This document is an Engineering Specification for the SR VC12-IR and VC12-Diag vacuum chambers to be used in the Advanced Light Source Upgrade (ALS-U) project at the Lawrence Berkeley National Laboratory (LBNL).
The specification details the technical requirements, fabrication processes, testing procedures, and environmental conditions for the manufacturing of these two vacuum chambers. Key requirements include the chambers being primarily constructed from stainless steel 316L and copper, achieving an outgassing rate better than 1.00e-11 Torr.l.s-1.cm-2 and a final vacuum pressure of 5.00e-10 Torr. Manufacturing processes are specified for part fabrication, cleaning, joining, final assembly, and final testing including dimensional measurements, water pressure tests, bakeout, residual gas analysis, and helium leak checks. All work must be performed in a clean room environment and comply with relevant industry standards.
The document references a related Statement of Work (AL-1704-8935) and lists the applicable documents that provide additional details. This specification supports the federal contract opportunity JS-2024-005_RFQ for providing the Crotch Chamber Tanks for the ALS-U project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AL-1704-5291A.pdf | ||
| AL-1620-9887A.pdf | ||
| AL-1454-4437A.pdf | ||
| AL-1453-7407A.pdf | ||
| AL-1686-7718B.pdf | ||
| AL-1580-1800D.pdf | ||
| AL-1454-2764A.pdf | ||
| AL-1454-2756A.pdf | ||
| AL-1559-8951A.pdf | ||
| 5. Rep Cert Form.docx | DOCX document | |
| 4b. GP-Commercial Foreign.pdf | ||
| AL-1709-7009A.pdf | ||
| AL-1220-7841F.pdf | ||
| 6. AL-1208-0209 ALS-U QA Survey.pdf | ||
| AL-1698-2423A.pdf | ||
| 01 JS-2024-005 RFQ.pdf | ||
| AL-1705-5717A.pdf | ||
| AL-1704-8936A.pdf | ||
| 4a. GP-Commercial Domestic.pdf | ||
| AL-1713-7011A.pdf | ||
| AL-1704-8935A.pdf | ||
| AL-1476-9886A.pdf | ||
| AL-1453-8149E.pdf | ||
| 02 Sample Subcontract .pdf |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Advanced Light Source Upgrade Project Lawrence Berkeley National Laboratory
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
Printed hard copies of this document are for reference only.
SR - VC12-IR & VC12-Diag - ESD
Thomas GAUCHER
Release Date: Apr 10 2024 10:04:27 AM PDT
Document Number: AL-1704-8934 Revision: A
Document Status: Released
Document Type: SPECIFICATION
Category Code: AL7531
ALS-U - STORAGE RING
VACUUM CHAMBERS
O ffi ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
7T
Downloaded by: Thomas Gaucher at April 11, 2024 07:19:09
AL-1704-8934 Rev. A Doc. Status: Released Page 2 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
TABLE OF CONTENTS
1 Revision History
2 Approvals
3 Abbreviations and Acronyms
4 Introduction
4.1 Introduction to ALS-U
4.2 Subject of this Engineering Specification
5 Document Definitions
6 Description of the SR VC12-IR & VC12-Diag
6.1 VC12-IR
6.2 VC12-Diag
6.3 Fabrication process
7 Environmental requirements
7.1 Codes and Standards
7.2 Cleanliness environment
7.3 Cleaning fluids
7.4 Cutting fluids
7.5 Fasteners
7.6 Flange and Gaskets
8 Technical requirement
8.1 Vacuum pressure
8.2 Manufacturing process
8.2.1 Material
8.2.2 Fabrication
8.2.2.1 Part fabrication
8.2.2.2 Cleaning after manufacturing
8.2.2.3 Part joining
8.3 Final Cleaning
8.4 Final Assembly
8.5 Final test
ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 3 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
8.5.1 CMM Measurement before bakeout
8.5.2 Water pressure test
8.5.3 Bakeout
8.5.4 Residual Gas Analysis
8.5.5 Final He Leak Test
8.5.6 Final Pressure measurement
8.5.7 HPN2 Backfill
8.5.8 CMM Measurement after Bakeout
8.6 Packing and shipping
9 Applicable Documents ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 4 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
1 REVISION HISTORY
Rev. CM Number Description of Change A Baseline
2 APPROVALS
The following individual(s) must approve this document:
Approver Project Role Ken Chow Chief Engineer and System Engineer Jiani Niu Project QA manager Olusola Omolayo Vacuum CAM Windchill Approved / Concurred By oomolayo,jianiniu,KPChow
3 ABBREVIATIONS AND ACRONYMS
ALS Advanced Light Source ALS-U Advanced Light Source Upgrade ASTM American Society for Testing and Materials AR Accumulator Ring CC Cooling Chanel CF Conflat Flange CMM Coordinate Measuring Machine COTS Commercial Off The Shelves DCC Document Control Center He Helium HPN2 High Pressure Nitrogen EN-ISO European International Organization for Standardization LBNL Lawrence Berkeley National Laboratory
US
UHV
Ultra sound Ultra High Vacuum
VC Vacuum Chamber VCR Vacuum Coupling Radiation WPS Welding Procedure Specification ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 5 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
4 INTRODUCTION
4.1 Introduction to ALS-U
ALS-U is an upgrade project to the LBNL Advanced Light Source (ALS). The ALS is a 1.9
GeV storage ring operating at 500 mA of beam current. It is optimized to produce intense beams of soft x-rays, which offer spectroscopic contrast, nanometer-scale resolution, and broad temporal sensitivity. The ALS facility includes an accelerator complex and photon delivery system that is capable of providing the foundations for an upgrade that will achieve world-leading soft x-ray coherent flux. The existing ALS provides a ready-made foundation, including conventional facilities and also includes extensive beamlines (up to
40 simultaneously operating beamlines) and instrumentation, an experimental hall, computing resources, ancillary laboratories, offices, and related infrastructure that will be heavily utilized in an upgrade scenario.
The ALS will be upgraded with a multibend achromat (MBA) lattice design that will provide a soft x-ray source that is orders of magnitudes brighter — an up to 100-1000 times increase in brightness and will provide a significantly higher fraction of coherent light in the soft x-ray region than is currently available at ALS.
4.2 Subject of this Engineering Specification
The chambers VC12-IR & VC12-Diag are located respectively in sector #2, #5 #10 and sector #7 of the Storage Ring (SR). Further introductory details of theses chambers can be found in the SR VC12-IR & VC12-Diag Chamber Statement of Work - AL-1704-8935, §4.2.
ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 6 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
5 DOCUMENT DEFINITIONS
Must, will, may, and should are used to define every specification listed in this document.
The definitions of these terms are as follows
May – is used to indicate a desire or goal of a specification. This can also be interpreted
‘as nice to have’ and are not contractually binding.
Must –is a specification that is contractually binding and must be implemented.
Should – is used to indicate a desire or goal of a specification. This can also be interpreted ‘as nice to have’ and are not contractually binding.
Will – is used to inform intent or declaration of purpose. This is not a specification.
Example, the author will use the word ‘must’ to indicate that a specification is contractually binding and must be implemented.
ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 7 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
6 DESCRIPTION OF THE SR VC12-IR & VC12-DIAG
6.1 VC12-IR
The main functions and requirements of the SR VC12-IR are:
1. Host M1 drive insert assembly at the bottom of the chamber
2. Provide a keyhole shaped common entry flange port for the electron and photon beam
3. Provide dedicate exit flange ports of the electron.
4. Provide ancillary ports for gauges, pumps and right angle valves
The VC12-IR has been designed by LBNL to meet these requirements and perform these functions. VC12-IR is shown in Figure 6-1.
Figure 6-1: VC12-IR
Upstream Downstream
Keyhole aperture
M1 mirror assembly port for
IR beamline
Electron beam
Pumping port
Gauges port
Gate Valve port
Gauges port ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 8 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
6.2 VC12-Diag
The main functions and requirements of the SR VC12-Diag are:
1. Host mask / cold finger assembly at the bottom of the chamber
2. Provide a square shaped and a round aperture in the common entry flange port for the photon and electron beam.
3. Provide dedicate exit flange ports of the electron.
4. Provide ancillary ports for gauges, pumps and right angle valves
5. Provide viewport port at the top of the chamber
The VC12-Diag has been designed by LBNL to meet these requirements and perform these functions. VC12-Diag is shown in Figure 6-2.
Figure 6-2: VC12-Diag
Upstream Downstream
Keyhole aperture
M1 mirror assembly port for
Diagnostic beamline
Electron beam
Pumping port
Gauges port
Viewport port
Gauges port ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 9 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
6.3 Fabrication process
Both chambers are primarily constructed from stainless steel 316L and copper (C18150 and C10100). The fabrication process for the parts involves CNC and EDM machining.
The parts are joined by TIG welding and EB welding. The fabrication processes are mostly the same for both chambers.
All the main chamber body parts (Figure 6-3) are machined separately and joined by TIG welding. The body absorber (Figure 6-4) features are achieved by EDM machining. The features are design to minimize geometrical beam impedance through the vacuum chamber.
Figure 6-3: Main chamber body 316L of
VC12-IR
Figure 6-4: Body Absorber of VC12-IR
The body absorber is joined to the main chamber body using EB welding.
All copper parts are joined together using EB welding.
All ports are welded onto the main chamber body using TIG welding
Figure 6-5: VC12-IR
The beam entry port and the electron beam exit port flanges utilize Helicoflex vacuum seals, while other ports use standard CF copper gaskets.
VC12-Diag is manufactured using the same fabrication process.
ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 10 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
7 ENVIRONMENTAL REQUIREMENTS
7.1 Codes and Standards
ID NUM
(SYY-XX-) Specification
S09-94-000151
The following standards must apply for the fabrication and test of the SR
VC12-IR & VC12-Diag Chamber:
EN ISO 13919 or EN ISO 5817
EN ISO 17637
ASTM E498.
EN ISO 17640
ASTM E2734/E2734 M − 10.
7.2 Cleanliness environment
ID NUM
(SYY-XX-) Specification
S09-94-000152 The cleaning environment must comply with UHV Chamber and Component Production Requirements AL-1220-7841, §7.2
7.3 Cleaning fluids
ID NUM
(SYY-XX-) Specification
S09-94-000153 The cleaning fluids must comply with UHV Chamber and Component Production Requirements AL-1220-7841, §7.3
7.4 Cutting fluids
ID NUM
(SYY-XX-) Specification
S09-94-000154 The cutting fluids must comply with UHV Chamber and Component Production Requirements AL-1220-7841, §7.4
7.5 Fasteners
ID NUM
(SYY-XX-) Specification
S09-94-000155 The fasteners of the of vacuum chambers must comply with AL- 1220-7841, §7.6 ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 11 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
7.6 Flange and Gaskets
ID NUM
(SYY-XX-) Specification
S09-94-000156 The flanges and gaskets of the vacuum chambers must comply with
AL-1220-7841, §7.7
8 TECHNICAL REQUIREMENT
8.1 Vacuum pressure
ID NUM
(SYY-XX-)
Specification
S09-94-000157 The maximum thermal outgassing rate must be better than 1.00e-11 Torr.l.s-1.cm-2
S09-94-000158 Achievable final pressure must be 5.00e-10 Torr
8.2 Manufacturing process
8.2.1 Material
The procurement of the raw material by the Sub-contractor must comply with the following requirements
ID NUM
(SYY-XX-) Specification
S09-94-000163 All materials must be new.
S09-94-000164 All material must be free from surface cracks and fissures, forge and other tool marks, burns, delamination and other defects that would make it incompatible with a high vacuum environment.
S09-94-000165 Certification must be in accordance with EN ISO 10204 3.1.
S09-94-000211 Magnetic permeability for vacuum chamber base material must be
1.01 and for welds or braze joints 1.04
S09-94-000168 The tube of the chamber must be seamless
S09-94-000169 The material must be compatible with synchrotron radiation ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 12 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
8.2.2 Fabrication
8.2.2.1 PART FABRICATION
The fabrication of the chambers must comply with the following requirements
Cutting fluids
ID NUM
(SYY-XX-) Specification
S09-94-000170 A water-soluble and non-halogenated cutting fluids must be used for fabrication
S09-94-000171 All others requirements relative to the vacuum components fabrication must comply with AL-1220-7841, §8.1, §8.2, §8.3
8.2.2.2 CLEANING AFTER MANUFACTURING
An intermediate cleaning must be done after manufacturing and must comply with the following requirements
ID NUM
(SYY-XX-) Specification
S09-94-000172 UHV surfaces must be protected as per best practices during handling operations.
S09-94-000173 Parts must be stored in a clean area from the workshop (See §7.2).
S09-94-000174 Parts must be suspended in tanks by wire, hooks or in baskets
S09-94-000175 All others requirements relative to the vacuum components cleaning must comply with AL-1220-7841, §9
8.2.2.3 PART JOINING
The joining process of the components must comply with the following requirements
General requirement
ID NUM
(SYY-XX-) Specification
S09-94-000176 Step change in geometrical profile across weld must be less than 0.2mm
S09-94-000177 All parts must be cleaned prior to welding (See §8.3)
S09-94-000178 A WPS is not required
S09-94-000179 The weld quality must be level D according to EN ISO 13919 or EN
ISO 5817
S09-94-000182 All welds must be free from cracks and fissures or other defects that would make it incompatible with a high vacuum environment.
ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 13 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
Inspection of welded joints
(SYY-XX-) Specification
S09-94-000183 100% of the vacuum boundary welded joints must be visually inspected
S09-94-000184 The visual inspection must comply with EN ISO 17637
Component leak check
ID NUM
(SYY-XX-) Specification
S09-94-000185 100% of the vacuum boundary welded joints must be leak tested.
S09-94-000186 The leak test of the welded joint must comply with ASTM E498.
S09-94-000187 The criteria and parameter expected for the He leak check must comply with AL-1220-7841, §14
8.3 Final Cleaning
The final cleaning of the chambers must comply with the following requirements
General requirement
ID NUM
(SYY-XX-) Specification
S09-94-000188 Once the final cleaning process has started, it must not be stopped before the end.
S09-94-000189 After the final cleaning, all subsequent operations must be performed in a cleanroom.
Cleaning
ID NUM
(SYY-XX-) Specification
S09-94-000190 The cleaning agent used must be identified and approved by LBNL prior to the Factory acceptance test.
S09-94-000191 All other requirements regarding the final cleaning and intermediate inspection must comply with AL-1220-7841, §11 and §12.
ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 14 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
8.4 Final Assembly
(SYY-XX-) Specification
S09-94-000192 All requirement with final assembly must comply AL-1220-7841, §13
8.5 Final test
The final tests to ensure the performance of the SR VC12-IR & VC12-Diag Chamber must be performed in the sequence shown in Figure 8-1.
Figure 8-1: Final test sequence ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 15 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
General requirement
(SYY-XX-) Specification
S09-94-000193 All test must take place in a clean room
S09-94-000194 During pumping down of the part, all connection above the turbo pump must be all-metal
S09-94-000195 The HPN2 port must be all-metal
S09-94-000196 The HPN2 port must be a VCR to CF16 adapter that is replaced with a CF16 blank as the last connection to the chamber prior to shipping.
S09-94-000197 LBNL must have right to visit the contractor during these tests
8.5.1 CMM Measurement before bakeout
ID NUM
(SYY-XX-) Specification
S09-94-000198 A CMM measurement must be performed, on all chambers
S09-94-000200 The dimensions to be controlled must be specified by the University technical representative.
8.5.2 Water pressure test
The water pressure for the cooling channel must comply with the following requirements
ID NUM
(SYY-XX-) Specification
S09-94-000201 The cooling channel pressure test must be conducted at 120 psi
S09-94-000202 The cooling channel pressure test must last 10 mins
Criteria
ID NUM
(SYY-XX-) Specification
S09-94-000203 No leak must appear at the completion of the pressure test
8.5.3 Bakeout
ID NUM
(SYY-XX-) Specification
S09-94-000204 Bakeout must comply with AL-1220-7841, §14.1 ci al ly R el ea se d to th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: A pr il th , 2
D C
C A ut h
K ey
: T B5
B8 V
RD
AL-1704-8934 Rev. A Doc. Status: Released Page 16 of 16
All officially released LBNL documents are watermarked and contain LBNL Document Control Center release information in the lower-left corner of the document's pages.
8.5.4 Residual Gas Analysis
(SYY-XX-) Specification
S09-94-000205 Residual Gas Analysis must comply with AL-1220-7841, §14.2
8.5.5 Final He Leak Test
ID NUM
(SYY-XX-) Specification
S09-94-000208 Final pressure measurement must comply with AL-1220-7841, §14.5
8.5.6 Final Pressure measurement
ID NUM
(SYY-XX-) Specification
S09-94-000207 Final He leak test must comply with UHV Chamber and Component Production Requirements AL-1220-7841, §14.4
8.5.7 HPN2 Backfill
ID NUM
(SYY-XX-) Specification
S09-94-000209 HPN2 Back fill must comply with AL-1220-7841, §14.6
8.5.8 CMM Measurement after Bakeout
ID NUM
(SYY-XX-) Specification
S09-94-000328 A CMM measurement must be performed on all chamber with the same critical dimension given in §8.5.1 after the bakeout
8.6 Packing and shipping
ID NUM
(SYY-XX-) Specification
S09-94-000210 Packing and shipping must comply with AL-1220-7841, §15
9 APPLICABLE DOCUMENTS
See applicable document in section 10 in the AL-1704-8935 SR - VC12-IR & VC12-Diag -
SOW.
ci al ly R el ea se d to th e
LB
N L