Appendix B - QASP.pdf
PDF 130 KB Posted
- Attached to
- Industrial Plant Equipment Maintenance Program
- Solicitation number
- N42158-22-R-S007-DRAFT
About this file
This document contains a Quality Assurance Surveillance Plan (QASP) for an industrial plant equipment maintenance program. The QASP outlines twelve maintenance and reporting tasks to be performed by the contractor, along with performance standards and acceptable quality levels for each task. Key tasks include annual preventive maintenance, certification and calibration testing, corrective maintenance response within allotted timeframes, on-the-job training for maintenance personnel, and provision of consumables and maintenance reports. The QASP specifies surveillance methods for each task to be used by the Contracting Officer's Representative, and defines acceptable performance as satisfactory or unsatisfactory. A deliverables schedule outlines nine contract data requirement lists with frequency of submission and copies required for items such as service reports, maintenance reports, certification reports, quality plans and inspections, and completion certificates.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N42158-22-R-S007-DRAFT.pdf | ||
| APPENDIX A.pdf | ||
| CDRL A008.pdf | ||
| CDRL A002.pdf | ||
| CDRL A001.pdf | ||
| CDRL A004.pdf | ||
| Exhibit 1 Past Performance Information Form.pdf | ||
| APPENDIX A.pdf | ||
| Attachment 2 - Wage Determination.pdf | ||
| Attachment 1 - Pricing Sheet.xlsx | XLSX spreadsheet | |
| CDRL A003.pdf | ||
| Exhibit 2 Past Performance Questionnaire.pdf | ||
| N4215822RS007 IPE Draft Solicitation.docx | DOCX document | |
| CDRL A007.pdf | ||
| CDRL A006.pdf | ||
| CDRL A009.pdf | ||
| CDRL A005.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Appendix B Quality Assurance Surveillance Plan (QASP)
This Quality Assurance Surveillance Plan (QASP) includes performance standards. The Government will use these standards to determine contractor performance and shall complete contractor performance to the Acceptable Quality
Level (AQL). The COR will use this document to rate contractor. Rating will be either SAT or UNSAT. Any USAT rating will be explained in the notes block.
PWS
Paragraph
Task
Performance Standard Acceptable Quality
Levels (AQL)
Surveillance
Method /
By Whom
Performance
Rating
Sat / Unsat
8.
The contractor shall perform annual
Preventive
Maintenance (PM) on all machines listed in
Appendix A.
The contractor shall coordinate arrival with COR and perform
PM successfully.
0 (zero) failures to respond to the agreed upon arrival date or perform successful PM.
100% Inspection
– COR will inspect.
9.
The contractor shall perform a
Certification and
Calibration test on all machines listed in
Appendix A.
The contractor shall coordinate arrival with COR and perform
Certification and Calibration test successfully.
0 (zero) failures to respond to agreed-upon arrival date or perform successful comprehensive calibration test.
100% Inspection
10.
perform corrective maintenance repair response.
The contractor shall respond to phone call within allotted time and perform maintenance successfully.
1 failure to respond in allotted time or perform maintenance successfully
Periodic
Inspection – COR will review
11.
provide on-the-job maintenance training.
The contractor shall provide on-the-job maintenance training to
NNSY maintenance personnel.
0 (zero) failures to supply training.
Periodic
Inspection – COR will review
12. The contractor shall provide consumables.
The contractor shall provide maintenance consumables for all relevant equipment on an as-needed basis as part of preventive and corrective maintenance.
0 (zero) failures to supply consumables.
100% Inspection
16. The contractor shall provide reports.
The contractor shall provide COR with maintenance report within 10 days of completion of maintenance.
0 (zero) failures to supply report within 10 days.
100% Inspection
Notes:
Deliverables Schedule
Deliverable Frequency Copies Medium/Format Submit To
5.1. Kick-Off
Meeting Minutes
(CDRL A001)
Within 10 calendar days after kick-off meeting
As specified/
Electronic
COR
5.2.1.2. and
5.2.2.3 Service
Reports
(CDRL A002)
Within 7 calendar days after event and weekly thereafter
As specified/
Electronic
COR
16.1.
PM Service
Report
(CDRL A003)
Within 10 calendar days after each PM and yearly thereafter
As specified/
Electronic
COR
8.6. Change of
PM
(CDRL A004)
Within 5 days after event 2 As specified/
Electronic
COR
16.2.
Certification and
Calibration
Report
(CDRL A005)
Within 30 calendar days after each Certification and Calibration and yearly thereafter
As specified/
Electronic
COR
16.3.
Corrective
Maintenance
Repair Report
(CDRL A006)
Within 10 calendar days after each CM Repair
As specified/
Electronic
COR
17.2.
Quality
Management
Plan
(CDRL A007)
Within 60 calendar days after award and within 7 calendar days of any changes and yearly thereafter
As specified/
Electronic
COR
17.4.
Quality
Inspection and
Surveillance
Report
(CDRL A008)
Within 30 calendar days of each
Quality Inspection and
Surveillance and monthly thereafter
As specified/
Electronic
COR
17.5.1.
Certificate of
Completion
(COC)
(CDRL A009)
After each PM and CM service 2 As specified/
Electronic
COR