This document contains the General Provisions for a construction contract between the William S. Hart Union High School District and a general contractor for the Culinary Arts Modernization Project, along with an Owner Controlled Insurance Program (OCIP) agreement administered by the Statewide Educational Wrap Up Program (SEWUP) Joint Powers Authority. The project encompasses culinary arts classroom upgrades at six high schools in Santa Clarita, California, including removal and replacement of countertops, sinks, and electrical infrastructure at Bowman, Canyon, Golden Valley, Valencia, West Ranch, and William S. Hart High Schools. The work is divided into two phases: Phase 1 during Winter Break from December 22, 2025, to January 9, 2026, and Phase 2 from March 25, 2026, to June 30, 2026. A mandatory job walk is scheduled for October 15, 2025, at Golden Valley High School, with electronic bids due via the District's eProcurement Portal by November 3, 2025, at 2:00 pm. The contractor must possess an active Class B (General Contractor) license and comply with all prevailing wage laws, DSA (Division of the State Architect) approvals, and comprehensive insurance requirements.

The contract incorporates extensive standard provisions governing contractor responsibilities, including quality control procedures, site safety, labor law compliance, progress payments with five percent retention, and detailed claims procedures. Eligible contractors must demonstrate an average Workers' Compensation Experience Modification Rate of 1.25 or less over the past five years, zero Serious and Willful violations in the past five years, and provide evidence of an Injury and Illness Prevention Program prior to award. The OCIP provides Workers' Compensation, Employer's Liability, General and Excess Liability, Contractor's Pollution Liability, and Builder's Risk insurance to enrolled contractors and subcontractors, with the District bearing all OCIP premiums. Contractors must still provide their own Automobile Liability Insurance with minimum limits of $2,000,000 for general contractors and $1,000,000 for subcontractors, Professional Liability Insurance if design services are required, and various other specialized coverages as needed. The project includes a $50,000 owner-controlled allowance, and all contractors must register with the Department of Industrial Relations and maintain compliance with SEWUP contractual provisions, safety programs, and monthly payroll reporting requirements.

View the file

Other files

File Type Posted
Culinary_Arts_Modernization_Project.pdf PDF
13283_Culinary_Arts_Specifications_9-26-25.pdf PDF
13283_Cullinary_Arts_Drawings_9-26-25.pdf PDF
DOJ_Rev._5.08.25_Certification_of_Employee_Background_Check.pdf PDF
(5)_Company_Guarantee_to_Owner_(1).pdf PDF
(6)_Safety_Program_A_(1).pdf PDF
(2)_Perfomance_Bond_(1).pdf PDF
(10)_PWC100_DIR_INFO_(1).pdf PDF
2-Certification_of_Safety_Program_(1).pdf PDF
(4)_Drug_and_Tobacco_(1).pdf PDF
(3)_Payment_Bond_Blank_(1).pdf PDF
1-Substitution_Request_(1).pdf PDF
(11)_Workers_Compensation_Exemption_Declaration_Construction_(1).pdf PDF
Agree__Hart__Front_End_GC__General_Provisions_OCIP_Rev_6.26.23JF_(Rev_6.21.24_Added_Blue_Beam_Illustration_Method).pdf PDF
Blank_IRS_W-9_(2024).pdf PDF
Agree__Hart__Front_End_CM-MP__General_Provisions_OCIP_Rev_6.26.23JF_(Rev_6.21.24_Added_Blue_Beam_Illustration_Method).pdf PDF
(1)_Asbestos-Free_Materials.pdf PDF
Agree__Hart__Front_End_CM-MP__General_Provisions_Rev_6.26.23JF_(Rev_6.21.24_Added_Blue_Beam_Illustration_Method_&_Insurance).pdf PDF
Agree__Hart__Front_End_GC__General_Provisions_Rev_6.26.23JF_(Rev_6.21.24_Added_Blue_Beam_Illustration_Method_&_Insurance).pdf PDF
CM-MP_Construction_Services_Agreement_2019_informal_and_formal_bids_CUPCCAA.pdf PDF
GC_Construction_Services_Agreement_2019.pdf PDF
(7)_Lead_Containing_176349_(1).pdf PDF
3-Conditional_Waiver_and_Release_(upon_Progress_Payment).pdf PDF
4-Unconditional_Waiver_and_Release_(Upon_Progress_Payment).pdf PDF
6-Unconditional_Waiver_and_Release_(Upon_Final_Payment).pdf PDF
5-Conditional_Waiver_and_Release_(Upon_Final_Payment).pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL PROVISIONS

TABLE OF CONTENTS

Page

Revision Date: 6/26/23 JF General Provisions i

006140.00003 24027126.5

PART 1 ACKNOWLEDGMENT, ORGANIZATION AND INTERPRETATION OF GENERAL PROVISIONS ... 1-1

1.1 Contractor Acknowledgment of General Provisions .......................................... 1-1

1.2 Organization of General Provisions .................................................................... 1-1

1.3 Guides for Interpreting General Provisions ........................................................ 1-1

1.4 Locations of Definitions of Capitalized Terms .................................................... 1-2

PART 2 DISTRICT ADMINISTRATION OF THE CONTRACT ...................................................................... 2-1

2.1 Status of Authorized District Officers ................................................................. 2-1

2.2 Status of District Contract Representatives ........................................................ 2-1

2.3 General Authority of District Contract Representatives ..................................... 2-1

2.4 Avoiding Conflicts of Interests ............................................................................ 2-2

2.5 Services and General Authority of Architect ...................................................... 2-2

2.6 Services and General Authority of Project Manager .......................................... 2-2

2.7 Services and General Authority of Inspector of Record ..................................... 2-3

2.8 General Authority to Reject Non-Conforming Work .......................................... 2-3

2.9 General Authority to Stop or Suspend Work ...................................................... 2-4

2.10 Contractor Must Ensure Access to the Work...................................................... 2-4

2.11 Contractor Must Provide Information Upon Request ........................................ 2-4

2.12 Communications from Contractor ...................................................................... 2-4

2.13 Communications to and through Contractor ..................................................... 2-5

2.14 Contractor Retains Responsibility for Work ....................................................... 2-5

2.15 Contractor Responsibility for Additional Professional Services .......................... 2-5

2.16 Damages Incurred by District Pursuant to Other Contracts ............................... 2-6

PART 3 CONTRACTOR ADMINISTRATION OF THE CONTRACT .............................................................. 3-1

3.1 Status of Contractor ............................................................................................ 3-1

3.2 Contractor Solely Responsible for Work ............................................................. 3-1

3.3 General Responsibilities of Contractor ............................................................... 3-1

3.4 Requirements for Job Superintendent ............................................................... 3-2

3.4.1 No Work if Job Superintendent Not Present ............................ 3-2

3.4.2 Selection and Replacement of Job Superintendent ................. 3-2

3.4.3 Job Superintendent Must be Exclusive to the Work ................ 3-3

3.4.4 Responsibilities and Authority of Job Superintendent ............. 3-3

3.5 Requirements for Subcontractors ...................................................................... 3-3

3.5.1 Written Subcontracts Required ................................................ 3-3

3.5.2 Subcontractors Have No Contractual Privity with District ....... 3-4

3.5.3 Subcontractors Must be Appropriately Licensed ..................... 3-4

3.5.4 District Approval of Subcontractors ......................................... 3-4

3.6 Prohibition Against Unlawful Discrimination......................................... 3-4

3.7 Contractor Must Provide for Own Communications .......................................... 3-5

3.8 Contractor Must Maintain Reference Materials at Project Site ......................... 3-5 ii

006140.00003 24027126.5

3.9 Contractor Must Prepare As-Built Plans and Specifications ............................... 3-5

3.9.1 Changes to be Illustrated .......................................................... 3-5

3.9.2 Method of Illustrating ............................................................... 3-6

3.9.3 Timing and Approval of Updates .............................................. 3-6

3.9.4 Responsibility for Accuracy ....................................................... 3-6

3.10 Contractor Must Implement Document Control System ................................... 3-7

3.11 Contractor Must Maintain Records of the Work ................................................ 3-7

3.12 State Review and Audit of Records of the Work ................................................ 3-7

3.13 Contractor Responsible for Subcontractor Compliance ..................................... 3-7

PART 4 THE CONTRACT AND CONTRACT DOCUMENTS ........................................................................ 4-1

4.1 Scope and Coverage of Contract ........................................................................ 4-1

4.2 Construing the Contract Documents .................................................................. 4-1

4.3 Interpretation of Plans ........................................................................................ 4-1

4.3.1 Purpose and Scope ................................................................... 4-1

4.3.2 Scaled and Numerical Dimensions............................................ 4-1

4.3.3 Notes and Schedules................................................................. 4-2

4.3.4 Typical Details ........................................................................... 4-2

4.3.5 Approximations ........................................................................ 4-2

4.4 Interpretation of Specifications .......................................................................... 4-2

4.4.1 Purpose and Scope ................................................................... 4-2

4.4.2 Discretionary Determinations................................................... 4-2

4.4.3 Industry or Governmental Standards and Specifications ......... 4-2

4.4.4 Fragmented or Truncated Wording .......................................... 4-2

4.4.5 Titles and Captions.................................................................... 4-3

4.4.6 Singular and Plural Senses ........................................................ 4-3

4.4.7 Gender ..................................................................................... 4-3

4.5 Addenda .............................................................................................................. 4-3

4.6 Deferred Approvals ............................................................................................. 4-3

4.7 Work to be Inferred from Contract Documents ................................................. 4-3

4.8 Geotechnical and Soils Reports .......................................................................... 4-4

4.8.1 Not Part of Contract Documents .............................................. 4-4

4.8.2 Specifications Govern ............................................................... 4-4

4.8.3 No Warranty of Information ..................................................... 4-4

4.9 Contractor to Know and Understand Applicable Law ........................................ 4-4

4.10 Pre-Construction Review of Contract Documents .............................................. 4-4

4.11 Notice After Pre-Construction Review ................................................................ 4-5

4.12 Ongoing Review of Contract Documents ............................................................ 4-5

4.13 Requests for Information Regarding the Work or the Contract Documents ..... 4-5

4.13.1 Submittal to Architect ............................................................... 4-5

4.13.2 Each RFI Must be Submitted Timely and in Good Faith ........... 4-6 iii

006140.00003 24027126.5

4.13.3 Architect Review and Response to RFI ..................................... 4-6

4.14 Costs of Erroneous or Non-Conforming Work .................................................... 4-6

4.15 Ownership and Rights to Contract Documents .................................................. 4-7

4.16 Use of Contract Documents ................................................................................ 4-7

4.17 Return of Contract Documents to District .......................................................... 4-7

PART 5 SHOP DRAWINGS, DEFERRED APPROVALS AND OTHER SUBMITTALS .................................... 5-1

5.1 General Requirements for Submittals ................................................................ 5-1

5.2 Requirements for Timely Submittals .................................................................. 5-1

5.3 Requirements for Identifying Submittals ............................................................ 5-1

5.4 Required Quantities of Submittal Materials ....................................................... 5-2

5.5 Contractor Must Identify Deviations from Contract Requirements ................... 5-2

5.6 Contractor Must Review and Verify All Submittals ............................................ 5-2

5.7 Contractor Must Provide Preliminary Materials Lists ......................................... 5-2

5.8 Requirements for Shop Drawings ....................................................................... 5-3

5.9 Requirements for Samples.................................................................................. 5-3

5.10 Requirements for Deferred Approvals ............................................................... 5-3

5.11 Scope of Submittal Review and Approval ........................................................... 5-4

5.12 Contractor Must Correct and Resubmit Rejected Submittals ............................ 5-5

5.13 No Work or Deliveries Permitted Absent Approved Submittals ........................ 5-5

PART 6 INSURANCE REQUIREMENTS .................................................................................................... 6-1

6.1 Introduction to Owner Controlled Insurance Program (OCIP) ........................... 6-1

6.2 Failure to Maintain Required Insurance ............................................................. 6-1

6.3 Insurer Standards ................................................................................................ 6-1

6.4 Premiums, Deductibles and Self-Insured Retentions ......................................... 6-1

6.5 Additional Required and/or Optional Insurance ................................................ 6-1

6.6 Compliance with Safety Programs ...................................................................... 6-2

PART 7 PERFORMANCE AND PAYMENT BONDING REQUIREMENTS ................................................... 7-1

7.1 Surety Bonds a Condition Precedent to Commencing the Work ....................... 7-1

7.2 Delivery of Surety Bonds ..................................................................................... 7-1

7.3 Forms of Surety Bonds ........................................................................................ 7-1

7.4 Penal Sums of Surety Bonds ............................................................................... 7-1

7.5 Surety Qualifications ........................................................................................... 7-1

7.6 Surety Obligations Not Affected by Changes in Work ........................................ 7-2

PART 8 PERFORMANCE OF THE WORK GENERALLY ............................................................................. 8-1

8.1 Contractor Must Furnish Everything Required ................................................... 8-1

8.2 Contractor Responsible for Permits and Fees .................................................... 8-1

8.3 Contractor Must Comply with Applicable Laws .................................................. 8-1 iv

006140.00003 24027126.5

8.4 Contractor Must Implement Quality Control Procedures .................................. 8-2

8.5 Contractor Must Appropriately Coordinate and Time the Work ....................... 8-2

8.6 Contractor Must Furnish Sufficient and Skilled Workforce ................................ 8-2

8.7 Contractor Must Confine Work to Designated Areas ......................................... 8-2

8.8 Requirements for Accessing the Project Site ...................................................... 8-3

8.9 District Responsible for Utility Easements and Rights of Entry .......................... 8-3

8.10 District to Furnish any Necessary Survey of Project Site .................................... 8-3

8.11 Contractor Responsible for Construction Surveying .......................................... 8-3

8.12 Contractor Must Preserve Survey Monuments and Markers ............................. 8-3

8.13 NPDES Permit and SWPPP .................................................................................. 8-3

8.13.1 District to Obtain Coverage ................................................................................ 8-3

8.13.2 Implementation and Compliance ....................................................................... 8-4

8.13.3 Consequences of Failure to Comply ................................................................... 8.4

8.14 Contractor Must Comply with Run-Off Control Requirements .......................... 8-4

8.15 Contractor Must Not Disturb Run-Off Control Measures ................................... 8-4

8.16 Contractor Must Protect Site and Existing Improvements ................................. 8-4

8.17 Requirements for Cutting and Patching of Work ............................................... 8-5

8.18 Requirements for Cutting, Drilling or Attaching to Structural Members ........... 8-5

8.19 District Responsibility to Provide for Testing and Inspection ............................. 8-6

8.20 Contractor Must Give Timely Notice of Testing and Inspections ....................... 8-6

8.21 District May Require Special or Additional Testing or Inspection ...................... 8-6

8.22 Contractor Responsibility for Costs of Testing and Inspections ......................... 8-7

8.23 Contractor Must Correct Non-Conforming Work ............................................... 8-7

8.24 Contractor Must File Verified Reports ................................................................ 8-7

8.25 Contractor Must File Daily Reports ..................................................................... 8-8

8.26 Contractor Must Control Noise and Dust ........................................................... 8-8

8.27 Contractor Must Clean Work Areas .................................................................... 8-8

8.28 Consequences of Failure by Contractor to Clean Work Areas ............................ 8-8

PART 9 COORDINATION WITH WORK BY OTHERS ................................................................................ 9-1

9.1 Contractor Must Ascertain Impacts of Work by Others ..................................... 9-1

9.2 Contractor Must Accommodate Partial Occupancy by District .......................... 9-1

9.3 Contractor Must Coordinate with Work by Others ............................................ 9-1

9.4 Contractor Must Inspect Certain Work by Others for Deficiencies .................... 9-2

PART 10 PROJECT SITE DECORUM ....................................................................................................... 10-1

10.1 Performance of Work at Operating School Facilities ........................................ 10-1

10.2 Prohibition Against Contact with Students and Other Minors ......................... 10-1

10.3 Procedures to Prevent Contact with Students ................................................. 10-1

10.3.1 Significance of Requirements ................................................. 10-1

10.3.2 Criminal-History Background Checks ...................................... 10-1 v

006140.00003 24027126.5

10.3.3 Responsibility for Subcontractor Compliance ........................ 10-2

10.3.4 Alternatives to Fingerprinting and Background Checks ......... 10-2

10.4 Consequences of Violating Prohibition Against Contact .................................. 10-2

10.5 Identification or Security Badges ...................................................................... 10-3

10.6 Prohibition Against Workers Leaving Vicinity of Their Work............................ 10-3

10.7 Prohibition Against Unfit Workers .................................................................... 10-3

10.8 Requirements for Courteous and Professional Conduct .................................. 10-3

10.9 Dress Code and Appearance Requirements ..................................................... 10-4

10.10 Requirements for Use of Restrooms ................................................................ 10-4

10.11 Control of Break-Time Activities ....................................................................... 10-4

10.12 Prohibition Against Drugs (including Alcohol) and Tobacco ............................. 10-4

10.13 Prohibition Against Unnecessary Noise ............................................................ 10-5

10.14 Limitations on Access to Project Site ................................................................ 10-5

10.15 Parking at the Project Site ................................................................................ 10-5

10.16 Use of Vehicles and Equipment at the Project Site .......................................... 10-5

10.17 Prohibition Against Displays on Vehicles and Equipment ................................ 10-6

10.18 No District Responsibility for Vehicles or Equipment ....................................... 10-6

10.19 Prohibition Against Animals at Project Site ...................................................... 10-6

10.20 Contractor to Require Compliance ................................................................... 10-6

10.21 Consequences of Non-Compliance ................................................................... 10-6

PART 11 PROJECT SITE SAFETY ............................................................................................................ 11-1

11.1 General Safety-Related Responsibilities of the Contractor .............................. 11-1

11.2 Required Safety Programs ................................................................................ 11-1

11.3 Designation and Duties of Safety Officers ........................................................ 11-1

11.3.1 Contractor Safety Officer ........................................................ 11-1

11.3.2 Subcontractor Safety Officer .................................................. 11-2

11.4 Required Safety Measures ................................................................................ 11-2

11.5 Contractor Must Not Impose Unsafe Loads ..................................................... 11-3

11.6 Design and Use of Temporary Structures and Equipment ............................... 11-3

11.7 Trench Safety Plans ........................................................................................... 11-3

11.8 Other Safety Requirements .............................................................................. 11-4

11.9 Contractor Response to Emergency Situations ................................................ 11-4

11.10 Required Reporting of Accidents, Injuries and Damage ................................... 11-4

11.10.1 Contractor Accident Reports .................................................. 11-4

11.10.2 Subcontractor Accident Reports ............................................. 11-4

11.11 Notice and Correction of Non-Compliance ....................................................... 11-5

11.12 Contractor Liability ........................................................................................... 11-5

11.13 Compliance a Condition Precedent to Payment ............................................... 11-5 vi

006140.00003 24027126.5

PART 12 COMPLIANCE WITH LABOR LAWS ........................................................................................ 12-1

12.1 Contractor Must Comply with Prevailing Wage Laws ...................................... 12-1

12.2 Copies of Prevailing Wage Rates ...................................................................... 12-1

12.3 Penalties for Violations of Prevailing Wage Laws ............................................. 12-1

12.4 Compliance with Monitoring and Enforcement ............................................... 12-1

12.5 Prohibition Against Debarred Subcontractors .................................................. 12-2

12.6 Employment of Apprentices ............................................................................. 12-2

12.7 Limitations on Daily Hours of Work .................................................................. 12-2

12.8 Requirements for Payroll Records .................................................................... 12-2

12.9 Contractor Must Know and Comply with All Labor Laws ................................. 12-3

12.10 Registration with DIR ........................................................................................ 12-3

PART 13 TIME FOR COMPLETION AND DELAYS .................................................................................. 13-1

13.1 Time is of the Essence ....................................................................................... 13-1

13.2 Pre-Construction Activities ............................................................................... 13-1

13.3 Proposed Master Construction Schedule ......................................................... 13-1

13.3.1 Submittal Requirements ......................................................... 13-1

13.3.2 Schedule Coverage ................................................................. 13-1

13.3.3 Minimum Required Elements ................................................. 13-2

13.3.4 Approval by Project Manager ................................................. 13-2

13.4 Normal Weather Deemed Foreseeable ............................................................ 13-2

13.5 Time for Deferred Approvals Deemed Included in Schedule ........................... 13-2

13.6 Modifications to Master Construction Schedule .............................................. 13-3

13.6.1 Updates and Revisions ............................................................ 13-3

13.6.2 Other Modifications ................................................................ 13-3

13.7 Issuance of Notice to Proceed .......................................................................... 13-3

13.8 Commencement and Diligent Performance of Work ....................................... 13-3

13.9 Times During Workday When Work May be Performed .................................. 13-4

13.9.1 Work During Regular Working Hours ..................................... 13-4

13.9.2 Permissive Work Outside of Regular Working Hours ............. 13-4

13.9.3 Mandatory Work Outside Regular Working Hours ................ 13-4

13.10 Mandatory Notice of Anticipated Delay ........................................................... 13-5

13.11 Mandatory Notice of Actual Delay ................................................................... 13-5

13.12 Review of Facts and Circumstances Resulting in Delay .................................... 13-5

13.13 Requests for Additional Time and/or Compensation for Delays ...................... 13-5

13.14 Change Orders Deemed Not to Cause or Create Delays ................................ 13-6

13.15 Delays Resulting from Abnormal Weather ....................................................... 13-6

13.16 Extensions of Time for Performance of the Work ............................................ 13-6

13.17 No Compensation for Certain Delays ............................................................... 13-6

13.18 Compensation for Delays Caused by District .................................................... 13-7

13.19 Compensation for Delays Caused by Contractor .............................................. 13-7 vii

006140.00003 24027126.5

13.20 No Compensation for Delays Having Concurrent Causes ................................. 13-8

13.21 Liquidated Damages for Delays in Completing Project .................................... 13-8

13.22 Contractor Claims Arising from Delays ............................................................. 13-9

PART 14 MATERIALS AND EQUIPMENT............................................................................................... 14-1

14.1 Types and Quality of Materials and Equipment ............................................... 14-1

14.2 Contractor to Furnish Sufficient Materials and Equipment .............................. 14-1

14.3 Storage and Protection of Materials and Equipment ....................................... 14-1

14.4 Authority to Request Substitution of Specified Items ...................................... 14-2

14.5 Procedures and Conditions for Requesting Substitution of Specified Items .... 14-2

14.6 Contractor Must Substantiate Requests for Substitution ................................ 14-2

14.6.1 Contractor Has Sole Responsibility ......................................... 14-2

14.6.2 Timing for Providing Substantiating Information ................... 14-3

14.6.3 Nature of Substantiating Information .................................... 14-3

14.6.4 Adequacy of Substantiating Information ................................ 14-3

14.6.5 Contractor Certification .......................................................... 14-3

14.7 District Discretion to Approve Requests for Substitution................................. 14-4

14.8 Conditional Approval of Requests for Substitution .......................................... 14-4

14.9 Contractor Responsible for Impacts and Costs of Substitution ........................ 14-4

14.10 Disapproval of Requests for Substitution ......................................................... 14-5

14.11 Purchase and Ownership of Materials and Equipment .................................... 14-5

PART 15 HAZARDOUS EQUIPMENT, MATERIALS AND SUBSTANCES ................................................. 15-1

15.1 Use of Hazardous Materials in Connection with the Work .............................. 15-1

15.2 Hazard Communication Program...................................................................... 15-1

15.3 Contractor Prohibited from Using Asbestos ..................................................... 15-1

15.4 Contractor Deemed Fully Aware of the Dangers of Asbestos .......................... 15-2

15.5 Consequences of Violating Prohibition Against Asbestos ................................ 15-2

15.6 District to Arrange for Necessary Asbestos Remediation ................................. 15-2

15.7 Discovery of Hazardous Materials During Performance of the Work .............. 15-2

15.8 Discovery of Hazardous Materials in Excavations Deeper Than Four Feet ...... 15-3

15.9 Delays Resulting from Discovery of Hazardous Materials ................................ 15-3

15.10 Contractor Responsibility for Releases of Hazardous Substances .................... 15-3

PART 16 EXCAVATIONS AND UTILITIES ............................................................................................... 16-1

16.1 Contractor Must Locate Underground Utilities and Installations .................... 16-1

16.2 Contractor Must Contact Regional Notification Center ................................... 16-1

16.3 Main or Trunkline Utilities Not Identified in Contract Documents................... 16-2

16.4 Responsibility for Cost of Relocating Utility Facilities ....................................... 16-2

16.5 Contractor Must Obtain and Pay for Utility Services ........................................ 16-2

16.6 Contractor Must Coordinate with Utility Companies ....................................... 16-2 viii

006140.00003 24027126.5

16.7 Contractor Must Have Permit for Excavations ................................................. 16-3

16.8 Contractor Must Protect Adjacent Improvements ........................................... 16-3

16.9 Trench Safety Plans for Trenches Deeper Than Five Feet ................................ 16-3

16.10 Differing Conditions in Excavations Deeper Than Four Feet ............................ 16-3

PART 17 CHANGES IN THE WORK ........................................................................................................ 17-1

17.1 Authorization Required for Changes in the Work ............................................ 17-1

17.1.1 District Approval of Changes Required ................................... 17-1

17.1.2 DSA Approval of Certain Changes ........................................... 17-1

17.1.3 Direction to Proceed With Changes ....................................... 17-1

17.1.4 Responsibility for Unauthorized Changes ............................... 17-1

17.2 Changes Required by Change Order ................................................................. 17-2

17.3 Changes Required by Architect Field Directive ................................................. 17-2

17.4 Changes Required by Unilateral Change Order ................................................ 17-2

17.5 Mandatory Notice of Disagreement Regarding Contract Price or Time ........... 17-3

17.6 Consequences of Failure to Provide Mandatory Notice ................................... 17-3

17.7 Changes Requested by the District ................................................................... 17-3

17.8 Changes Requested by the Contractor ............................................................. 17-4

17.9 Determining Effect of Change on Contract Price .............................................. 17-4

17.10 Determining Change Order Cost Based on Time and Materials ....................... 17-5

17.11 Determining Change Order Cost Based on Lump Sum Proposal ...................... 17-5

17.12 Determining Change Order Cost Based on Unit Pricing ................................... 17-5

17.13 Cost Components to be Included in All Estimates ............................................ 17-5

17.14 Deductive or Reduced Change Order Costs ...................................................... 17-7

17.15 Discounts and Refunds Deducted from Change Order Costs ........................... 17-7

17.16 Substantiation of Subcontractor Pricing Included in Estimates ....................... 17-8

17.17 Substantiation of Time and Materials and Unit-Price Costs ............................. 17-8

17.17.1 Requirement for Notice .......................................................... 17-8

17.17.2 Requirements for Daily Time and Materials Tickets ............... 17-8

17.17.3 Requirements for Separate Accounting Records.................... 17-8

17.18 Changes Required Based on Bid Alternates ...................................................... 17-9

17.19 Change Orders Include Full and Final Compensation ....................................... 17-9

17.20 Alterations to Directives and Change Orders Prohibited ................................. 17-9

17.21 District Not Liable for Non-Conforming Work .................................................. 17-9

PART 18 FINAL INSPECTION AND COMPLETION OF WORK ................................................................ 18-1

18.1 Contractor Must Determine When Work is Complete ..................................... 18-1

18.2 Contractor Must Complete Prerequisites Before Inspection ........................... 18-1

18.3 Contractor’s Initial Request for Final Inspection .............................................. 18-2

18.4 Requirements for Re-Inspection of Work ......................................................... 18-2

18.5 Determination that Work is Substantially Complete ........................................ 18-3 ix

006140.00003 24027126.5

18.6 Contractor Must Timely Complete Remaining Work........................................ 18-3

18.7 Contractor Request for Final Walk-Through ..................................................... 18-3

18.8 Contractor Responsible for Certain Inspection Costs ....................................... 18-3

18.9 Acceptance of the Completed Project .............................................................. 18-4

PART 19 CLOSE-OUT OF THE WORK .................................................................................................... 19-1

19.1 Close-Out Submittals are Prerequisite to Final Payment ................................. 19-1

19.2 As-Built Plans and Specifications ...................................................................... 19-1

19.3 Project-Related Documents .............................................................................. 19-1

19.4 Equipment Operations and Maintenance Manuals .......................................... 19-1

19.4.1 Required Contents .................................................................. 19-1

19.4.2 Required Format ..................................................................... 19-2

19.4.3 Required Correction and Certification .................................... 19-2

19.5 Special Guarantees and Warranties ................................................................. 19-2

19.6 Identification-Tag Log ....................................................................................... 19-2

19.7 Keys for Doors, Panels, Cabinets, Et Cetera ...................................................... 19-2

19.8 Tools, Spare Parts, Et Cetera ............................................................................. 19-3

19.9 DSA Close-Out Materials ................................................................................... 19-3

19.10 Contractor Warranty ......................................................................................... 19-3

19.11 Other Contract Document Close-Out Requirements ........................................ 19-3

PART 20 CONTRACTOR GUARANTEE OF WORK .................................................................................. 20-1

20.1 No Waiver of District Rights .............................................................................. 20-1

20.2 Contractor’s General Warranty of Work .......................................................... 20-1

20.3 Limitations on Contractor Guarantee ............................................................... 20-1

20.4 Applicable Guarantee Periods ...................................................................... 20-1

20.5 Specific Guarantee Periods for HVAC and Roofing ........................................... 20-2

20.6 Manufacturer and Other Third-Party Guarantees and Warranties .................. 20-2

20.7 Guarantee Work by Contractor ........................................................................ 20-2

20.8 District Performance of Guarantee Work ......................................................... 20-2

20.9 Two-Year Extended Guarantee Period After Guarantee Work ........................ 20-3

20.10 Warranty of Title to Work ................................................................................. 20-3

PART 21 PROGRESS PAYMENTS AND FINAL PAYMENT ...................................................................... 21-1

21.1 Maximum Amount Payable to Contractor ........................................................ 21-1

21.2 Contractor Must Propose a Schedule of Values ............................................... 21-1

21.3 Contractor Must Obtain Approval of Schedule of Values ................................ 21-2

21.4 Contractor Must Monitor and Update Schedule of Values .............................. 21-2

21.5 Payment for On-Site Materials Not Incorporated into Work ........................... 21-2

21.6 Payment for Specially Manufactured Items Stored Off-Site ............................ 21-3

21.7 Contractor Must Arrange Progress Payment Review Meetings ....................... 21-4 x

006140.00003 24027126.5

21.8 Contractor Submittal of Progress Payment Requests ...................................... 21-4

21.8.1 Timing and Content of Progress Payment Request ................ 21-4

21.8.2 Materials to be Submitted with Progress Payment Request.. 21-5

21.8.3 Final Progress Payment Request ............................................ 21-6

21.8.4 Copies of Progress Payment Requests and Supporting

Materials ................................................................................. 21-6

21.9 Requirement for Progress Payment Waivers and Releases ............................. 21-6

21.10 Summary of Public Contract Code Sections 9204 and 20104.50 ..................... 21-6

21.11 Contractor Compliance a Condition Precedent ................................................ 21-7

21.12 Review by Project Manager and Inspector of Record ...................................... 21-7

21.13 Architect Decisions Regarding Progress Payment Requests ............................ 21-7

21.13.1 Architect Review of Recommendations ................................. 21-7

21.13.2 Notice of Approval or Disapproval ......................................... 21-8

21.13.3 Certification of Payment Upon Approval ................................ 21-8

21.13.4 Rejection and Resubmittal of Progress Payment Requests .... 21-8

21.14 Withholding of Retention from Payments to the Contractor ........................... 21-8

21.15 Additional Deductions and Withholdings ......................................................... 21-9

21.15.1 Authority and Reasons ............................................................ 21-9

21.15.2 Amount and Application ....................................................... 21-10

21.16 District Payment of Construction Progress Payments .................................... 21-10

21.17 Final Payment and Release of Retention ........................................................ 21-11

21.18 District Issuance of Joint Checks ..................................................................... 21-11

21.19 District Does Not Waive Rights by Inspecting, Approving or Paying .............. 21-11

21.20 Contractor Must Timely Pay Subcontractors .................................................. 21-12

21.21 Stop Notices and Liens .................................................................................... 21-13

21.22 Unconditional Waivers and Releases After Final Payment ............................. 21-13 PART 22 TERMINATION OF WORK AND OTHER REMEDIES ................................................................ 22-1

22.1 Cause for Termination of the Contractor’s Right to Perform Work ................. 22-1

22.2 Opportunity to Cure and Termination for Cause .............................................. 22-1

22.3 Surety and District Rights to Perform Work After Termination for Cause ....... 22-2

22.4 District Performance of Work After Termination for Cause ............................. 22-2

22.5 Contractor Compensation After Termination for Cause .................................. 22-2

22.6 Termination for Convenience of Contractor’s Right to Perform Work ............ 22-3

22.7 Contractor Must Cease Work Upon Termination for Convenience ................. 22-3

22.8 Documenting Costs After Termination for Convenience .................................. 22-3

22.9 Compensation After Termination for Convenience.......................................... 22-3

22.10 Termination by the Contractor for Cause ......................................................... 22-4

22.11 Documenting Costs After Termination by Contractor for Cause ...................... 22-5

22.12 Remedies for Default Other Than Termination ................................................ 22-5

22.13 Declaring the Contractor a Non-Responsible Bidder ........................................ 22-6 xi

006140.00003 24027126.5

PART 23 INDEMNIFICATION OF DISTRICT AND OTHERS ..................................................................... 23-1

23.1 Indemnification of District and its Representatives ......................................... 23-1

23.2 Contractor Defense of District and its Representatives ................................... 23-1

23.3 Indemnification of Officers, Employees, and Agents of District Indemnitees .. 23-2

23.4 Limitation on the Contractor Indemnification Obligations .............................. 23-2

23.5 Contractor Must Ensure Subcontractors Indemnify District ............................ 23-2

23.6 Attorney’s Fees ................................................................................................. 23-2

PART 24 CLAIMS AND LEGAL PROCEEDINGS ....................................................................................... 24-1

24.1 Requirements and Procedures for Filing Claims Are Mandatory ..................... 24-1

24.2 Mandatory Time Limits for Filing of Claims ...................................................... 24-1

24.3 Content of Claims and Substantiating Materials .............................................. 24-1

24.4 Mandatory Certification of Claims Subject to Penalty of Perjury ..................... 24-1

24.5 Prerequisites for Filing Delay Claims................................................................. 24-2

24.6 Method of Filing Claims .................................................................................... 24-2

24.7 PCC Claims Procedures ..................................................................................... 24-2

24.8 District Requests for Additional Information .................................................... 24-3

24.9 Procedures for Initial Review of Claim by Architect ......................................... 24-3

24.10 District Response to Claim Following Initial Architect Review ......................... 24-3

24.11 Initiation of Informal Claim-Resolution Efforts ................................................. 24-3

24.12 Documentation of Compromise ....................................................................... 24-4

24.13 Architect Ruling if Claim Remains Unresolved.................................................. 24-4

24.14 Conditions Precedent to Initiating Subsequent Actions ................................... 24-4

24.15 Contractor Must Continue Work While Claims Pending .................................. 24-4

24.16 Resolving Disputes Through Binding Arbitration .............................................. 24-4

24.17 Resolving Disputes in Court of Competent Jurisdiction.................................... 24-5

24.18 Neither Party’s Remedies are Limited .............................................................. 24-5

24.19 Applicable Law and Venue ................................................................................ 24-5

PART 25 MISCELLANEOUS PROVISIONS .............................................................................................. 25-1

25.1 Entire Understanding and Agreement .............................................................. 25-1

25.2 Provisions Required by Law Deemed Included ................................................. 25-1

25.3 Execution of Documents in Counterparts ......................................................... 25-1

25.4 Captions and Headings ..................................................................................... 25-1

25.5 No Third-Party Beneficiaries of Contract .......................................................... 25-1

25.6 Circumscribed Right to Assign Contract............................................................ 25-1

25.7 Waiver of Contract Requirements .................................................................... 25-2

25.8 Requirements of Contract are Severable ......................................................... 25-2

25.9 Assignment of Anti-Trust Claims ....................................................................... 25-2

25.10 Service of Demands and Other Notices ............................................................ 25-2

25.11 Public Inquiries and Complaints ....................................................................... 25-3 xii

006140.00003 24027126.5

25.12 District Notice of Third-Party Claims ................................................................ 25-3

ATTACHMENT A TO GC GENERAL PROVISIONS - OWNER CONTROLLED INSURANCE PROGRAM (OCIP)

1-1

006140.00003 24027126.5

PART 1

ACKNOWLEDGMENT, ORGANIZATION, AND

INTERPRETATION OF GENERAL PROVISIONS

1.1 Contractor Acknowledgment of General Provisions. These General Provisions are an integral component of the Contract Documents. By entering into the Contract, the Contractor: (i) acknowledges that it had the opportunity prior to submitting its bid for the Work to review and seek clarification of any and all provisions of these General Provisions from the District, Architect, and/or Project Manager; and (ii) acknowledges and agrees that the Contractor shall be deemed and construed to have read and that it fully understands these General Provisions. The Contractor shall not disclaim either knowledge of, or the meaning and effect of, any term or provision of these General Provisions and shall strictly abide by their meaning and intent. The Contractor further acknowledges that these General Provisions include requirements for including various provisions in the Contractor’s contracts with its Subcontractors. THE CONTRACTOR MUST PROVIDE A COPY OF THESE GENERAL PROVISIONS TO EACH SUBCONTRACTOR AND SHALL REQUIRE IN EACH OF ITS SUBCONTRACTS THAT THE SUBCONTRACTOR

ALSO MUST READ AND UNDERSTAND THESE GENERAL PROVISIONS.

1.2 Organization of General Provisions. These General Provisions are organized according to general subject matter. However, requirements applicable to any particular item, material, service, scope, et cetera, may be included in multiple provisions of these General Provisions. Therefore, unless expressly stated otherwise, the requirements of any one provision in these General Provisions shall not be deemed or construed to govern or apply exclusively over other provisions in these General Provisions applicable to the same item, material, service, scope, et cetera. The provisions of these General Provisions are also organized based on a numbering system in which: (i) Parts (e.g., Part 3) may be subdivided into Sections (e.g., Section 3.5); and (ii) Sections may be subdivided into Subsections (e.g., Subsection 3.5.1). Lists (i.e., enumerations of items) are set forth in these General Provisions using Romanette symbols (i.e., i, ii, iii, iv, et cetera).

1.3 Guides for Interpreting General Provisions. As used in these General Provisions, “shall” and “must” shall be deemed and construed as mandatory, and “may” shall be deemed and construed as permissive. If any pronoun, term or phrase in these General Provisions is stated in either the masculine or feminine sense (e.g., “materialman”), the pronoun, term or phrase, unless otherwise required by context, shall be interpreted as including both or either of such genders. Unless specified otherwise, any reference in these General Provisions to a number of “days,” “months,” or “years” shall mean, respectively, calendar days, months or years. Unless specified otherwise, any reference in these General Provisions to a number of “hours,” “days,” “weeks,” “months” or “years” shall mean, respectively, consecutive hours, days, weeks, months or years. Language in these General Provisions to the effect that the Contractor or other person or entity is to provide or furnish something, or words to the same or similar effect, shall be deemed to mean that the thing must be “provided, complete in place,” “furnished and installed,” or otherwise incorporated into the Work and/or used as necessary to complete the Work and/or administer the Contract in accordance with the Contract Documents. For the convenience of the reader and in order to shorten the length of these General Provisions, capitalized terms are used in these General Provisions to designate defined terms. Each term or phrase that is not capitalized or defined shall be construed in accordance with the meaning commonly associated with such term or phrase within the State and region within which the Project is located.

1-2

006140.00003

1.4 Locations of Definitions of Capitalized Terms. For the convenience of the reader, the following table specifies the location in these General Provisions and other Contract Documents of the definitions of certain capitalized terms used in these General Provisions. The following table may not include all such capitalized terms and, therefore, should not be considered to be a comprehensive list of all such defined terms.

Defined Term Location of Definition in General Provisions

Location of Definition in Other Contract Documents

Abnormal Weather Section 13.15

Accident Report Subsection 11.10.1

Addenda Section 4.5

Architect* Section 2.2 *Identified in Special Provisions

Architect Field Directive Section 17.3

As-Built Plans and Specifications Subsection 3.9.1

As-Built Plans Change Log Subsection 3.9.3

Asbestos Remediation Section 15.5

Authorized Contractor Officer Section 16, Instructions For Bidders

Authorized District Officer Section 2.1

Bulletin Subsection 4.13.3

Cal-OSHA Section 11.4

CCD Section 17.1.2

CCR Section 2, Instructions For Bidders

Certification of Final Inspection Section 18.3

Certification of Payment Subsection 21.13.3

Change Order Section 17.2

Change Order Cost Section 17.7

Change Order Request Section 17.8

Claim Section 24.1

Clarification Subsection 4.13.3

1-3

006140.00003 24027126.5

Defined Term Location of Definition in General Provisions

Location of Definition in Other Contract Documents

Commencement Date Section 4, Construction Services Agreement

Compensable Delay Section 13.18

Conduct Rules Section 10.20

Construction Change Directive Subsection 17.1.3

Construction Progress Payment Section 21.16

Contract Section 4.1

Contract Documents Section 4.1

Contractor Guarantee Section 20.2

Contract Price Section 5, Construction Services Agreement

Contract Time Section 4, Construction Services Agreement

County Section 7.5

Deferred Approval Section 5.10

District Board Section 2.1

District Indemnitee Section 23.1

Plans Subsection 4.3.1

Emergency Section 3.7

EPA Section 15.6

Guarantee Period Section 20.4

Guarantee Work Section 20.7

HCP Section 15.2

Inspector of Record Section 2.2

Interpretation Subsection 4.13.3

Job Superintendent Subsection 3.4.1

Master Construction Schedule Subsection 13.3.1

1-4

006140.00003 24027126.5

D…