This document is Amendment #4 to Request for Proposals (RFP) #32122-2024-001 issued by the State of Tennessee Department of General Services, Megasite Authority of West Tennessee for Potable Water Treatment Plant (WTP), Wastewater (WWTP) Management, Force Main & Pump Station, Operation, and Maintenance Services. The RFP schedule has been updated, confirming dates for key events such as the mandatory pre-response conference, written questions and comments deadlines, response deadline, oral presentations, cost proposal opening, negotiations, and contract award. The revised schedule extends the overall RFP process from January 23, 2024 to May 13, 2024.

The pricing terms, set-asides, incumbent information, funding requirements, and other salient commercial details are not provided in this amendment. The amendment focuses solely on updating the RFP schedule of events.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

09-20-18 RFP-AMEND

RFP # 32122-2024-001 – Amendment # 4 Page 1 of 2

STATE OF TENNESSEE

DEPARTMENT OF GENERAL SERVICES, MEGASITE AUTHORITY OF WEST

TENNESSEE

REQUEST FOR PROPOSALS # 32122-2024-001

AMENDMENT # 4

FOR Potable Water Treatment Plant (WTP), Wastewater (WWTP) Management, Force Main & Pump Station, Operation, and Maintenance Services for the Megasite Authority of West Tennessee

DATE: APRIL 23, 2024

RFP # 32122-2024-001 IS AMENDED AS FOLLOWS:

1. This RFP Schedule of Events updates and confirms scheduled RFP dates. Any event, time, or date containing revised or new text is highlighted.

EVENT

TIME

(central time zone)

DATE

1. RFP Issued January 23, 2024

2. Disability Accommodation Request Deadline 2:00 p.m. January 26, 2024

3. Mandatory Pre-response Conference 9:00 a.m. January 31, 2024

4. Notice of Intent to Respond Deadline 2:00 p.m. February 2, 2024

5. Written “Questions & Comments” Deadline 2:00 p.m. February 8, 2024

6. State Response to Written “Questions & Comments” February 23, 2024

7. Written “Questions & Comments” Deadline – ROUND 2 2:00 p.m. March 1, 2024

8. State Response to Written “Questions & Comments” – ROUND 2 March 6, 2024

9. Response Deadline 2:00 p.m. March 22, 2024

10. State Completion of Technical Response Evaluations (Sections B. and C., RFP Attachment 6.2) April 5, 2024

11. State Schedules Oral Presentations April 8, 2024

12. Respondent Oral Presentations April 16, 2024, through April 17, 2024

13. State Completion of Technical Response Evaluations (Section D., RFP Attachment 6.2.) April 18, 2024

14. State Opening & Scoring of Cost Proposals 2:00 p.m. April 19, 2024

15. Negotiations April 22, 2024

09-20-18 RFP-AMEND

RFP # 32122-2024-001 – Amendment # 4 Page 2 of 2

16. State Notice of Intent to Award Released and RFP Files Opened for Public Inspection 2:00 p.m. April 23, 2024

17. End of Open File Period April 30, 2024

18. State sends contract to Contractor for signature May 2, 2024

19. Contractor Signature Deadline 2:00 p.m. May 13, 2024

20. Performance Bond Deadline 4:30 p.m. May 13, 2024

2. RFP Amendment Effective Date. The revisions set forth herein shall be effective upon release. All other terms and conditions of this RFP not expressly amended herein shall remain in full force and ef fect.