About this file
This is Amendment 1 to a solicitation issued by the Medical University of South Carolina (MUSC) for chiller maintenance and repair services. The solicitation requests comprehensive maintenance and repair services for multiple water-cooled chillers and associated equipment, including units without variable frequency drives (VFDs) at various facilities (MRE #5 Trane, IOP #1 York, RT #3 Trane, and QF 1&2 Trane). A non-mandatory pre-proposal conference and site visit will be held on March 21, 2024, at 10:00 AM at 97 Jonathan Lucas, Conference PG 203A, Charleston, SC 29425. Questions from offerors must be received by March 21, 2024, at 4:00 PM EST. Offers must be submitted electronically by April 22, 2024, at 11:00 AM EST, with award posting scheduled for May 10, 2024. Offerors must submit one electronic technical proposal, one electronic business proposal, and redacted copies of both documents marked as "Redacted" unless otherwise exempted. The offer must remain open for a minimum of 60 calendar days after the opening date.
The amendment addresses six questions and answers clarifying contract requirements, including that MUSC does not currently possess a recent chiller condition report, that VFD maintenance must be performed by OEM-certified personnel specific to the manufacturer's equipment, and that tube brushing and eddy current services are required as part of the base contract scope with separate pricing required. Additionally, contractors must perform refrigerant monitor alarm tests according to manufacturer recommendations and government regulations, and calibrate all refrigerant monitors annually per OEM standards. Offerors must acknowledge receipt of amendments by signing and returning the amendment, identifying the amendment number and date on page two of the solicitation, or submitting a bid indicating receipt. Submissions should be made through the South Carolina procurement website at www.procurement.sc.gov, with all procurement and contract-related notices directed to Andy Champion, the procurement officer, at champiow@musc.edu or 843-792-1300.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NRA.pdf | ||
| RFP.pdf | ||
| Attachment A.xlsx | XLSX spreadsheet | |
| Attachment B.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAP
SAP
State of South Carolina
Amendment 1 (Only items highlighted or Q&A are subject to additional questions)
Solicitation:
Date Issued:
Procurement Officer:
Phone:
E-Mail Address:
Mailing Address:
5400026445 04/03/2024 Andy Champion 843-792-1300 champiow@musc.edu University Procurement 1 South Park Plaza, JB402 Charleston SC 29407
DESCRIPTION: CHILLER MAINTENANCE AND REPAIR
USING GOVERNMENTAL UNIT: Medical University of South Carolina
SUBMIT YOUR OFFER ON-LINE AT THE FOLLOWING URL: http://www.procurement.sc.gov SUBMIT OFFER BY (Opening Date/Time): 04/16/2024 04/22/2024 at 11:00 AM EST (See "Deadline For Submission Of Offer" provision) QUESTIONS MUST BE RECEIVED BY: 03/21/2024 at 4:00 PM EST (See "Questions From Offerors" provision) NUMBER OF COPIES TO BE SUBMITTED: One (1) Electronic Technical Proposal, One (1) Electronic Business Proposal, One (1) Electronic Redacted Copy of Technical Proposal marked "Redacted", One (1) Electronic Redacted Copy of Business Proposal marked "Redacted", (See “DISCLOSURE OF YOUR BID / PROPOSAL and SUBMITTING CONFIDENTIAL DATA” Section II.A.)
Initial here if NO redacted copy is necessary___________ CONFERENCE TYPE:Non-Mandatory Pre-Proposal Conference* DATE & TIME: 03/21/2024 at 10:00 am.
*Site Visit immediately after conference (As appropriate, see "Conferences - Pre- Bid/Proposal" & "Site Visit" provisions)
LOCATION:
97 Jonathan Lucas Conference PG 203A Charleston SC, 29425
AWARD &
AMENDMENTS
Award will be posted on 05/10/2024. The award, this solicitation, any amendments, and any related notices will be posted at the following web address: http://www.procurement.sc.gov
You must submit a signed copy of this form with Your Offer. By signing, You agree to be bound by the terms of the Solicitation. You agree to hold Your Offer open for a minimum of sixty (60) calendar days after the Opening Date. (See "Signing Your Offer" provision.)
NAME OF OFFEROR
(full legal name of business submitting the offer)
Any award issued will be issued to, and the contract will be formed with, the entity identified as the Offeror. The entity named as the offeror must be a single and distinct legal entity. Do not use the name of a branch office or a division of a larger entity if the branch or division is not a separate legal entity, i.e., a separate corporation, partnership, sole proprietorship, etc.
AUTHORIZED SIGNATURE
(Person must be authorized to submit binding offer to contract on behalf of Offeror.)
DATE SIGNED
TITLE
(business title of person signing above)
STATE VENDOR NO.
(Register to Obtain S.C. Vendor No. at www.procurement.sc.gov)
PRINTED NAME
(printed name of person signing above)
STATE OF INCORPORATION
(If you are a corporation, identify the state of incorporation.)
OFFEROR'S TYPE OF ENTITY: (Check one) (See "Signing Your Offer" provision.)
___ Sole Proprietorship ___ Partnership ___ Other_____________________________
___ Corporate entity (not tax-exempt) ___ Corporation (tax-exempt) ___ Government entity (federal, state, or local)
COVER PAGE - PAPER ONLY (MAR. 2015)
mailto:champiow@musc.edu http://www.procurement.sc.gov/ http://www.procurement.sc.gov/
PAGE TWO
(Return Page Two with Your Offer) HOME OFFICE ADDRESS (Address for offeror's home office / principal place of business)
NOTICE ADDRESS (Address to which all procurement and contract related notices should be sent.) (See "Notice" clause)
_________________________________________________ Area Code - Number - Extension Facsimile
_________________________________________________ E-mail Address
PAYMENT ADDRESS (Address to which payments will be sent.)
(See "Payment" clause)
____Payment Address same as Home Office Address ____Payment Address same as Notice Address (check only one)
ORDER ADDRESS (Address to which purchase orders will be sent) (See "Purchase Orders and "Contract Documents" clauses)
____Order Address same as Home Office Address ____Order Address same as Notice Address (check only one)
ACKNOWLEDGMENT OF AMENDMENTS
Offerors acknowledges receipt of amendments by indicating amendment number and its date of issue. (See "Amendments to Solicitation" Provision) Amendment No. Amendment Issue
Date Amendment No. Amendment Issue
Date Amendment No. Amendment Issue
Date Amendment No. Amendment Issue
Date
DISCOUNT FOR
PROMPT PAYMENT
(See "Discount for Prompt
Payment" clause)
10 Calendar Days (%) 20 Calendar Days (%) 30 Calendar Days (%) _____Calendar Days (%)
PREFERENCES - A NOTICE TO VENDORS (SEP. 2009): Preferences do not apply to Request for Proposals per SC Consolidated Procurement Code Section 11-35-1524(5)
PREFERENCES - ADDRESS AND PHONE OF IN-STATE OFFICE: Preferences do not apply to Request for Proposals per SC Consolidated Procurement Code Section 11-35-1524(5)
PAGE TWO (SEP 2009) End of PAGE TWO
AMENDMENTS TO SOLICITATION (JAN 2004):
the solicitation may be amended at any time prior to opening. All actual and prospective Offerors should monitor the following web site for the issuance of amendments: www.procurement.sc.gov(b) Offerors shall acknowledge receipt of any amendment to this solicitation (1) by signing and returning the amendment, (2) by identifying the amendment number and date in the space provided for this purpose on page two, (3) by letter, or (4) by submitting a bid that indicates in some way that the bidder received the amendment. (c) if this solicitation is amended, then all terms and conditions which are not modified remain unchanged. [02- 2a005-1]
QUESTIONS FROM OFFERORS - AMENDMENT (Jun 2017) The solicitation is amended as provided herein. Information or changes resulting from questions will be shown in a question-and-answer format. All questions received have been reprinted below. The “state’s response” should be read without reference to the questions. The questions are included solely to provide a cross-reference to the potential Offeror that submitted the question. Questions do not form a part of the contract; the “state’s response” does. Any restatement of part or all of an existing provision of the solicitation in an answer does not modify the original provision except as follows:
underlined text is added to the original provision.
Stricken text is deleted. [02-2a097-1]
QUESTIONS AND ANSWERS
Q1. Do you have a current copy of the most recent Chiller/VFD Equipment Condition Report?
A1. MUSC does not have a current copy of the most recent condition report.
Q2. Which water-cooled chillers do NOT have VFDs?
A2. MRE #5 Trane , IOP #1 York, RT #3 Trane, QF 1&2, Trane do not have VFDs.
Q3. 4.vii. Is contractor required to perform monthly/quarterly alarm test on all refrigerant monitors?
Q3. No change. Contractor must perform alarm test on refrigerant monitor as per manufacturer's recommendations and within all Government regulations.
Q4. 4.ix & 5.x Is it required that each chiller VFD is maintained by the respective chiller OEM personnel or can PMs be performed by one manufacturer’s certified personnel?
A4.No Change. Maintenance on VFDs must be performed by OEM certified personnel in accordance with OEM maintenance recommendations. To clarify, personnel must be certified on the manufacturer’s equipment on which they are working.
Q5. 5.vi & 5.vii Tube brushing and eddy current are listed in the annual scope of work, but also asked at additional pricing on the business proposal. Are we to include in the base pricing or just as an adder?
A5. Tube brushing and Eddy Current is required as part of the contract. Please list on the RFP response a separate price for this service.
Q6. 5.viii. Is contractor required to calibrate all refrigerant monitors annually?
A6. No change. Contractor is required to calibrate all refrigerant monitors annually (as specified by OEM standards).
| AMENDMENTS TO SOLICITATION (JAN 2004): |
| QUESTIONS FROM OFFERORS - AMENDMENT (Jun 2017) |
File details come from the government source that posted it. Updated .