Appendix_6_-_UWS.pdf

PDF 2 MB Posted

Attached to
Guardrail along Keystone Road
Solicitation number
23-0114-ITB-CONSTRUCTION
Issued by
Pinellas County, Clewiston City, Florida

About this file

The document is a Utility Work Schedule (UWS) for Pinellas County, Florida, involving multiple utility agencies including Clearwater Gas System, Frontier, Charter, and Uniti Fiber/Southern Light for a proposed guardrail area project. The project is located on the south side of Keystone Road from E. Lake Road to the Pinellas/Hillsborough County Line (County Project #: 111495A), and involves utility work coordination for guardrail installation. Each utility agency has submitted a detailed work schedule outlining their non-construction items, estimated calendar days, construction items, and specific work activities related to protecting, adjusting, or relocating their utility infrastructure during the guardrail project.

The utility work schedules indicate minimal to no disruption for most utility services, with most agencies requiring only 1-2 days of work during the project construction phase. Special conditions and constraints for each utility agency include standard requirements such as maintaining normal business hours (typically 8am-5pm, Monday-Friday), providing 48-72 hours advance notice for any work outside normal hours, ensuring extreme caution when excavating near facilities, and maintaining access to monitor and maintain their infrastructure. The documents are dated between 10/15/2019 and 4/4/2022, with acceptance dates in early 2022, suggesting the project was planned over several years and prepared for implementation.

View the file

Other files

File Type Posted
Guardrail_along_Keystone_Road.pdf PDF
Appendix_1-Permits.pdf PDF
Section_E_-_Specifications.pdf PDF
Plans.pdf PDF
Section_I_-_Agreement.pdf PDF
Topographic_Survey.pdf PDF
Invitation_to_Bid_(ITB).pdf PDF
Section_F_-_Bid_Submittal_Sheet-protected.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

4/1/2022 aelvambuena Typewriter 3/30/22

Page 2 of 3 PINELLAS COUNTY 11/19//2019

UTILITY WORK SCHEDULE

COUNTY PROJECT #: 111495A PROJECT TITLE: Proposed Guardrail Area, South Side of Keystone Road to E. Lake Road to Pinellas/Hillsborough County Line

UTILITY AGENCY/OWNER (UAO): Clearwater Gas System

B. Special Conditions / Constraints

1. Contact CGS Maintanance Supervisor, Allen Tucker (727) 224 7434, one week before Guardrail Installation at (Sta. 272+70, 22.7 RT).

2. For emergencies, please contact the 24 hour emergency hotline at 727-462-6633.

Page 3 of 3 PINELLAS COUNTY 11/19//2019

COUNTY PROJECT #: 111495A PROJECT TITLE: Proposed Guardrail Area, South Side of Keystone Road to E. Lake Road to Pinellas/Hillsborough County Line

UTILITY AGENCY/OWNER (UAO): Clearwater Gas System

SECTION C: UAO’s WORK ACTIVITIES

Action

Utility Facility (Type, Size, Material, Status)

From Station/ Offset

To Station/ Offset

Utility Work Description Dependent Activity TCP Phase

Consecutive Days

Prior To During

1 4” HDPE Natural Gas Main

Sta.

272+70,

22.7 RT

Sta.

272+70,

22.7 RT

To be protected/adjusted if needed Guardrail Installation N/A N/A 2

2 All remaining Gas Lines

N/A N/A To Remain N/A N/A N/A N/A

Page 1 of 3 PINELLAS COUNTY 10/15//2019

COUNTY PROJECT #: 000195A

PROJECT TITLE #: Proposed Guardrail Area South Side of Keystone Rd from E. Lake Rd to Pinellas/Hillsborough County Line

UTILITY AGENCY/OWNER (UAO): Frontier

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS

ESTIMATED *CALENDAR

DAYS

CONSTRUCTION ITEMS

ESTIMATED *CALENDAR

DAYS

Total Preliminary 15 Prior to Pinellas County Project Construction

Total Material Procurement 30 During Pinellas County Project Construction 24

Total Right-of-Way Permitting

Total NON-Construction Time 45 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.

The following data is based on Pinellas County final design phase construction plans dated . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: Rick Stratton Telephone Number: 727-204-3158

UAO Field Representative: Christopher Blauvelt Telephone Number: 727-313-6235

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

(Signature) (Signature) (Signature)

Rick Stratton

(Printed Name) (Printed Name) (Printed Name)

Sr. Network Engineer

(Title) (Title) (Title)

2/28/2022

(Date) (Date) (Date)

Tim Messina

Utilities Coordinator rss051 Typewriter Rick Stratton aelvambuena Typewriter Ariel Elvambuena aelvambuena Typewriter Engineer of Record aelvambuena

Page 2 of 3 PINELLAS COUNTY 10/15//2019

COUNTY PROJECT #: 000195A

PROJECT TITLE #: Proposed Guardrail Area South Side of Keystone Rd from E. Lake Rd

B. Special Conditions / Constraints

1) Frontier and Frontier Contractors' normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).

2) Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.

3) The Road Contractor is to notify Frontier at 813-952-8819 48 hours prior to start of construction and when working within 2' of Frontier facilities.

4) Extreme caution is to be used when excavating near or around Frontier facilities.

5) Frontier is to have access throughout the duration of the project to monitor and maintain facilities for the ability to provide service.

6) The Frontier Inspector (813-952-8819) is to be the point of contact during construction and is to notified when working within 2' of Frontier facilities.

7) Frontier requests a copy of the Road Contractors CPM Schedule when available.

8) Frontier requests for the Road Contractor to provide staking with elevations prior to Frontier adjustment activities.

9) Work order preperation to begin after reciept of executed URS and Right of Way Acquisition to completed prior to Frontier's relocation effort.

10) All Frontier Facilities in green form Sta 259+00 to Sta 407+40 on Ketstone Road are to remain.

11) Frontier will need the guardrail running line staked out between station# 307+60 to 316+75 so Frontier can determine which post will be in conflict with the Frontier cables.

Page 3 of 3 PINELLAS COUNTY 10/15//2019

COUNTY PROJECT #: 000195A

PROJECT TITLE #: Proposed Guardrail Area South Side of Keystone Rd from E. Lake Rd

SECTION C: UAO’s WORK ACTIVITIES

Action

Utility Facility

(Type, Size, Material, Status)

From

Station/

Offset

To

Station/

Offset

Utility Work Description Dependent Activity

TCP

Phase

Consecutive

Days

Prior

To During

1 FTR BT

275+89, 17’ RT

275+89, 30’ RT

HOLD, GUARD AND PROTECT DURING CONSTRCUTION OF

GUARD RAIL

PLACEMENT OF GUARD RAIL N/A 1

2 FTR 4-BT

282+00, 34’ RT

283+75, 35’ TO 37’

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL

N/A

3 FTR 2-BT

284+30, 40’ RT

284+50, 41’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL

N/A

4 FTR BT

289+02, 36’ RT

289+57, 32’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL

N/A

5 FTR BT

291+01

32’ RT

291+60, 31’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL

N/A

6 FTR BT

307+58, 23’ RT

316+72, 24’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL N/A

7 FTR BT

321+30, 24’ RT

325+42, 24’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL N/A

8 FTR BT

325+65, 23’ RT

327+67, 22’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL N/A

FTR BT 328+63,

22’ RT

330+17, 22’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL N/A

FTR BT 330+43,

21’ RT

338+43, 23’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL N/A

FTR BT 347+77,

22’ RT

351+07, 21’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL N/A

FTR BT 351+61,

22’ RT

352+50, 26’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL N/A

FTR BT 354+70,

26’ RT

358+80, 21’ RT

ADJUST OR REMOVE & REPLACE AS NEEDED DURING

CONSTRCUTION OF GUARD RAIL

PLACEMENT OF GUARD RAIL N/A

4/4/2022

3-30-22

CGS UWS-Pinellas-County-Template Keystone Guardrail Clearwater Gas
During Pinellas County Project Construction
Special Conditions / Constraints
FTR UWS-Pinellas-County-Keystone Guardrail Placement
Spectrum #3465244_FR FDOT Keystone Guardrail_UWS Charter
Uniti F000195A Pinellas Keystone Rd Guardrail Uniti Fiber - SL UWS_Signed

File details come from the government source that posted it. Updated .