP TURBINE PHYSICAL CONNECTIONS SHALL REMAIN THE SAME. ONCOR SHALL CONTROL WHICH UTILITY SOURCE IS AVAILABLE TO THE VA VIA A SEPARATE ONGOING PROJECT OUTSIDE THE SCOPE OF THIS PROJECT. EXISTING PROTECTIVE RELAYS ARE SCHWEITZER ENGINEERING LAB (SEL), ALL NEW CONTROL SHALL MATCH EXISTING MANUFACTURER. UPON COMPLETION OF PROJECT, CONTROL OF WHICH POWER SOURCE IS BEING USED (i.e. SELECTION OF POWER SOURCE BETWEEN UTIL 1, UTIL 2, GENERATOR SOURCE (IN FUTURE PHASE), WHICH NEW TIE BREKER IS "OPEN" AND WHICH IS "CLOSED", ETC.) SHALL BE CONTROLLED COMPLETE BY VA ENGINEER PER CONTROL SEQUENCE AND DIAGRAMS INCLUDED IN THESE CONSTRUCTION DOCUMENTS). ALL CONTROLS NECESSARY TO GIVE THIS CONTROL TO VA ENGINEER SHALL BE IMPLEMENTED COMPLETE. ALL SAFETY MEASURES NECESSARY SHALL BE INCLUDED. NEW CONTROLS (SEE KEYNOTE #2 SHALL BE IN PLACE TO ALLOW THIS CONTROL). ALL CONTROLS RELATED TO SEQUENCING OF EXISTING GEAR ALONG WITH NEW COMPONENTS SHOWN ON NEW DRAWINGS SHALL BE REVISED COMPLETE TO MEET NEW CONTROL SCHEME. SEE SINGLE LINE DIAGRAM, PHASING NOTES, CONTROL SCHEME NOTES AND LOGIC DIAGRAMS ON EV101 - EV104. 2. EXISTING RTAC CONTROLLERS, ETC. TO REMAIN TO MOST DEGREE. SYNCH PANEL IS SEL REAL TIME AUTOMATION CONTROLLER (RTAC) DESIGNED AND INSTALLED BY THE EXISTING RTAC CONTROLLERS, ETC. TO REMAIN TO MOST DEGREE. SYNCH PANEL IS SEL REAL TIME AUTOMATION CONTROLLER (RTAC) DESIGNED AND INSTALLED BY THE ATRON GROUP. NEW CONTROLLERS, LOGIC, PROGRAMMING, ETC. SHALL BE PROVIDED TO MEET NEW CONTROL SCHEME NECESSARY FOR PERFORMANCE DICTATED AND INDICATED ABOVE AND IN OTHER LOCATIONS IN THIS CD SET. SEE NEW CONTROL SCHEME NOTES/DIAGRAMS, PROGRAMMING INFORMATION, ETC. FOR ADDITIONAL INFORMATION. 3. PROVIDE NEW PULLBOX OVERHEAD ON WALL OR CEILING AND CONNECT AS INDICATED. FOR FUTURE EXPANSI0N/CONNECTION TO FUTURE GENERATOR. SIZE AS REQUIRED PROVIDE NEW PULLBOX OVERHEAD ON WALL OR CEILING AND CONNECT AS INDICATED. FOR FUTURE EXPANSI0N/CONNECTION TO FUTURE GENERATOR. SIZE AS REQUIRED FOR CONDUITS INDICATED AND ANTICIPATED FEEDERS. FIELD COORDINATE EXACT LOCATION WITH EXISTING CONDITIONS, ALL TRADES, ETC. 4. PROVIDE NEW MEDIUM VOLTAGE GEAR LINEUP INDICATED CONNECTED AS INDICATED. SEE SINGLE-LINE DIAGRAM ON DRAWING EG102 FOR FURTHER INFORMATION ON PROVIDE NEW MEDIUM VOLTAGE GEAR LINEUP INDICATED CONNECTED AS INDICATED. SEE SINGLE-LINE DIAGRAM ON DRAWING EG102 FOR FURTHER INFORMATION ON CONNECTIONS (ONE TO EACH OF THE NEW TIE SWITCHES AT MAIN GEAR, AND ONE TO NEW TRANSFORMER FOR SERVICE TO ATS-871CHP) AND ONE STUBBED FOR CONNECTION TO FUTURE GENERATOR. CONTRACTOR SHALL FIELD COORDINATE EXACT LOCATION AND SHALL MOVE/RELOCATE ANY ITEM AS NECESSARY IN ORDER TO PLACE GEAR IN THIS APPROXIMATE LOCATION. MAKE ALL PROVISIONS/ALTERATIONS REQUIRED. 5. PROVIDE 15KV TIE SWITCH TO CONNECT NEW 15KV GEAR LINEUP (SEE KEYNOTE #4) TO EXISTING GEAR LINEUP (SEE KEYNOTE #1). ONE SWITCH TO BE NORMALLY PROVIDE 15KV TIE SWITCH TO CONNECT NEW 15KV GEAR LINEUP (SEE KEYNOTE #4) TO EXISTING GEAR LINEUP (SEE KEYNOTE #1). ONE SWITCH TO BE NORMALLY OPEN, THE OTHER TO BE NORMALLY CLOSED. SEE SEQUENCING NOTES AND LOGIC DIAGRAMS. 6. PROVIDE OIL FILLED TRANSFORMER WITH OIL CONTAINMENT SYSTEM/DIKE. PROVIDE PRIMARY CONNECTION TO "MVMVSE3 SEC G2-3" AND ROUTE SECONDARY CONDUIT TO PROVIDE OIL FILLED TRANSFORMER WITH OIL CONTAINMENT SYSTEM/DIKE. PROVIDE PRIMARY CONNECTION TO "MVMVSE3 SEC G2-3" AND ROUTE SECONDARY CONDUIT TO NEW FUSED DISCONNECT SWITCH "FDSW-G". SEE SINGLE-LINE DIAGRAM ON EG102 FOR ADDITIONAL INFORMATION. SEE APPROXIMATE LAYOUT OF DIKE AND SEE DETAIL OF OIL CONTAINMENT DIKE ON EG201. APPROX SIZE 15'-0"X 7'-0" INSIDE DIMENSIONS, 6" DEEP. MUST BE CONSTRUCTED TO CONTAIN OIL GALLONS IN CASE OF LEAKAGE. FIELD COORDINATE WITH MANUFACTURER. 7. EXISTING ATS-871CHP INCLUDING METERING, CT, INSTRUMENTATION, ETC. SHALL REMAIN. EXISTING ATS-871CHP INCLUDING METERING, CT, INSTRUMENTATION, ETC. SHALL REMAIN. 8. PROVIDE NEUTRAL GROUNDING RESISTOR FOR NEW FUTURE GENERATOR, PROVIDE CONNECTION TO NEUTRAL IN SEC G2-0 IN GENERATOR GEAR LINE-UP AND PROVIDE PROVIDE NEUTRAL GROUNDING RESISTOR FOR NEW FUTURE GENERATOR, PROVIDE CONNECTION TO NEUTRAL IN SEC G2-0 IN GENERATOR GEAR LINE-UP AND PROVIDE GROUNDING CONNECTION POST RESISTOR INTO EXISTING COUNTERPOISE GROUNDING SYSTEM IN BUILDING, ALL WITH 350KCM IN 1-1/2"C. FIELD COORDINATE EXACT CONNECTION POINT WITH VA ENGINEER AND ENGINEER OF RECORD. POINT OF CONNECTION SHOWN FOR REFERENCE ONLY. 9. EXISTING GROUNDING COUNTERPOISE SYSTEM AND BONDING TO STRUCTURE. PROVIDE GROUNDING OF ALL NEW EQUIPMENT AS REQUIRED AND SIZED PER NEC, TYPICAL. EXISTING GROUNDING COUNTERPOISE SYSTEM AND BONDING TO STRUCTURE. PROVIDE GROUNDING OF ALL NEW EQUIPMENT AS REQUIRED AND SIZED PER NEC, TYPICAL. 10. PROVIDE NEW 800A, 480Y/277V, 3 , 4W FUSED DISCONNECT SWITCH. MOUNT TO WALL, COORDINATE EXACT LOCATION WITH EXISTING CONDITIONS. PROVIDE NEW 800A, 480Y/277V, 3 , 4W FUSED DISCONNECT SWITCH. MOUNT TO WALL, COORDINATE EXACT LOCATION WITH EXISTING CONDITIONS.11. PROVIDE A CONCRETE HOUSEKEEPING PAD PER EQUIPMENT MANUFACTURER, STRUCTURAL, SEISMIC STANDARDS TO MEET ALL LOCAL, STATE, AND NATIONAL CODE PROVIDE A CONCRETE HOUSEKEEPING PAD PER EQUIPMENT MANUFACTURER, STRUCTURAL, SEISMIC STANDARDS TO MEET ALL LOCAL, STATE, AND NATIONAL CODE REQUIREMENTS. SEE DETAIL ON DRAWING EG201. 12. PROVIDE CONTROLS CONDUITS AND WIRING PER CONTROLS MANUFACTURER. TERMINATIONS BY CONTROLS VENDOR. FIELD COORDINATE EXACT LOCATIONS WITH CONTROLS PROVIDE CONTROLS CONDUITS AND WIRING PER CONTROLS MANUFACTURER. TERMINATIONS BY CONTROLS VENDOR. FIELD COORDINATE EXACT LOCATIONS WITH CONTROLS VENDOR. SEE CONTROL CIRCUIT SCHEDULE ON EG102. 13. PROVIDE POWER CONDUIT AND FEEDERS PER CABLING SCHEDULE AND SINGLE-LINE DIAGRAM ON EG102. ROUTE CONDUITS OVERHEAD BETWEEN EQUIPMENT. LOCATIONS PROVIDE POWER CONDUIT AND FEEDERS PER CABLING SCHEDULE AND SINGLE-LINE DIAGRAM ON EG102. ROUTE CONDUITS OVERHEAD BETWEEN EQUIPMENT. LOCATIONS SHOWN IS DIAGRAMMATIC. CONTRACTOR SHALL EVALUATE SITE CONDITIONS AND ROUTE AS NECESSARY/REQUIRED DUE TO EXISTING CONDITIONS. SEE POWER FEEDER SCHEDULE ON EG102. 14. STUB CONDUIT UP FROM SECTION TO EXISTING CABLE TRAY. PROVIDE WIRING PER KEYNOTE #12. STUB CONDUIT UP FROM SECTION TO EXISTING CABLE TRAY. PROVIDE WIRING PER KEYNOTE #12. 15. NEW LOCATION FOR FA AND MASS NOTIFICATION DEVICES. RECONNECT TO EXISTING SYSTEMS AS REQUIRED COMPLETE. NEW LOCATION FOR FA AND MASS NOTIFICATION DEVICES. RECONNECT TO EXISTING SYSTEMS AS REQUIRED COMPLETE. 16. PROVIDE NEW PULLBOX OVERHEAD IN PROXIMITY OF ATS AND CONNECT TO NEW FDSW-G PER SINGLE-LINE DIAGRAM. FIELD COORDINATE EXACT LOCATION OF PULLBOX PROVIDE NEW PULLBOX OVERHEAD IN PROXIMITY OF ATS AND CONNECT TO NEW FDSW-G PER SINGLE-LINE DIAGRAM. FIELD COORDINATE EXACT LOCATION OF PULLBOX AND PROVIDE ALL NECESSARY INTERMEDIATE PULL BOXES PER NEC. PROVIDE FEEDER FROM FDSW-G TO PULL BOX WITH 30' OF WIRE LOOPED AT PULL BOX FOR FUTURE CONNECTION TO ATS. 17. ROUTE CAT 6e IN 1"C FROM PM800 TO ETHERNET SWITCH, FIELD COORDINATE EXACT ROUTING AND TERMINATIONS. ROUTE CAT 6e IN 1"C FROM PM800 TO ETHERNET SWITCH, FIELD COORDINATE EXACT ROUTING AND TERMINATIONS.

AutoCAD SHX Text A. SEE DRAWING EG.01 FOR ADDITIONAL GENERAL NOTES. SEE DRAWING EG.01 FOR ADDITIONAL GENERAL NOTES. B. GENERAL SCOPE DEFINITION IS THE REWORK OF EXISTING SWITCHGEAR AND ALL ASSOCIATED CONTROLS, ADDING GEAR SWITCHES AT EACH END OF EXISTING LINE-UP GENERAL SCOPE DEFINITION IS THE REWORK OF EXISTING SWITCHGEAR AND ALL ASSOCIATED CONTROLS, ADDING GEAR SWITCHES AT EACH END OF EXISTING LINE-UP TO ALLOW CONNECTION TO NEW 15KV GEAR LINEUP (SEE ADDITIONAL INFO HERE), NEW 15KV GEAR SWITCHES ARE ADDED AT EITHER END OF EXISTING MAIN SWITCHGEAR TO TIE IN NEW GENERATOR 15KV GEAR. PROVDIE NEW 15KV - 480V PAD MOUNTED TRANSFORMER WITH OIL DIKE, NEW SECONDARY FUSED DISCONNECT AND CONDUIT/FEEDER TO GENERAL LOCATION OF EXISTING ATS-871SHP. NOTE FOR INFORMATION ONLY - FUTURE PROJECT FOR COMPLETION OF THIS INVOLVES REMOVAL NOTE FOR INFORMATION ONLY - FUTURE PROJECT FOR COMPLETION OF THIS INVOLVES REMOVAL - FUTURE PROJECT FOR COMPLETION OF THIS INVOLVES REMOVAL OF EXISTING GENERATOR AND FINAL CONNECTION OF NEW 15KV GEAR VIA TRANSFORMER TO EXISTING ATS-871CHP. FUTURE WORK INVOLVES ADDITION OF FUTURE 2.5 MVA, 15KV GENERATOR CONNECTED TO THIS NEW 15KV GEAR LINEUP IN ORDER TO CONNECT NEW GENERATOR INTO LOOP CONFIGURATION... BUT THIS PORTION IS NOT IN CONTRACT -NIC. C. ALL POWER DISRUPTIONS SHALL BE CLOSELY COORDINATED WITH VA ENGINEER AND SHALL BE SCHEDULED WITH A MINIMUM OF 10 DAYS NOTICE. WORK MAY BE ALL POWER DISRUPTIONS SHALL BE CLOSELY COORDINATED WITH VA ENGINEER AND SHALL BE SCHEDULED WITH A MINIMUM OF 10 DAYS NOTICE. WORK MAY BE REQUIRED DURING OFF HOURS TO MITIGATE DOWN TIME, COORDINATE WITH PHASING NOTES. ALL WORK TO BE CLOSELY COORDINATED WITH THE VA ENGINEERING STAFF, ENGINEER OF RECORD AND VA CAMPUS. D. CONTRACTOR SHALL DEVELOP DETAILED PHASING PLAN NOTING ALL WORK TO MINIMIZE/MITIGATE POWER SHUTDOWNS. SEE ADDITIONAL PHASING NOTES ON THESE CONTRACTOR SHALL DEVELOP DETAILED PHASING PLAN NOTING ALL WORK TO MINIMIZE/MITIGATE POWER SHUTDOWNS. SEE ADDITIONAL PHASING NOTES ON THESE DRAWINGS FOR ADDITIONAL INFORMATION. E. CONDUIT RUNS, CABLE PULLS, ETC. SHALL BE MADE TO "GREATEST EXTENT POSSIBLE" PRIOR TO ANY DEMOLITION TO ENSURE MINIMAL DISRUPTION OF POWER. SEE CONDUIT RUNS, CABLE PULLS, ETC. SHALL BE MADE TO "GREATEST EXTENT POSSIBLE" PRIOR TO ANY DEMOLITION TO ENSURE MINIMAL DISRUPTION OF POWER. SEE NEW WORK PLAN, SINGLE-LINE DIAGRAM AND ALL CONTRACT DOCUMENTS PRIOR TO BEGINNING ANY WORK. F. SEE/REVIEW/COORDINATE FULL SET OF CONSTRUCTION DOCUMENTS (PLANS AND SPECIFICATIONS) IN CONJUNCTION WITH DEMOLITION DRAWING PRIOR TO ANY WORK TO SEE/REVIEW/COORDINATE FULL SET OF CONSTRUCTION DOCUMENTS (PLANS AND SPECIFICATIONS) IN CONJUNCTION WITH DEMOLITION DRAWING PRIOR TO ANY WORK TO ENSURE FULL COMPREHENSION OF OBJECTIVES. G. NOTE: ALL DEVICES/CONDUIT/JUNCTION BOXES, ETC. ARE NOT INDICATED ON DRAWINGS, DEVICES/EQUIPMENT INDICATED ON DRAWINGS ARE FOR CLARIFICATION AND NOTE: ALL DEVICES/CONDUIT/JUNCTION BOXES, ETC. ARE NOT INDICATED ON DRAWINGS, DEVICES/EQUIPMENT INDICATED ON DRAWINGS ARE FOR CLARIFICATION AND INTENT ONLY. CONTRACTOR SHALL FIELD COORDINATE ALL COMPONENTS AND ENSURE OVERALL INTENT IS ACCOMPLISHED COMPLETE FOR BID PRICE SUBMITTED. H. COORDINATE WITH ALL TRADES AND THEIR DOCUMENTS FOR THE DEMOLITION AND RELOCATION EQUIPMENT. PROVIDE ALL LABOR AND MATERIAL WHERE REQUIRED. COORDINATE WITH ALL TRADES AND THEIR DOCUMENTS FOR THE DEMOLITION AND RELOCATION EQUIPMENT. PROVIDE ALL LABOR AND MATERIAL WHERE REQUIRED. I. THE LOCATION OF ALL EXISTING ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, SYSTEMS EQUIPMENT, CIRCUITS, FEEDERS, TERMINATIONS, ETC., AS INDICATED THE LOCATION OF ALL EXISTING ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, SYSTEMS EQUIPMENT, CIRCUITS, FEEDERS, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE EXISTING AND DEMOLITION INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE (COORDINATE ALL VISITS WITH VA ENGINEER) AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE WILL BE ABLE TO COMPLETE ALL WORK COMPLETE REQUIRED FOR THE BID AMOUNT ALL WORK COMPLETE REQUIRED FOR THE BID AMOUNT WORK COMPLETE REQUIRED FOR THE BID AMOUNT COMPLETE REQUIRED FOR THE BID AMOUNT REQUIRED FOR THE BID AMOUNT PROPOSED. J. COORDINATE THE LOCATION OF EXISTING CONDUITS AND JUNCTION BOXES WITH NEW MECHANICAL SYSTEM AND OTHER APPLICABLE SYSTEMS. DEVICES, CONDUITS, COORDINATE THE LOCATION OF EXISTING CONDUITS AND JUNCTION BOXES WITH NEW MECHANICAL SYSTEM AND OTHER APPLICABLE SYSTEMS. DEVICES, CONDUITS, CABLING, SUPPORTS, AND JUNCTION BOXES THAT ARE IN CONFLICT SHALL BE RELOCATED TO BOTTOM OF STRUCTURE ABOVE AS NECESSARY TO ACCOMMODATE ALL NEW CONSTRUCTION, INCLUDING BUT NOT LIMITED TO NEW CEILINGS, MECHANICAL, PLUMBING, NEW CONDUIT ROUTING, AND ELECTRICAL EQUIPMENT AND SYSTEMS. K. THE CONTRACTOR SHALL MAINTAIN THE CONTINUITY OF EXISTING CIRCUITS THAT CONTAIN DEVICES OR EQUIPMENT THAT ARE TO REMAIN. WHERE THE CONTRACTOR SHALL MAINTAIN THE CONTINUITY OF EXISTING CIRCUITS THAT CONTAIN DEVICES OR EQUIPMENT THAT ARE TO REMAIN. WHERE DEMOLITION/RELOCATION OF DEVICES AND EQUIPMENT IS INDICATED, THE CONTRACTOR SHALL ENSURE THAT OTHER DEVICES OR EQUIPMENT THAT ARE CONNECTED TO THE SAME CIRCUIT, WHETHER "UPSTREAM" OR "DOWNSTREAM", SHALL REMAIN OPERATIONAL. UNUSED CIRCUIT BREAKERS SHALL REMAIN AND BE LABELED AS SPARES IN ALL AFFECTED PANELBOARDS. IN ADDITION, PROVIDE NEW TYPEWRITTEN DIRECTORIES IN ALL AFFECTED PANELBOARDS. L. COORDINATE WITH ALL TRADES NOT TO DAMAGE EXISTING CABLES AND WIRING (DESIGNATED TO BE RELOCATED IN NEW CONSTRUCTION) BEING TEMPORARILY COILING COORDINATE WITH ALL TRADES NOT TO DAMAGE EXISTING CABLES AND WIRING (DESIGNATED TO BE RELOCATED IN NEW CONSTRUCTION) BEING TEMPORARILY COILING UP AND STORED ABOVE CEILING. TEST ALL CABLES AND WIRING PRIOR TO DEMOLITION. NOTIFY CONSTRUCTION MANAGER OF ALL CABLES THAT DO NOT OPERATE PER SYSTEMS SPECIFICATIONS. CABLES NOT BEING REUSED SHALL BE REMOVED COMPLETELY. MAINTAIN "UPSTREAM" AND/OR "DOWNSTREAM" CONNECTIONS. M. SEE POWER CABLING FEEDER SCHEDULE AND CONTROL CIRCUIT SCHEDULE ON DRAWING EG102. SEE POWER CABLING FEEDER SCHEDULE AND CONTROL CIRCUIT SCHEDULE ON DRAWING EG102. N. SEE FLOOR PLANS AND SINGLE-LINE DIAGRAMS FOR ADDITIONAL INFORMATION AND COORDINATE BETWEEN THEM. SEE FLOOR PLANS AND SINGLE-LINE DIAGRAMS FOR ADDITIONAL INFORMATION AND COORDINATE BETWEEN THEM. Q. DUE TO COMPLEXITY OF PROJECT. ATTENDANCE OF PRE-BID WALK THROUGH IS MANDATORY - NO EXCEPTIONS. DUE TO COMPLEXITY OF PROJECT. ATTENDANCE OF PRE-BID WALK THROUGH IS MANDATORY - NO EXCEPTIONS. R. ALL NEW CONDUIT RUNS AND PULL BOX LOCATIONS INDICATED ON PLAN ARE DIAGRAMMATIC IN NATURE - CONTRACTOR SHALL FIELD COORDINATE EXACT ROUTING AND ALL NEW CONDUIT RUNS AND PULL BOX LOCATIONS INDICATED ON PLAN ARE DIAGRAMMATIC IN NATURE - CONTRACTOR SHALL FIELD COORDINATE EXACT ROUTING AND LOCATIONS OF CONDUIT RUNS AND PULL BOXES WITH EXISTING CONDITIONS, ALL TRADES, NEW ELECTRICAL, ETC. PROVIDE ALL ADDITIONAL PULL BOXES NECESSARY DUE TO EXISTING CONDITIONS, CONDUIT ROUTING, BENDS, ETC. PER NEC REQUIREMENTS - SIZED PER NEC.

AutoCAD SHX Text A. SEE DRAWING EG.01 FOR ADDITIONAL GENERAL NOTES. SEE DRAWING EG.01 FOR ADDITIONAL GENERAL NOTES. B. GENERAL SCOPE DEFINITION IS THE REWORK OF EXISTING SWITCHGEAR AND ALL ASSOCIATED CONTROLS, ADDING GEAR SWITCHES AT EACH END OF EXISTING LINE-UP GENERAL SCOPE DEFINITION IS THE REWORK OF EXISTING SWITCHGEAR AND ALL ASSOCIATED CONTROLS, ADDING GEAR SWITCHES AT EACH END OF EXISTING LINE-UP TO ALLOW CONNECTION TO NEW 15KV GEAR LINEUP (SEE ADDITIONAL INFO HERE), NEW 15KV GEAR SWITCHES ARE ADDED AT EITHER END OF EXISTING MAIN SWITCHGEAR TO TIE IN NEW GENERATOR 15KV GEAR. PROVDIE NEW 15KV - 480V PAD MOUNTED TRANSFORMER WITH OIL DIKE, NEW SECONDARY FUSED DISCONNECT AND CONDUIT/FEEDER TO GENERAL LOCATION OF EXISTING ATS-871SHP. NOTE FOR INFORMATION ONLY - FUTURE PROJECT FOR COMPLETION OF THIS INVOLVES REMOVAL NOTE FOR INFORMATION ONLY - FUTURE PROJECT FOR COMPLETION OF THIS INVOLVES REMOVAL - FUTURE PROJECT FOR COMPLETION OF THIS INVOLVES REMOVAL OF EXISTING GENERATOR AND FINAL CONNECTION OF NEW 15KV GEAR VIA TRANSFORMER TO EXISTING ATS-871CHP. FUTURE WORK INVOLVES ADDITION OF FUTURE 2.5 MVA, 15KV GENERATOR CONNECTED TO THIS NEW 15KV GEAR LINEUP IN ORDER TO CONNECT NEW GENERATOR INTO LOOP CONFIGURATION... BUT THIS PORTION IS NOT IN CONTRACT -NIC. C. ALL POWER DISRUPTIONS SHALL BE CLOSELY COORDINATED WITH VA ENGINEER AND SHALL BE SCHEDULED WITH A MINIMUM OF 10 DAYS NOTICE. WORK MAY BE ALL POWER DISRUPTIONS SHALL BE CLOSELY COORDINATED WITH VA ENGINEER AND SHALL BE SCHEDULED WITH A MINIMUM OF 10 DAYS NOTICE. WORK MAY BE REQUIRED DURING OFF HOURS TO MITIGATE DOWN TIME, COORDINATE WITH PHASING NOTES. ALL WORK TO BE CLOSELY COORDINATED WITH THE VA ENGINEERING STAFF, ENGINEER OF RECORD AND VA CAMPUS. D. CONTRACTOR SHALL DEVELOP DETAILED PHASING PLAN NOTING ALL WORK TO MINIMIZE/MITIGATE POWER SHUTDOWNS. SEE ADDITIONAL PHASING NOTES ON THESE CONTRACTOR SHALL DEVELOP DETAILED PHASING PLAN NOTING ALL WORK TO MINIMIZE/MITIGATE POWER SHUTDOWNS. SEE ADDITIONAL PHASING NOTES ON THESE DRAWINGS FOR ADDITIONAL INFORMATION. E. CONDUIT RUNS, CABLE PULLS, ETC. SHALL BE MADE TO "GREATEST EXTENT POSSIBLE" PRIOR TO ANY DEMOLITION TO ENSURE MINIMAL DISRUPTION OF POWER. SEE CONDUIT RUNS, CABLE PULLS, ETC. SHALL BE MADE TO "GREATEST EXTENT POSSIBLE" PRIOR TO ANY DEMOLITION TO ENSURE MINIMAL DISRUPTION OF POWER. SEE NEW WORK PLAN, SINGLE-LINE DIAGRAM AND ALL CONTRACT DOCUMENTS PRIOR TO BEGINNING ANY WORK. F. SEE/REVIEW/COORDINATE FULL SET OF CONSTRUCTION DOCUMENTS (PLANS AND SPECIFICATIONS) IN CONJUNCTION WITH DEMOLITION DRAWING PRIOR TO ANY WORK TO SEE/REVIEW/COORDINATE FULL SET OF CONSTRUCTION DOCUMENTS (PLANS AND SPECIFICATIONS) IN CONJUNCTION WITH DEMOLITION DRAWING PRIOR TO ANY WORK TO ENSURE FULL COMPREHENSION OF OBJECTIVES. G. NOTE: ALL DEVICES/CONDUIT/JUNCTION BOXES, ETC. ARE NOT INDICATED ON DRAWINGS, DEVICES/EQUIPMENT INDICATED ON DRAWINGS ARE FOR CLARIFICATION AND NOTE: ALL DEVICES/CONDUIT/JUNCTION BOXES, ETC. ARE NOT INDICATED ON DRAWINGS, DEVICES/EQUIPMENT INDICATED ON DRAWINGS ARE FOR CLARIFICATION AND INTENT ONLY. CONTRACTOR SHALL FIELD COORDINATE ALL COMPONENTS AND ENSURE OVERALL INTENT IS ACCOMPLISHED COMPLETE FOR BID PRICE SUBMITTED. H. COORDINATE WITH ALL TRADES AND THEIR DOCUMENTS FOR THE DEMOLITION AND RELOCATION EQUIPMENT. PROVIDE ALL LABOR AND MATERIAL WHERE REQUIRED. COORDINATE WITH ALL TRADES AND THEIR DOCUMENTS FOR THE DEMOLITION AND RELOCATION EQUIPMENT. PROVIDE ALL LABOR AND MATERIAL WHERE REQUIRED. I. THE LOCATION OF ALL EXISTING ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, SYSTEMS EQUIPMENT, CIRCUITS, FEEDERS, TERMINATIONS, ETC., AS INDICATED THE LOCATION OF ALL EXISTING ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, SYSTEMS EQUIPMENT, CIRCUITS, FEEDERS, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE EXISTING AND DEMOLITION INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE (COORDINATE ALL VISITS WITH VA ENGINEER) AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE WILL BE ABLE TO COMPLETE ALL WORK COMPLETE REQUIRED FOR THE BID AMOUNT ALL WORK COMPLETE REQUIRED FOR THE BID AMOUNT WORK COMPLETE REQUIRED FOR THE BID AMOUNT COMPLETE REQUIRED FOR THE BID AMOUNT REQUIRED FOR THE BID AMOUNT PROPOSED. J. COORDINATE THE LOCATION OF EXISTING CONDUITS AND JUNCTION BOXES WITH NEW MECHANICAL SYSTEM AND OTHER APPLICABLE SYSTEMS. DEVICES, CONDUITS, COORDINATE THE LOCATION OF EXISTING CONDUITS AND JUNCTION BOXES WITH NEW MECHANICAL SYSTEM AND OTHER APPLICABLE SYSTEMS. DEVICES, CONDUITS, CABLING, SUPPORTS, AND JUNCTION BOXES THAT ARE IN CONFLICT SHALL BE RELOCATED TO BOTTOM OF STRUCTURE ABOVE AS NECESSARY TO ACCOMMODATE ALL NEW CONSTRUCTION, INCLUDING BUT NOT LIMITED TO NEW CEILINGS, MECHANICAL, PLUMBING, NEW CONDUIT ROUTING, AND ELECTRICAL EQUIPMENT AND SYSTEMS. K. THE CONTRACTOR SHALL MAINTAIN THE CONTINUITY OF EXISTING CIRCUITS THAT CONTAIN DEVICES OR EQUIPMENT THAT ARE TO REMAIN. WHERE THE CONTRACTOR SHALL MAINTAIN THE CONTINUITY OF EXISTING CIRCUITS THAT CONTAIN DEVICES OR EQUIPMENT THAT ARE TO REMAIN. WHERE DEMOLITION/RELOCATION OF DEVICES AND EQUIPMENT IS INDICATED, THE CONTRACTOR SHALL ENSURE THAT OTHER DEVICES OR EQUIPMENT THAT ARE CONNECTED TO THE SAME CIRCUIT, WHETHER "UPSTREAM" OR "DOWNSTREAM", SHALL REMAIN OPERATIONAL. UNUSED CIRCUIT BREAKERS SHALL REMAIN AND BE LABELED AS SPARES IN ALL AFFECTED PANELBOARDS. IN ADDITION, PROVIDE NEW TYPEWRITTEN DIRECTORIES IN ALL AFFECTED PANELBOARDS. L. COORDINATE WITH ALL TRADES NOT TO DAMAGE EXISTING CABLES AND WIRING (DESIGNATED TO BE RELOCATED IN NEW CONSTRUCTION) BEING TEMPORARILY COILING COORDINATE WITH ALL TRADES NOT TO DAMAGE EXISTING CABLES AND WIRING (DESIGNATED TO BE RELOCATED IN NEW CONSTRUCTION) BEING TEMPORARILY COILING UP AND STORED ABOVE CEILING. TEST ALL CABLES AND WIRING PRIOR TO DEMOLITION. NOTIFY CONSTRUCTION MANAGER OF ALL CABLES THAT DO NOT OPERATE PER SYSTEMS SPECIFICATIONS. CABLES NOT BEING REUSED SHALL BE REMOVED COMPLETELY. MAINTAIN "UPSTREAM" AND/OR "DOWNSTREAM" CONNECTIONS. M. SEE POWER CABLING FEEDER SCHEDULE AND CONTROL CIRCUIT SCHEDULE ON DRAWING EG102. SEE POWER CABLING FEEDER SCHEDULE AND CONTROL CIRCUIT SCHEDULE ON DRAWING EG102. N. SEE FLOOR PLANS AND SINGLE-LINE DIAGRAMS FOR ADDITIONAL INFORMATION AND COORDINATE BETWEEN THEM. SEE FLOOR PLANS AND SINGLE-LINE DIAGRAMS FOR ADDITIONAL INFORMATION AND COORDINATE BETWEEN THEM. Q. DUE TO COMPLEXITY OF PROJECT. ATTENDANCE OF PRE-BID WALK THROUGH IS MANDATORY - NO EXCEPTIONS. DUE TO COMPLEXITY OF PROJECT. ATTENDANCE OF PRE-BID WALK THROUGH IS MANDATORY - NO EXCEPTIONS. R. ALL NEW CONDUIT RUNS AND PULL BOX LOCATIONS INDICATED ON PLAN ARE DIAGRAMMATIC IN NATURE - CONTRACTOR SHALL FIELD COORDINATE EXACT ROUTING AND ALL NEW CONDUIT RUNS AND PULL BOX LOCATIONS INDICATED ON PLAN ARE DIAGRAMMATIC IN NATURE - CONTRACTOR SHALL FIELD COORDINATE EXACT ROUTING AND LOCATIONS OF CONDUIT RUNS AND PULL BOXES WITH EXISTING CONDITIONS, ALL TRADES, NEW ELECTRICAL, ETC. PROVIDE ALL ADDITIONAL PULL BOXES NECESSARY DUE TO EXISTING CONDITIONS, CONDUIT ROUTING, BENDS, ETC. PER NEC REQUIREMENTS - SIZED PER NEC.

File details come from the government source that posted it. Updated .