Answer no. 15 Clarification - 36C25722B0011 Dallas VA MC.pdf

PDF 121 KB Posted

Attached to
Y1DA--549-19-190 Correct Electrical Deficiencies Phase I
Solicitation number
36C25722B0011
Issued by

About this file

This document outlines requirements for a federal contract opportunity to correct electrical deficiencies at a Veterans Affairs medical center in Dallas, Texas. The project scope includes adding electrical utility feeders and switchgear, installing a secondary distribution system for a future generator, and integrating new and existing automation systems to provide seamless system operation. The contractor must provide all labor, materials, equipment, testing, commissioning, permits, as-built drawings and manuals. The performance period is 365 calendar days with a deadline to submit performance and payment bonds within 10 calendar days of notice of award. The contractor must also develop safety, quality control, and infection control plans meeting specified criteria and timelines.

View the file

Other files

File Type Posted
Provision 52.211-6 Brand Name or Equal.pdf PDF
36C25722B0011 0008.docx DOCX document
SELF-PERFORMED CALCULATIONS.pdf PDF
OSHA - EMR requirement.pdf PDF
36C25722B0011 0007.docx DOCX document
36C25722B0011 0006.docx DOCX document
Answer no. 15 Clarification - 36C25722B0011 Dallas VAMC RFI Questions.pdf PDF
36C25722B0011 0005.docx DOCX document
Answers to RFIs-Questions 36C25722B0011 Dallas VAMC.pdf PDF
36C25722B0011 0004.docx DOCX document
36C25722B0011 0003.docx DOCX document
Pre-Bid Site Visit Sign in 01-19-2022.pdf PDF
Site Visit Sign in 01-25-2022.pdf PDF
36C25722B0011 0002.docx DOCX document
36C25722B0011 0001.docx DOCX document
549-19-190 Dallas Correct Elec Deficiencies 15July2021.pdf PDF
261316 MEDIUM-VOLTAGE FUSIBLE INTERRUPTER SWITCHES.pdf PDF
As Built 87.pdf PDF
Specs Combined 07-15-2021.pdf PDF
36C25722B0011_1.docx DOCX document
As Built EP101.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25722B0011 Dallas TX VA MC Correct Electrical Deficiencies

RFI Answer Clarification

15) Situation: Type of switchgear is not identified on drawings to know section to quote

Request for Clarification: Can a plate name be provided for switchgear or photos in order to get to proper quote for breakers and additional switchgear section?

Answer: Atron will supply all switchgear, transformers, relays prewired to match existing function precisely to contractor awarded this contract

Clarification: The custom electrical switchgear for this project shall be acquired by contractor from Atron to assure that it will integrate with the existing custom switchgear. Atron (formally Standard Control) was the provider of the original automation controls off the electrical switchgear being altered under this project.

This process will assure that the end product will provide a known quality and quantity when commissioned in an active major medical center.

3/2/2022 - Answer from A/E: We can simply clarify that the equipment indicated is “basis of design” and the contractor can select equivalent insomuch as it meets or exceeds the basis of design equipment indicated. This satisfies the acquisition requirements while giving the contractor the specific equipment needs for comparison. All equivalent items submitted will be reviewed for conformance through the submittal process if this goes to construction and will need to be compatible with the existing and system as a whole.