About this file

This document is a Questions and Answers Log for Solicitation #140A1124B0004 related to the White Mtn Detention Center Interior Pod Repairs contract opportunity. The key details are:

The contractor, Praire Band Construction, submitted several questions about the contract, including requests for building plans and square footage information, hazardous material surveys, facility access and security procedures, and material staging and debris removal processes. The agency provided responses to these questions, indicating that some additional details would be provided. The contract opportunity, Solicitation #140A1124B0006 for the "WHITE MTN APACHE ADULT DET. POD COMPL." project, is for interior finishes work at the White Mtn Apache Adult Detention Center, issued by the Department of the Interior Bureau of Indian Affairs Western Region.

View the file

Other files for this federal contract opportunity

Other files attached to WHITE MTN APACHE ADULT DET. POD COMPL., newest first.
File Type Posted
B09__-_Questions_and_Answers_Log_-_IEE_-_08-16-2024_0002.pdf PDF
Sol_140A1124B0006_Amd_0002.pdf PDF
Sol_140A1124B0006_Amd_0001.pdf PDF
SOW_White_Mountain_Detention_Pod_Competion_-_5_23_24.pdf PDF
Amendment_1_-_Questions_and_Answers_Log__7-15-2024.xlsx XLSX spreadsheet
Amendment_2_-_Questions_and_Answers_Log_7_16_24_part_1.xlsx XLSX spreadsheet
Sol_140A1124B0006.pdf PDF
Amendemnt_1_-_2019_Plans_Detention.pdf PDF
Amendment_3_-_2019_Plans_Detention_Page_7_-_7_19_24.pdf PDF
B03_-_DOL_Wage_Determination_-_IEE.pdf PDF
B09__-_Questions_and_Answers_Log_-_IEE.xlsx XLSX spreadsheet
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Questions and Answers Log for Solicitation #140A1124B0004 - White Mtn Detention Center - Interior Pod Repairs

NumberDate ReceivedContractorQuestionDate Sent to CSAnswerDate Answered
1Praire Band ConstructionThe documents only indicate the square footage of the entire building rather than the two pod areas. Can building plans be provided? And/or the SF of the E & F pod area provided?
2Praire Band ConstructionWill the government provide information regarding hazardous survey for asbestos and/or lead?
3Praire Band ConstructionWhat is the in/out of the facility procedure and time commitment everyday? ie tool bages with nails/screws, etc.
4Praire Band ConstructionWhat is the government escort protcol? Is an escort required at all times ie. Restroom? Are restrooms on the otherside of the security door? Etc.
5Praire Band ConstructionWhat is the procedure for bringing materials and/or debris each day? Will the construction team and belongings be searched each time they leave the building? Will there be space to stage materials in the pod area?
6
7
8
9
10