2Revised_Section_C_for_Amendment_1.pdf

PDF 74 KB Posted

Attached to
Callahan North Residence Remodel Federal contract opportunity
Solicitation number
AG-9AC7-S-15-0104
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

02 Revised Section C

View the file

Other files for this federal contract opportunity

Other files attached to Callahan North Residence Remodel, newest first.
File Type Posted
6Site_Visit_Notes.pdf PDF
1Summary_of_changes_for_Amendment_2.pdf PDF
5_attach__4SF24_Bid_Bond.pdf PDF
4attach_2Plans_Rev_01_0615.pdf PDF
3attach_1SpecialProject_Specs_A2.pdf PDF
Amendment2_SF30.pdf PDF
Amendment_001_AG-9AC7-S-15-0104-signed.pdf PDF
General_Decision_Number.pdf PDF
PLANS-CALLAHAN-NORTH-REMODEL.pdf PDF
Callahan_North_Project_Specsrevised.pdf PDF
AG-9AC7-S-15-0104_Solicitation.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Callahan North Residence Remodel, Klamath NF - 6 -

AG-9AC7-S-15-0104 Amendment 2

SECTION C - Description/Specifications/Statement of Work

C.1 Scope of Work

The project is to remodel and upgrade a government residential building within the Callahan Guard

Station on the Klamath National Forest. The work includes, but is not limited to, removing existing siding, removal and replacement of exterior bat insulation with R-15, installing new siding and house wrap, installing exterior wall ½” OSB sheathing, patching the roof, removal and repair of exposed wall framing where destroyed by wood eating pests or moisture, upgrading the electrical service to the building from its current 100 amp service to a new 200 amp service (verify final panel location with utility company prior to setting panel and other wiring to avoid possible conflict with roof) with circuits for a heat pump, installing a new heat pump and corresponding ductwork and concrete pad for the condenser, removing hallway 7’ drop ceiling and replace with drywall lid, tape and texture to match remaining ceiling and walls and to accommodate new attic access work, removing existing furnace (and it’s closet), kitchen chimney and all associated ductwork, patching any existing openings for components from existing ductwork, replacing all the windows, replacing the front and back doors and frames and hardware, installing new screen doors on both the back and front of the building, modifying the attic for the new heat pump, replacing all the interior and exterior light fixtures and their corresponding electrical components, removing existing linoleum flooring and particle board underlayment, removal and replacement of damaged or interfering portions of subfloor in kitchen, laundry area and bath, installing new carpet and vinyl flooring system, relocating or replacement of any plumbing lines as needed, installing new cabinets, countertops and backsplash, install venting hood and ducting over the stove, associated roof penetrations and flashing systems, removing gas piping for the gas dryer. Drywall removed on any wall to accommodate proposed improvements or utility work shall be removed completely and replaced, at a minimum, to the nearest corner transition point (floor to ceiling, wall corner to wall corner). Bathroom work includes remodeling existing bathroom and installing new bathroom with bathtub/shower, shower kit, surround, toilets, vanity, sinks, mirrors and towel racks in both baths, texturing and painting all walls and ceilings in the building, replacing damaged studs in the living room, sweep and clear existing chimney flue, and verify and repair, if necessary, fireplace stove proper operation and functionality, installing a new hearth for the wood stove to meet code compliance, installing new vinyl flooring in the front entryway, relocating a bathroom wall, constructing new walls and door frames, doors and hardware

(suitable for bathrooms and bedrooms) constructing a partition wall with doorway, and installing a new water heater. The complete description of the work and all required specifications are included as an attachment called Callahan North Residence Reconstruction Special Project Specifications (Amendment

2).

The primary descriptions within the specifications were developed utilizing standard Construction

Industry specifications incorporating the latest California Building Codes and Title 24 Energy Efficiency

Standards, plus Green Building Council for green, biobased, and energy efficient construction. The

Contractor shall utilize products and materials that promote energy conservation, waste reduction, use of recovered materials, environmentally preferable, with recycled content or biobased materials (e.g., insulating foam and composite panels), and are energy efficient (Energy Star-qualified) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered.

C.2 Location of Project

The project is located at the US Forest Service’s Callahan Guard Station’s North Residence owned by the Klamath National Forest. The guard station is located at 12549 S Highway 3 Callahan, California

96014. Refer to project map on the plans

Callahan North Residence Remodel, Klamath NF - 6 -

AG-9AC7-S-15-0104 Amendment 2

C.3 Codes and Standards

All work shall be performed in accordance with the 2010 California Building Code, 2010 California

Plumbing Code, 2010 California Electrical Code, 2010 California Mechanical Code, 2010 California Fire

Code, 2010 California Energy Code, and 2010 Architectural Barriers Act (ABA) as specified elsewhere herein.

C.4 Attachments to Statement Of Work/Specifications AGAR 452.211-73 (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made a part of this solicitation and any resultant contract. See the special project specifications included as an attachment.

File details come from the government source that posted it. Updated .