Amendment Five.pdf

PDF 71 KB Posted

Attached to
Grizzly Creek Restroom Replacement Federal contract opportunity
Solicitation number
AG-9JNE-S-10-0009
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

Amendment Five

View the file

Other files for this federal contract opportunity

Other files attached to Grizzly Creek Restroom Replacement, newest first.
File Type Posted
Amendment Five Revised Specs_060310.pdf PDF
Amendment Four.pdf PDF
Combined Amendment 3.pdf PDF
Amendment Two.pdf PDF
Amendment One.pdf PDF
Return Package.pdf PDF
C1.12009 Grizzly RR EXISTING RR.pdf PDF
Wage Determination 04-12-10.pdf PDF
P1.0 E1.0 Plumbing and Electrical.pdf PDF
Solicitation.pdf PDF
C2.1 2009 Grizzly RR REPLACEMENT RR 4.pdf PDF
Specifications.pdf PDF
C3.0 Accble-Hyd-Layout1.pdf PDF
T2.0 2009 Grizzly RR -Location Map.pdf PDF
T1.0 2009 Grizzly RR-COVER PAGE.pdf PDF
S1.0 TO 2.3 STRUCTURALS.pdf PDF
C2.0 2009 Grizzly RR REPLACEMENT 1.pdf PDF
C1.0 2009 Grizzly RR SITEPLAN.pdf PDF
Fire Plan_0809_BkRD.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE Page of Pages 1 2

2. Amendment/Modification No. 3. Effective Date 4. Requisition/Purchase Req. No. 5. Project No.

Amendment 5 June 7, 2010

6. Issued By: Code 7. Administered By: Code USDA Forest Service Sierra Cascade Province, Acquisition Group 2550 Riverside Drive Susanville, CA 96130

See Block 6

8. Name and Address of Contractor (X) 9A. Amendment of Solicitation No.

AG-9JNE-S-10-0009

9B. Dated (See Item 11)

4/16/2010 10A. Modification of Contract No.

10B. Date Issued (See Item 13)

Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning ___1___ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting and Appropriation Data (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE

CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X) A. This Change Order is issued pursuant to: (specify authority) The changes set forth in item 14 are made in the Contract

Order No. in item 10A.

B. The above numbered contract/order is modified to reflect the administrative changes set forth in Item 14. pursuant to the authority of FAR 43.103(b).

C. This supplemental agreement is entered into pursuant to authority of:

D. Other (specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return ___ copies to the issuing office.

14. Description of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Grizzly Creek Campground Restrooms.

Changes were made to the solicitation Schedule of Items and the Specifications. The scope of the project remains unchanged. Delete the previous Specifications (78 pages) and replace with Specifications Amendment 5 (89 pages).

Review the attached Schedule of Items and Specifications. Submit a copy of “Amendment 5 Schedule of Items” by June 17, 2010, COB. New bid bonds will not be required for offers submitted previously. Revised technical proposals may be submitted but are not required.

All other terms and condition remain unchanged.

By signature in Block 15B Contractor releases the Government from all claims relating to this modification. This settlement is complete accord and satisfaction. Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name and Title of Signer 16A. Name and Title of Contracting Officer

15B. Contractor/Offeror Date Signed 16B. United States of America Date Signed

(Authorized Signature) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (REV.10-83)

PRESCRIBED BY GSA

FAR (48CFR) 53.243

Amendment Five

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS SCHEDULE OF ITEMS

Name of Offeror or Contractor

ITEM NO. DESCRIPTION METHOD

OF

MEASURE

QUANTITY PAY UNIT UNIT PRICE TOTAL

SCHEDULE OF ITEMS

DIVISION 1 - GENERAL

01505 MOBILIZATION LSQ 1 JOB xxxxxxx $________

01810 BUILDINGS LSQ 2 JOB $_______ $________

DIVISION 2 – SITE WORK

02200 EARTHWORK LSQ 1 JOB xxxxxxx $_________

TOTAL ALL ITEMS

QUANTITY

File details come from the government source that posted it. Updated .