This is a PowerPoint slide showing a notional schedule/roadmap for the deployment of NextGen PPS (Procurement Planning System) and BFM (Business Financial Management) 4.0 systems.

The timeline indicates a target deployment date of October 1, 2027, contingent upon SAP delivering a fully operational NextGen PPS product by October 2025 and BFM 4.0 product by October 2026. The schedule outlines several key phases including data archiving, ECC (SAP ERP Central Component) to S/4 conversion, integration testing, regression testing, UAT (User Acceptance Testing), and production execution. Notable milestones include an IBP (Integrated Business Planning) go-live in February 2026, SRM (Supplier Relationship Management) retrofit implementation, and incremental deployment of BPRs (Business Process Re-engineering) to S/4. The roadmap also includes multiple testing cycles and hypercare periods for both PPS and BFM implementations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Next Gen PPS & BFM 4.0 Notional Schedule

Summary Next Gen PPS & BFM 4.0 Notional Schedule:

Notional plan to deploy NextGen PPS and BFM 4.0 by October 1, 2027 This assumes SAP provides a fully operational NextGen PPS product by October 2025 and BFM 4.0 product by October 2026. This is based on the current known product release dates provided by the SAP product teams.

Warfighter Always

PEOPLE PRECISION POSTURE PARTNERSHIPS

S/ Migration Schedule Go Live Feb’ 2026

CVI

IBP (Energy Planning) Data Archiving Go Live IBP Go Live ECC, CRM, SRM ECC to S/4 Conversion Integration Testing Regression Test and UAT S4 Go Live

Production Execution SRM Retrofit

Go Live in Production

SAP Product Release HP and Regression testing impacts NextGen PPS

BFM 4.0

S/4 Test Env.

PPS Pilot Fit /Gap Analysis Pre-Conversion S/4 Execution & PPS Execution DMLT - Mock Testing

Cycle 1 Cycle 2

PROD

Incrementally deploy BPRs to S/4 Next Gen PPS Design, Build, Test PPS Go Live

Hypercare

Cycle 5

BFM 3.0 Retrofit

Cycle

Hypercare BPR Development

Human Performance Cycle As of November 12, 2024

Warfighter Always

PEOPLE PRECISION POSTURE PARTNERSHIPS

image11.png image1.jpeg image2.png image3.png image4.png image5.jpeg image6.png image7.png image9.png image10.png

File details come from the government source that posted it. Updated .