This is a Unit Pricing Form from the Colorado Office of the State Architect's State Buildings Program for the Auraria Higher Education Center (AHEC), Project No. 2020-55P21, which involves HVAC Infrastructure Replacement and Asbestos Abatement for Central Classroom (Project A) and West Classroom (Project B). The form establishes unit prices for various asbestos abatement work items that will be used to adjust the contract sum when changes to the work are deemed necessary. The seven unit pricing line items include non-friable asbestos-containing window caulking (measured in linear feet), non-friable asbestos-containing window glazing (linear feet), non-friable trace asbestos-containing drywall system (square feet), construction of a 5' X 5' secondary containment structure (each), and labor categories including asbestos abatement workers (hourly rate), asbestos abatement supervisors (hourly rate), and project managers (hourly rate). Unit prices shall remain valid until the contract completion date specified in the Notice to Proceed.
The unit prices provided by the bidder shall include the pro-rata share of all material, equipment, and disposal costs required to complete each work item. Overhead, profit, and bond costs will be calculated separately on a Change Order Proposal Form (SC-6.312). The form requires the bidder company name, signature, and date to be completed as part of the submission process. All unit prices are subject to the conditions and requirements outlined in the State Buildings Program contract documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAM
UNIT PRICING FORM
Institution or Agency: Auraria Higher Education Center Project No./Project Name: 2020-55P21 / AHEC HVAC Infrastructure Replacement (Capital Renewal) – Asbestos Abatement for Central Classroom (Project A) and West Classroom (Project B)
INSTRUCTIONS:
The unit prices below shall be used to determine adjustment to the contract sum when changes in the work involving said items are deemed necessary.
Unit Prices shall apply until the date of contract completion established on the Notice to Proceed.
All unit prices shall include the pro-rata share of all costs of materials, equipment and disposal required to complete the work item. Overhead, profit and bond will be calculated on a Change Order Proposal (SC-6.312).
UNIT PRICING
| Number |
| Description |
Unit of Measure
Unit Price
| U1 |
| Non-friable asbestos containing window caulking |
| LF |
| $ |
| U2 |
| Non-friable asbestos containing window glazing |
| LF |
| $ |
| U3 |
| Non-friable trace asbestos containing drywall system |
SF
| U4 |
| Construct one (1) 5’ X 5’ Secondary Containment |
| EA |
| $ |
| U5 |
| Asbestos Abatement Worker |
| HR |
| $ |
| U6 |
| Asbestos Abatement Supervisor |
| HR |
| $ |
| U7 |
| Project Manager |
| HR |
| $ |
THE BIDDER
BY_________________________________________________________________
Company Name
BY__________________________________________________________________
Signature Date
SBP-6.133