Amendment Two.pdf
PDF 96 KB Posted
- Attached to
- Grizzly Creek Restroom Replacement Federal contract opportunity
- Solicitation number
- AG-9JNE-S-10-0009
About this file
Amendment Two
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment Five.pdf | ||
| Amendment Five Revised Specs_060310.pdf | ||
| Amendment Four.pdf | ||
| Combined Amendment 3.pdf | ||
| Amendment One.pdf | ||
| Return Package.pdf | ||
| C1.12009 Grizzly RR EXISTING RR.pdf | ||
| Wage Determination 04-12-10.pdf | ||
| P1.0 E1.0 Plumbing and Electrical.pdf | ||
| C2.1 2009 Grizzly RR REPLACEMENT RR 4.pdf | ||
| Specifications.pdf | ||
| C3.0 Accble-Hyd-Layout1.pdf | ||
| T2.0 2009 Grizzly RR -Location Map.pdf | ||
| T1.0 2009 Grizzly RR-COVER PAGE.pdf | ||
| S1.0 TO 2.3 STRUCTURALS.pdf | ||
| C2.0 2009 Grizzly RR REPLACEMENT 1.pdf | ||
| C1.0 2009 Grizzly RR SITEPLAN.pdf | ||
| Fire Plan_0809_BkRD.pdf | ||
| Solicitation.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE Page of Pages 1 3
2. Amendment/Modification No. 3. Effective Date 4. Requisition/Purchase Req. No. 5. Project No.
Two 05/14/2010
6. Issued By: Code 7. Administered By: Code USDA Forest Service Sierra Cascade Province, Acquisition Group 2550 Riverside Drive Susanville, CA 96130
See Block 6
8. Name and Address of Contractor (X) 9A. Amendment of Solicitation No.
AG-9JNE-S-10-0009
9B. Dated (See Item 11)
4/16/2010 10A. Modification of Contract No.
10B. Date Issued (See Item 13)
Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning ___1___ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE
CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. This Change Order is issued pursuant to: (specify authority) The changes set forth in item 14 are made in the Contract
Order No. in item 10A.
B. The above numbered contract/order is modified to reflect the administrative changes set forth in Item 14. pursuant to the authority of FAR 43.103(b).
C. This supplemental agreement is entered into pursuant to authority of:
D. Other (specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _1__ copies to the issuing office.
14. Description of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment to the Solicitation for Grizzly Campground Restroom Replacement.
Attached are two more questions and answers from that meeting.
The receipt of Offers is extended to May 21, 2010 COB.
Please replace the Schedule of Items with the Revised Schedule of Items.
By signature in Block 15B Contractor releases the Government from all claims relating to this modification. This settlement is complete accord and satisfaction. Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name and Title of Signer 16A. Name and Title of Contracting Officer
15B. Contractor/Offeror Date Signed 16B. United States of America Date Signed
(Authorized Signature) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION UNUSABLE
30-105 STANDARD FORM 30 (REV.10-83)
PRESCRIBED BY GSA
FAR (48CFR) 53.243
Name of Offeror or Contractor Amendment No. Two
ITEM NO. DESCRPITION METHOD
OF
MEASURE
QUANTITY PAY UNIT UNIT PRICE TOTAL
SCHEDULE OF ITEMS
01010 RESTROOM BUILDING (Incl. plumbing and Elec.) CQ 2 EA $ _______ $_______
1505 MOBILIZATION LSQ ALL LS xxxxxx $_______
SELECTIVE DEMOLITION
02070 REMOVAL OF EXISTING UTILITIES LSQ ALL LS xxxxxx $_______
CLEARING AND GRUBBING
02110B BUILDING AND WALKWAY LSQ ALL LS xxxxxx $_______
UTILITY TRENCH AND BACKFILL
ELECTRICAL CQ 30 LF $_______ $_______
WATER CQ 30 LF $_______ $_______
AGGREGATE BASE
2223 ACCESS ROAD AND PARKING AREA CQ 1,000 SF $_______ $_______
ROCK MATERIAL
02271 TRAFFIC ROCK BARRIERS (I TON) CQ 20 EA $_______ $_______
2553 ASPHALT CONCRETE PAVEMENT CQ 15 TON $_______ $_______
ACCESS ROAD AND PARKING AREA
CONCRETE
3300 BUILDING SLAB CQ 1,664 SF $_______ $_______
03300B UTILITY BOXES CQ 8 EA $_______ $_______
WATER SYSTEM
13208A WATER LINE REPLACEMENT CQ 30 LS $_______ $_______
ACCESSIBLE HYDRANT INSTALLATION CQ 2 EA $_______ $_______
LIGHTING AND ELECTRICAL
16050 SITE ELECTRICAL (Service to Restroom) LSQ ALL LS xxxxxx $_______
TOTAL ALL ITEMS
Grizzly Campground Restroom Replacement Amendment Two
How many boulders are needed for this job?
The schedule of Items shows 20 EA under the boulders. There will only be two boulders per rest-room (a total of four boulders) to be furnished and installed by the contractor as per the drawings and specifications. Revised schedule of items is attached.
How will the government pay for quality control testing?
The specifications state that the contractor is responsible for materials testing and compaction testing as per the specifications. The quality control is incidental to it's respective item. For example compaction testing for the base and sub base are incidental to 02220 - Earth Work and the compression testing for concrete shall be incidental to 03300 - Concrete.
| Modification Amendment sf-30 #2 |
| Modification 2 |
| Sheet1 |