Specifications.pdf

PDF 227 KB Posted

Attached to
Witch Fire Road Repair Federal contract opportunity
Solicitation number
AG-9A40-S-16-0005
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Witch Fire Road Repair, newest first.
File Type Posted
Revised_SF-30.pdf PDF
Pre-Bid_attendance_Sheet.pdf PDF
Pre-Bid_Mtg_Notes.pdf PDF
Revised_Road_Logs_.pdf PDF
Revised_Schedule_of_Items.xls XLS spreadsheet
Contract_Map_(North_Map_2).pdf PDF
RIPRAP_rev.pdf PDF
Section_L_and_M_(Part_IV).pdf PDF
SF-30.pdf PDF
Statement_of_Work.pdf PDF
Witch_Fire_Road_Logs.pdf PDF
Fire_Plan_.pdf PDF
Schedule_of_Items.xls XLS spreadsheet
Wage_Determination.pdf PDF
SPS.pdf PDF
Drawings.pdf PDF
Maps.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Standard Specifications

Attachment A

Standard Specifications included:

Section 806 - REGULATORY REQUIREMENTS Section 807 - EQUIPMENT RENTAL Section 808 - WORK AREA MANAGEMENT Section 811 - BLADING Section 813 - SPOT SURFACING Section 814 - ASPHALT PAVEMENT PATCHING Section 815 - PAVED SURFACE CLEANING Section 816 - MAINTENANCE OF UNPAVED SHOULDERS Section 819 - RIPRAP Section 831 - DITCH MAINTENANCE Section 832 - REMOVE AND END HAUL MATERIALS Section 833 - CULVERT REPLACEMENT Section 834 - DRAINAGE STRUCTURE MAINTENANCE Section 835 - ROADWAY DRAINAGE MAINTENANCE Section 836 - ROAD DECOMMISSIONING Section 838 - MAINTENANCE FOR LIMITED USE Section 839 - RESTORE DRAINAGE FUNCTION Section 841 - CUTTING ROADWAY VEGETATION Section 842 - OUTLET STRUCTURES Section 851 - LOGGING OUT Section 854 - HAZARD REMOVAL AND CLEANUP Section 861 - MAINTENANCE OF CATTLEGUARDS Section 872 - SIGN MAINTENANCE Section 881 - MOBILIZATION Section 882 - EQUIPMENT MOVING Section 883 - CLEANING OF EQUIPMENT Section 884 - MULCHING Section 891 - WATER SUPPLY AND WATERING Section 892 - BITUMINOUS PRODUCTS Section 893 - AGGREGATES Section 894 - CULVERT PIPE

806 – REGULATORY REQUIREMENTS (4/02)

1. DESCRIPTION

This Section identifies the codes and standards which apply to the work in this contract.

2 REQUIREMENTS

The Contractor shall comply with any Federal, State, and municipal laws, codes, regulations, and standards that apply to the work to include but not limited to the following:

29 CFR Part 1926 – Safety and Health Regulations for Construction 49 CFR – Transportation Manual of Uniform Traffic Control Devices (MUTCD) NFPA 30 – Flammable and Combustible Liquids Code NFPA 30A – Motor Fuel Dispensing Facilities and Repair Garages American Society for Testing and Materials (ASTM) Standards

BMP Notes

Soil erosion and storm water pollution control measures, where specified, shall be in accordance with section 204 and Caltrans “Best Management Practices”.

Caltrans Storm Water Quality Handbook, “Construction Site Best Management Practices Manual” (BMP’s) can be purchased from California Department of Transportation, publications distribution unit, (916) 445-3520.

When specified, the contractor shall submit a written “Storm Water Management Plan” at least 5 business days prior to beginning work.

The contractor shall not disturb the area beyond project limits. The contractor shall take all appropriate steps to insure that no discharge or pollutants enter any streambed as a result of the contractor’s work activities.

3 MEASUREMENT AND PAYMENT

No separate measurement or payment will be made for meeting requirements of this Section. All work and materials shall be incidental to paid work in this contract.

807 EQUIPMENT RENTAL (2/99)

1. DESCRIPTION

This Section establishes the basis for the Government to order road maintenance work not otherwise under the contract.

2. PREWORK REQUIREMENTS

Prior to the issuance the Work Order, the Contractor shall provide the Government with a listing of proposed rental rates for specified equipment.

3. EQUIPMENT

a. Equipment under this Section, shall be provided fully operated by the Contractor and includes subcontractor equipment performing work under the contract. A competent qualified operator shall be provided by the Contractor.

b. The Government will review the proposed rates and those common to the area for this type of use.

Mutually agreed rates will be established. Work Orders may be issued as needed to obtain work under this Section.

4. DELIVERY OF EQUIPMENT TO SITE

The Government, in conjunction with the Contractor, will determine if equipment is to be moved onto and off the site by roading under its own power or by use of Contractor's truck transport. The Work Order will include the method of moving as roading or transport. Subsequent moving of equipment from one portion of the job to another shall be by roading unless otherwise documented in the Work Order.

5. HOURS OF OPERATION

Hours of operation shall be the same as for the Contractor's regular work shift, unless otherwise directed in writing by the Government.

6. TIMEKEEPING AND COMPENSATION

a. The Government will maintain a daily record showing the actual hours, to the nearest half (1/2) hour, that the equipment is in operation performing work under this item.

b. Time for equipment roading will commence with the beginning of the move. Time will be counted for the operator during roading.

c. Time for equipment transported will be in accordance with the appropriate of the following:

1. When equipment is not being actively used on the contract at the time moving is ordered under this Section, time will be counted for the transporting vehicle, but not the equipment being transported.

2. Where work under this contract is interrupted for ordered performance under this Section, time will be counted for the transporting vehicle and the equipment that would otherwise have been operating.

d. The equipment hours recorded will be paid for at the agreed rate. Labor costs paid for under this Section will be those paid by the Contractor under this contract.

7. PAYMENT

a. Equipment rental rates will include operator.

b. Payment will be made under:

Pay Item Pay Unit

807(1) Rental Equipment, Type , Hour Horsepower, Minimum 807(2) Equipment Moving, Truck Transport Hour 807(3) Laborer Hour

808 - WORK AREA MANAGEMENT (1/92)

This Section establishes Contractor responsibilities for traffic control and equipment requirements in work areas.

2. REQUIREMENTS

a. Traffic Conditions - Roads other than those listed for work under Section 835 shall be open to traffic with not more than fifteen (15) minutes maximum delay time unless otherwise provided in Special Project Specifications.

b. Work which interferes with use of traveled roadways shall not be initiated or performed until a plan for satisfactory handling of traffic has been approved by the Government.

c. Traffic Control Devices

1. The Contractor shall provide signs and other devices complying with National Standards as contained in Part VI of the Manual of Uniform Traffic Control Devices (MUTCD). Traffic control for occupied work areas shall be in accordance with MUTCD specifications. All signs and devices remain the property of the Contractor.

2. Traffic devices shall be kept current with maintenance operation and removed upon its completion.

3. Traffic approaching the work zone from either direction and side accesses open to travel within the work zone shall be warned by signing.

4. Required signs may be mounted on portable or temporary mountings. Standard MUTCD shapes, colors, sizes, and legends shall be used.

5. Hazards incidental to the work within or on the traveled way, shoulders, or turnouts shall be marked with hazard identification markers, illuminated beacons, and other MUTCD devices to safely guide road users through the area. Work segments not completed on a daily basis shall be marked appropriately for night travel. Contractor shall obtain authorization before commencing work at night.

6. Advisory speed plates may be used to control traffic through the work area.

d. Flaggers - Properly equipped flag person(s) shall be provided where the traffic is required to stop before proceeding. Traffic shall be stopped in locations which provide width enough for passage of traffic and reasonable protection for vehicles. When flag control is used, advance warning signs are required.

e. Contractor's Equipment

1. All vehicles and machinery operating on or from the traveled way or road shoulder shall have flashing lights, strobes, or rotary beacons operated continuously while work is in progress. Truck headlights shall be on while operating. Back-up horns shall be required on all self-propelled equipment.

2. Vehicles and machinery not currently used in the maintenance operation shall be parked off the traveled way at approved locations to minimize interference with normal use.

3. MEASUREMENT AND PAYMENT

No separate measurement or payment will be made for meeting requirements of this Section. All work and materials shall be incidental to paid work in this contract.

811 BLADING (2/99)

1. DESCRIPTION

This work consists of surface blading native or aggregate roads to a condition to facilitate traffic and provide proper drainage. Blading includes shaping the crown or slope of traveled way, maintaining berms and drainage dips, and compacting the surface in accordance with this specification.

2. MAINTENANCE REQUIREMENTS

a. Timing

Surface blading shall be performed during the contract period as ordered by the Government.

b. General

1. The existing traveled way and shoulders, including turnouts unless otherwise ordered, shall be bladed and shaped to produce a surface which is uniform, consistent to grade, and crowned or cross-sloped as indicated by the character of the existing surface unless otherwise Marked on the Ground, to at least one half inch (1/2") per foot of width, but not more than three quarter inch (3/4") per foot of width. Surfacing materials shall be thoroughly loosened to a depth of no less than 2 inches or the depth of potholes or corrugations. Corrugations are washboarding and similar defects. Scarification to facilitate cutting to the full depth of potholes or corrugations may be elected by the Contractor but will be considered incidental to blading. Scarification shall not go deep enough to cause contamination of the surfacing.

2. When Section 891 is included in the Road Listing, the Contractor shall apply water during blading when sufficient moisture is not present to prevent segregation. Water supply, hauling, and application shall be in accordance with Section 891 and shall be incidental to blading unless Pay Items for Section 891 are included in the Schedule of Items.

3. Existing native, rock or aggregate surfaced drainage dips shall be cleaned and shaped incidental to blading to divert surface runoff to existing outlet devices, ditches and discharge locations.

4. The Contractor shall establish a blading pattern which provides a uniform driving surface, retains the surfacing on the roadbed and provides a thorough mixing of the materials within the completed surface width. Upon final blading, no disturbed rock shall protrude more than two (2) inches above the adjacent surface unless otherwise provided in the contract. Material not meeting this dimension shall be removed and placed outside the roadbed so as not to obstruct drainageways or structures. This material may be scattered off the roadbed if there is free drainage.

c. Routine Blading

1. Excess roadbed width shall be shaped only as needed to provide drainage away from the traveled way. Established grasses and other vegetation shall not be removed from the excess width except as incidental to providing drainage or unless otherwise provided in the contract.

d. Compaction

All roads bladed under this section shall be compacted using Method A. Compaction Method A is considered incidental to blading.

Compaction shall commence immediately following blading. Compaction methods are:

Compaction Method A: By breaking track while operating equipment on the bladed surface. Compaction shall cover the full width bladed surface.

Compaction Method B: 8-10 ton pneumatic, steel or equivalent vibrating roller, operated to cover the full width of the bladed surface two (2) times.

e. Intrusions

Where the minimum width of 12 feet is not available, the Contractor shall construct berms where ordered and marked on the ground. Material to provide berms will come from sources designated by the Government.

f. Undercutting

Roadway backslope shall not be undercut.

g. Intersections

1. Intersections with side roads which are not closed or restricted to vehicular use shall be bladed to assure smooth transitions.

2. Field evidence of closure or restrictions shall be considered to be signing, cross ditching in the road surface (traveled way), earth berms or other devices placed to discourage or eliminate use by passenger cars. Also, roads listed for work under Sections 835 or 838 shall be considered restricted.

3. Side roads listed for work under this Section shall be considered as not restricted.

h. Cleaning of Structures

Materials resulting from work under this Section shall not be allowed to remain on or in structures, such as bridges, culverts, cattleguards, drainage dips, aprons, or flumes.

i. Berms

Existing berms shall be maintained to the condition of adjacent segments when ordered by the Government.

j. Scarification

1. This work shall consist of distroying or breaking up old or damaged chip seal and dust oil surfaces and the loosening of native and pit run surfaces for blading and reshaping the road surface.

2. Scarification shall be accomplished by rippers spaced not more than 12 inches apart.

3. Scarification shall not penetrate the aggregate base to the subgrade. Where aggregate base is 3 inches or greater in depth, the minimum scaification depth shall be 3 inches.

3. MEASUREMENT

Measurement under this Section will be made by the total number of units for each item listed in the Schedule of Items completed and accepted.

a. Measurement for blading will be single-lane mile measured along the centerline of the roadway (see quantity measurement terms). Two-lane roads will be measured as two (2) single-lane miles. Measurement will be to the nearest one-tenth (0.1) mile.

b. Each intersection bladed under 2.g. will be equivalent to one-tenth (0.1) single-lane mile; however, when the intersecting side road is scheduled for subsequent blading under this Section, no measurement will be made.

c. Berm maintained or established will be measured by linear foot.

d. No measurement will be made under this Section for Compaction Method A. Measurement for

Compaction Method B will be the same as stated in 3.a for blading.

4. PAYMENT

a. The quantities measured and accepted will be paid for at the contract unit price shown in the Schedule of

Items.

b. Payment will be made under:

Pay Item Pay Unit

811(1) Blading Surfaced Roads Mile 811(2) Blading Native and Pit Run Roads Mile 811(3) Berm Maintained Linear Foot 811(4) Establishing Berms Linear Foot 811(5) Compaction - Method B Mile 811(6) Scarification Pass Mile

813 SPOT SURFACING (3/96)

This work consists of placing surface aggregate as staked on the ground. It includes preparing the area, furnishing, hauling, and placing all necessary materials and other work necessary to blend with the adjacent road cross section.

2. MATERIALS

a. Materials will be Government furnished when stated in Schedule of Items.

b. Materials furnished by the Contractor shall conform to the gradation requirements and the quality requirements of Section 893.

3. MAINTENANCE REQUIREMENTS

a. The area to be spot surfaced shall be thoroughly loosened to a minimum depth of one (1) inch prior to placement of aggregate.

b. Mixing and Placing

1. When scheduled coincident with work under Section 811, spot surfacing and existing aggregate, when ordered, shall be mixed with water until a uniform mixture is obtained prior to final shaping and compaction.

2. The material shall otherwise be spread on the prepared area in layers no more than four (4) inches in depth. When more than one (1) layer is required, each layer shall be shaped and compacted before the succeeding layer is placed. Upon completion, the spot surfacing shall reasonably conform to the adjacent cross section and provide smooth transition in the road profile.

3. Compaction shall be accomplished by using Method A. Compaction Method A is considered incidental. Compaction Method B shall be used when ordered.

Compaction methods are:

Compaction Method A: By breaking track while operating equipment on the bladed surface.

Compaction shall cover the full width bladed surface.

Compaction Method B: 8-10 ton pneumatic, steel or equivalent vibrating roller, operated to cover the full width of each layer two (2) times.

4. MEASUREMENT

a. The quantity will be the number of cubic yards measured in the vehicles, or square yards of aggregate placed, or tonnage verified by weight slips whichever is shown in the Schedule of Items.

b. Hauling is considered incidental when materials are furnished by the Contractor and when the haul distance is less than one (1) mile for Government furnished materials. When the haul distance exceeds one

(1) mile for Government furnished materials haul will be ordered and paid under 832(3).

5. PAYMENT

a. The accepted quantities will be paid for at the contract unit prices shown in the Schedule of Items.

813(1) Spot Surfacing, Grading ____ Cubic Yard 813(2) Spot Surfacing, Grading ____ Square Yard 813(3) Spot Surfacing, Grading ____ Ton 813(4) Spot Surfacing, Government Furnished Materials Cubic Yard 813(5) Compaction Method B Square Yard

814 ASPHALT PAVEMENT PATCHING (2/99)

This work consists of patching potholes, deep patching of asphalt surfaces, skin patching of asphalt surfaces, and patching asphalt berms. The work includes preparing the area to be patched, furnishing and placing all necessary materials and work. All areas to be patched will be marked by the Government.

2. MATERIALS

Materials used for asphalt patching shall conform to the requirements in Sections 892 and 893.

a. Deep Patching

1. Existing materials shall be removed to a minimum of two (2) inches below the bottom of the asphalt surfacing or as necessary to reach firm support, but limited to a maximum depth of eighteen (18) inches.

If firm support for a patch is not available, the hole shall be barricaded and the Government shall be notified. Prior to the Contractor placing any materials, the Government will decide on any corrections to be made.

2. The edges of the prepared hole shall be extended to form a vertical face of unfractured asphalt surfacing. The prepared hole shall be rectangular in shape and cleaned of all loose material. The prepared area shall be backfilled with crushed aggregate base material in layers not to exceed six (6) inches in depth, compacting each layer with mechanical equipment designed for this purpose.

Compaction shall continue until visual displacement ceases. Backfilling shall continue to a depth of four

(4) inches from the top of the existing asphalt surface. The bottom and faces shall be sprayed with an emulsified asphalt.

3. Prepared holes shall be patched or barricaded immediately.

4. The hot bituminous mixture shall be placed in layers not exceeding four (4) inches. Each layer shall be compacted thoroughly with hand tampers, mechanical tampers, or rollers.

5. Finished surface shall be compacted with an eight (8) to ten (10) ton steel roller or comparable vibratory roller. Upon completion, the compacted patch shall be flush with or not more than one quarter (1/4) inch above the level of the adjacent pavement.

b. Skin Patches

1. Prior to skin patching, potholes shall be patched.

2. Minor depressions, light ravelling, or surface checking at scattered locations marked on the ground shall be treated by applying a skin patch.

3. Prior to skin patching, the surface shall be cleaned of loose and deleterious material, then sprayed with emulsified asphalt at the rate of 0.1 gallons per square yard. The emusified asphalt tack coat will be considered incidental to the patching materials. No bituminous mixture shall be placed until the prepared surface is approved by the Government.

4. Hot bituminous mixture shall be distributed uniformly in layers not to exceed two (2) inches compacted depth. When multiple layers are ordered, joints shall be offset at least six (6) inches between layers.

5. Each layer shall be compacted with an eight (8) to ten (10) ton steel roller or comparable vibratory roller.

6. The completed patch shall not have abrupt transitions which adversely affect the steering of a passenger car. The surface must be at least as smooth as the adjacent pavement after twenty-four (24) hours of exposure to traffic.

c. Potholes

1. Surfacing material, loose aggregate, and other debris shall be removed from potholes prior to patching.

2. The cleaned pothole shall be sprayed with emulsified asphalt.

3. The prepared pothole shall be filled with a hard setting cold bituminous mixture and compacted with hand tampers, mechanical tampers, or wheel rolled by deliver vehicles. The finished patch shall not protrude more than one half (1/2) inch above the adjacent surface.

d. Asphalt Berm

Damaged segments of berm shall be removed and exposed ends beveled at approximately forty-five (45) degrees from vertical. The berm foundation shall be cleaned and patched as necessary. The foundation and joining surfaces shall be coated with emulsified asphalt. Asphalt mix shall be placed and compacted to conform with the shape of the undamaged berm segment.

e. Disposal

All materials removed from potholes, patches, and berms shall be disposed of in areas designated by the

Government.

a. Bituminous Mixture

1. Hot and cold bituminous mixture acceptably placed will be measured by the ton for Pay Items 814(2) and 814(4) and by the square yard for Pay Items 814(1) and 814(3). Bituminous materials incorporated into the mixture will be incidental to the item.

2. Ton Measure - The quantity of mixture will be the number of tons in the accepted work. Any material rejected in the field as not meeting specifications shall be deducted based on estimated quantities.

Rejected quantities shall be reconciled between the Government and the Contractor each day. If not reconciled each day, the Government's figures will apply.

b. The following work and materials are incidental:

1. Cleaning of surfaces.

2. Haul and compaction of bituminous mixture.

3. Material removal and disposal.

4. Emulsified asphalt for tack coat.

5. Crushed aggregate backfill material.

5. PAYMENT

a. The accepted quantities will be paid for at the contract unit price shown in the Schedule of Items.

b. Payment will be made under:

Pay Item Pay Unit

814(1) Deep Patching Square Yard 814(2) Skin Patching Ton 814(3) Pothole Patching Square Yard 814(4) Asphalt Berm Maintenance Ton

815 PAVED SURFACE CLEANING (2/99)

This work consists of removing loose material from paved traveled ways, including bridge decks and paved shoulders.

2. EQUIPMENT

a. Equipment shall have the capability of removing all loose material from paved surfaces without damage to the surface.

b. Use of hydraulic flushing equipment will not be permitted within a horizontal distance of two hundred

(200) feet from a live stream, unless approved by the Government.

The paved surface shall be cleaned to the width stated in 4(a) or 4(c) for the Pay Item or as ordered under 4(b).

Materials shall be moved away from road centerline on double-lane roads. Bridge deck cleaning shall require all materials be moved off the deck and disposed of at a designated site.

a. Measurement for Pay Item 815(1), will be by the pass mile, determined by the product of the number of five (5) foot wide increments times the length to the nearest one-tenth (0.1) mile.

b. Partial width passes ordered under Pay Item 815(1) will be measured as full five (5) foot passes.

Additional width incidentally produced by Contractor's equpment will not be considered as a partial pass.

c. Measurement for Pay Item 815(2) will be single lane miles measured to the nearest one-tenth (0.1) miles for cleaning the entire width of the paved surface, including turnouts.

d. Measurement for Pay Item 815(3) will be for cleaning the entire length and width of the surface of each bridge and paved approaches.

a. The ordered and accepted quantities shall be paid for at the unit price shown in the Schedule of Items.

815(1) Paved Surface Cleaning Pass Mile 815(2) Paved Surface Cleaning Single Lane Mile 815(3) Bridge Deck Cleaning Each

816 MAINTENANCE OF UNPAVED SHOULDERS (2/99)

This work consists of maintaining unpaved shoulders adjacent to a paved traveled way. Work will be Marked on the Ground.

2. MAINTENANCE REQUIREMENTS

Existing shoulder material shall be bladed and shaped the entire width to drain away from the traveled way.

Vegetative or other unsuitable materials may be bladed onto slopes adjacent to the roadbed. The shoulder material shall be moistened as necessary for compaction. The shoulder shall be compacted adjacent to paved surface edge prior to final shaping. Grader wheels may be used for this compaction. Final shaping shall provide a smooth transition to the paved surface edge. Upon completion, the paved surface shall be cleaned of loose materials in accordance with Section 815 and is incidental.

3. MEASUREMENT

Measurement of unpaved shoulder maintenance will be the number of side miles of each shoulder completed and accepted. Measurement will be to the nearest one-tenth (1/10) mile determined along the centerline.

4. PAYMENT

a. The accepted quantities shall be paid for at the contract unit price shown in the Schedule of Items.

816(1) Unpaved Shoulder Maintenance Side Mile

819 RIPRAP (11/07)

This work shall consist of furnishing, hauling and placing erosion resistant and protective materials for use on embankments, streambanks, culvert inlets and outlets, channel bottoms and side slopes, abutment wings, structure foundations, and other designated locations.

2. EQUIPMENT

All methods employed in performing the work and all equipment, tools and machinery used for handling the material and executing any part of the work shall be subject to the approval of the Government before the work is started, and whenever unsatisfactory, they shall be changed or improved as required.

3. MATERIALS

Unless shown in the Schedule of Items, all materials shall be furnished by the Contractor and shall meet the following requirements:

a. Riprap

Rock used for riprap shall be hard angular rock with a Durability Absorption Ratio greater than 23 or between 10 – 23 if the Durability Index is greater than 52.

Durability Absorption Ratio = Durability Index (Course) AASHTO T 210 Percent Aborption + 1 AASHTO T 85

Neither the breadth nor thickness of any piece of riprap shall be less than one-third its length. Rock shall be free from overburden, spoil, shale, and organic material; shall meet the following gradation requirements for the class specified; and shall be delivered to designated locatons.

Rock for grouted riprap shall be free of fines that prevent penetration of grout.

Size of Rock (Pounds)

Percent of Total Weight Smaller Than the Given Size

Class I 50 100 35 80 10 50 2 Not to exceed 10

Class II 100 100 60 80 25 50 2 Not to exceed 10 Class III 250 100 150 80 50 50 10 Not to exceed 10

Class IV 400 100 250 70 100 30

Size of Rock (Pounds)

Percent of Total Weight Smaller Than the Given Size

20 Not to exceed 10

Class V 700 100 400 70 200 30 25 Not to exceed 10

Class VI 1,600 100 800 70 400 30 50 Not to exceed 10

Class VII

2.700 100 1,600 70 800 30 100 Not to exceed 10

Class VIII 4,000 100 2,000 80 500 50 100 Not to exceed 10

Class IX 6,000 100 3,000 80 1,000 50 200 Not to exceed 10

Each load of riprap shall be well graded from the smallest to the maximum size specified.

b. Grout

Grout for riprap shall be delivered to designated sites. Grout for riprap shall consist of concrete containing 5 sacks of cement per cubic yard, aggregate with a maximum size of ¾ inches, and water limited to that necessary to ensure good workability. Reasonably clean and strong aggregate of appropriate size gradation, as approved by the CO, shall be used.

A water reducer, set retarder shall be submitted for approval and will include recommended dosage for 2, 3, and 4 hour hauls.

The quantity will be the number of cubic yards measured in the hauling vehicles, or tonnage verified by certified weight slips whichever is shown in the Schedule of Items.

Hauling is considered incidental when materials are furnished by the Contractor and when the haul distance is less than one (1) mile for Government furnished materials. When the haul distance exceeds one (1) mile for Government furnished materials haul will be ordered and paid under 832(3).

Application of grout will be measured by the hour for mixer truck standby starting when application begins. On site mixing and setup will be considered incidental to grout cost.

6. PAYMENT

The accepted quantity will be paid for at the contract unit price shown in the Schedule of Items.

The loading and hauling of Govermnet furnished riprap will be paid for under Section 832.

Payment will be made under:

819(1) Riprap, Class _____ Ton 819(2) Riprap, Government Furnished Cubic Yard 819(3) Grout Cubic Yard 819(4) Grout Application Hour

831 DITCH MAINTENANCE (2/99)

1. DESCRIPTION

This Section provides for routine maintenance of various types of ditches to provide a waterway which is unobstructed, at locations marked on the ground. Drainage ditch maintenance is limited to materials contained within the ditch below the elevation of the adjacent edge of the traveled way or shoulder.

2. MAINTENANCE REQUIREMENTS

a. Ditches shall be maintained by removing rock, soil, wood, and other materials. Upon completion the maintained ditch shall be of the same character as abutting segments that were not required to be maintained.

b. Backslopes shall not be undercut by removal operations.

c. Suitable material up to four (4) inches in greatest dimension removed from the ditches may be blended into existing native road surface and shoulder or placed in designated berm.

d. Material from ditch cleaning operations shall not be blended into or bladed across aggregate surfaced roads nor bladed onto or across bituminous surfaced roads.

e. Material in excess of 2(d) or subject to 2(e) shall be disposed of at a designated waste area under Section 832. Excess materials temporarily stored on the ditch slope or edge of the shoulder shall be removed daily.

f. Limbs and wood chunks in excess of one (1) foot in length or three (3) inches in diameter shall be removed from ditches and placed outside the roadway.

g. Paved surfaces shall be cleaned of all materials resulting from Contractor's ditch maintenance work.

Paved surface cleaning shall be in accordance with Section 815.

h. Lead-off ditches shall be shaped to drain away from the traveled way.

3. VEGETATION

a. Brush and trees one (1) inch in diameter or smaller shall be removed as incidental to Item 831(1). Brush and trees larger than one (1) inch and less than six (6) inches in diamenter shall be removed and paid for under Item 831(3). Trees six (6) inches and larger in diameter shall be removed and paid for under Item 831(4).

b. Removed brush and trees shall be cut into lengths of four (4) feet or less and scattered on the fill slopes or outside the roadway limits. Concentrations of material will not be allowed. If ordered, materials shall be hauled and disposed of in accordance with Section 832.

a. Pay Items 831(1) and 831(3) will be measured to the nearest one-tenth (0.1) mile. Segments of less than one-tenth (0.1) mile will be counted as a full one-tenth (0.1) mile. Pay Item 831(2) will be measured by the number of ditches completed. Pay Item 831(4) will be measured by the number of units removed.

b. Ordered haul of excess material will be measured and paid under Section 832.

a. The accepted quantity will be paid for at the contract unit price shown in the Schedule of Items.

831(1) Clean and Reshape Drainage Ditch Ditch Mile 831(2) Clean and Reshape Lead off Ditch Each 831(3) Remove Vegetation Larger Than 1" Ditch Mile and Less Than 6" in Diameter 831(4) Remove Vegetation 6" and Larger Each in Diamenter

832 REMOVE AND END HAUL MATERIALS (2/99)

Work consists of ordered loading, hauling, and placing of slide, slough, or excess materials such as rock, soil, vegetation, and other materials to designated disposal sites.

a. Excess materials generated by work under other Sections of this contract may be ordered for removal, haul, and disposal under this Section. Removal and disposal under all Sections will be ordered without haul when a distance of less than one (1) mile is involved.

b. Slide and slough materials to be removed shall include those in the area extending approximately six (6) feet vertically above the road surface and that area extending not more than four (4) feet downslope from the roadbed. Material shall be disposed of at designated sites as Marked on the Ground.

The slope which generated the slide material shall be reshaped as nearly as practical to its original condition by equipment operating from road surface. Reshaping of roadside ditches in slide area shall be in accordance with Section 831.

c. When ordered by the Government, slumps shall be filled by compacting selected materials into roadway depressions. Compaction shall be by Method 2.

d. All materials removed and placed in disposal sites shall be placed by one or more of the following methods as shown in Road Listing.

1. Method 1 - Side Casting and End Dumping. Material may be placed by side casting and end dumping. Where materials include large rocks, a solid fill shall be provided by working smaller pieces and fines into voids. The finished surfaces shall be shaped to drain.

2. Method 2 - Layer Placement. Surfaces on which materials are to be placed shall be stepped or roughened prior to placing any material. Materials shall be placed in approximately horizontal layers no more than twelve (12) inches thick. Each layer shall be compacted by using one of the following methods:

Compaction Method A: By breaking track while operating equipment on the bladed surface.

Compaction shall cover the full width bladed surface. Compaction method A is incidental Placement method 2 and shall be used unless compaction method B is specified.

Compaction Method B: 8-10 ton steel or equivalent vibrating roller, operated to cover the full width of each layer two (2) times.

3. MEASUREMENT

a. Removal and disposal will be measured by the cubic yard, determined by equipment measure, for materials acceptably removed and placed.

b. Except as provided in 2(a) of this Section, haul of materials will be measured by the cubic yard mile, determined by the number of miles hauled times the cubic yards. Mileage will be measured one way rounded to the nearest 1/10 mile.

832(1) Removal and Disposal, Placement Method 1 Cubic Yard 832(2) Removal and Disposal, Placement Method 2 Cubic Yard 832(3) Haul Yard Mile 832(4) Compaction Method B Cubic Yard

833 CULVERT REPLACEMENT (11/07)

This work includes removal of existing culverts and appurtenances, bed preparation, and installation and backfill of new culverts and appurtenances of the size and length specified.

2. MATERIALS

Materials shall be furnished by the Contractor. All materials shall meet the requirements of Section 894

a. Excavation for culverts shall be at least as wide as three diameters of the existing pipe, and long enough to provide for proper joining of the culvert. The completed bottom shall be firm for its entire length and width.

The culvert shall be installed to maintain a uniform flow line from inlet to outlet, with a positive camber in the invert. See Drawing 833-1 for culvert installation details.

b. Pipe sections shall be joined firmly by form-fitting coupling bands. End sections shall be attached to pipe by connecting bands or other means recommended by the manufacturer. Gaskets shall be installed at each joint to form a watertight connection.

c. After the bedding is prepared and the pipe is placed, backfill material shall be placed in layers not exceeding six (6) inches loose thickness and compacted under the haunches and alongside the pipe. The material shall be readily compactible material free of frozen lumps, chunks of highly plastic clay or other objectionable material. Rocks larger than three (3) inches in greatest dimension shall not be used within one

(1) foot of the pipe.

d. Backfill density shall be that obtained by compacting each layer with mechanical equipment designed for this purpose. Compaction shall continue until visual displacement ceases.

e. Backfill shall continue for a minimum of twelve (12) inches above the top of the culvert. Compaction shall continue to finished grade.

f. Culverts with cover exceeding seven (7) feet from the bottom of the pipe to the top of the fill or at locations requiring dewatering shall not be replaced under this section.

g. Drop Inlets shall be frabricated and installed as SHOWN ON DRAWING 833-2.

h. Removed culverts and appurtenances become the property of the Contractor and shall be disposed of off of Government land. Disposal of removed culverts and appurtenances is considered incidental to the work in this specification.

Measurement will be made for each lineal foot of culvert specified and installed for culvert replacement and downpipe installation.

Measurement for hinged elbows, drop inlets, and drop inlet covers will be for each unit specified and installed.

Costs included are for materials, labor for fabrication and installation, and miscellaneous parts.

Measurement for anchor assemblies will be for each assembly specified and installed.

a. Accepted quantities will be paid for at the Contract unit prices shown in the Schedule of Items.

833(1) Culvert Replacement, 18 inches Diameter Linear Foot 833(2) Culvert Replacement, 24 inches Diameter Linear Foot 833(3) Culvert Replacement, 36 inches Diameter Linear Foot 833(4) Culvert Replacement, 48 inches Diameter Linear Foot 833(5) Downpipe, 18 inches Diameter Linear Foot 833(6) Downpipe, 24 inches Diameter Linear Foot 833(7) Downpipe, 36 inches Diameter Linear Foot 833(8) Downpipe, 48 inches Diameter Linear Foot 833(9) Hinged Elbow, 18 and 24 inches Diameter Each 833(10) Hinged Elbow, 36 and 48 inches Diameter Each 833(11) Drop Inlet, 36 inches Diameter Each 833(12) Drop Inlet Cover Each 833(13) Anchor Assembly, 18 inches Diameter Each 833(14) Anchor Assembly, 24 inches Diameter Each 833(15) Anchor Assembly, 36 inches Diameter Each 833(16) Anchor Assembly, 48 inches Diameter Each 833(17) 18 inch Polyethylene Pipe, Dual Wall Linear Foot 833(18) 24 inch Polyethylene Pipe, Dual Wall Linear Foot 833(19) 36 inch Polyethylene Pipe, Dual Wall Linear Foot 833(20) 48 inch Polyethylene Pipe, Dual Wall Linear Foot

834 DRAINAGE STRUCTURE MAINTENANCE (8/96)

This work consists of cleaning and reconditioning culverts and other drainage structures.

a. Drainage structures, inlet structures, culverts, catch basins, and inlet and outlet channels shall be cleaned when required by the Government. Catch basins shall be cleaned by removing the material within the area shown on Drawing 834-1.

b. The transition from the ditchline to the catch basin shall be cleaned a distance of ten (10) feet. Inlet channels shall be cleaned for a distance of ten (10) feet of debris that obstructs water flow or could move down and plug the culvert inlet. Outlet channels and lead-off ditches shall be cleaned a distance of six (6) feet. Debris and vegetation shall be removed and placed so as to not enter the channel or ditch or obstruct traffic. Debris and vegetation in quantities of ten (10) cubic yards or less is incidental. Quantities over ten

(10) cubic yards will be paid for under Section 832. Debris and vegetation ordered to be hauled shall be hauled to a designated disposal area in accordance with Section 832.

c. Hydraulic flushing of drainage structures is not allowed unless approved by the Government.

d. Cleaning and reconditioning is limited to the first four (4) feet of inlet and outlet determined along the top of the structure. Ordered reconditioning of culvert inlet or outlet shall be by field methods such as jacking out or cutting away damaged metal which obstructs flow. All cut edges and damage to galvanized coating shall be cleaned and treated with zinc rich coating. Damage or obstructions which are not field corrected under the requirements of this Section shall be reported to the Government.

e. Removal of brush and trees less than six (6) inches in diameter is incidental. The removal of brush and trees six (6) inches in diameter and larger shall be paid under Section 831. Brush and trees shall be disposed of by cutting into lengths of four (4) feet or less and scattered on fill slopes or outside the roadway limits.

a. Measurement will be the number of units of each culvert type including cleaning of inlet and outlet ditches or channels and catch basins completed and accepted.

b. Reconditioning and cleaning of drainage structures will be incidental to cleaning.

c. Ordered haul of materials will be measured under Section 832.

a. Quantities as determined above will be paid at the contract unit price.

834(1) Clean Culverts 24" Diameter and under Each 834(2) Clean Culverts Over 24" through 48" diameter Each 834(3) Clean Culverts Over 48" diameter Each

835 ROADWAY DRAINAGE MAINTENANCE (3/96)

1. DESCRIPTION

This work consists of providing drainage on roads that have been physically closed to traffic.

a. Access

1. The Government will provide for access through locked gates and also provide any special devices other than standard wrenches or tools, required for removal or replacement of fabricated barricades.

2. Other work associated with Contractor's access shall be the responsibility of the Contractor. The entrance shall not be left available for access to persons not associated with this contract; temporary barricades shall be used during the active performance of work.

b. Drainage

1. Upon completion of work, the roadway shall be shaped to provide for the removal of surface water, but need not be passable to vehicles. Waterbars, barriers or berms existing prior to the Contractor's operation shall be repaired or reinstalled. Areas where water is ponded by existing centerline profile sags in through cuts may be left untreated.

2. Continuous blade shaping of the roadbed is not required under this specification.

3. Work to be done at staked locations shall be as indicated on the stake.

4. Any of the following methods are acceptable for use at eroded or rutted locations.

a. Method A: Outsloping the roadbed at not less than one-half (1/2) inch per foot.

b. Method B: Insloping the roadbed at not less than one-half (1/2) inch per foot of width.

c. Method C: Water bar roadbed at locations staked on the ground. Construct in accordance with Drawings.

5. Drainage structures located in through fills and natural watercourses shall be fully functional without obstructions, including inlet and outlet channel within twenty (20) feet of the structure.

6. Culverts and other fabricated structures providing drainage from road ditches shall either be cleaned and the ditch made functional or waterbar(s) shall be provided across the roadbed. Fabricated drainage structures discharging on natural ground within three (3) feet of roadbed elevation may be removed at Government's option to provide the waterbar. Removed structures shall become Contractor's property to be removed from National Forest. Contractor-installed temporary drainage structures, if any, shall be removed and replaced with a water bar.

c. Slides, Slumps and Slough

1. Slides and slough may be left in place provided they do not potentially impound water or divert water from watercourses. Reshaping of the various surfaces shall be done as necessary to provide drainage.

2. Drainage shall be provided to effectively decrease or eliminate the entry of surface water into slides, slumps, and roadbed surface cracks. The Contractor shall place berms, waterbars, or ditches as needed to intercept and remove runoff water from the roadbed. Cracks shall be surface sealed by covering with native soil materials to prevent additional water entry and compacting with equipment tires.

d. Entrance Devices

Upon completion of work, entrance devices shall be replaced to effectively eliminate access by motorized vehicles having four (4) wheels and a width in excess of fifty (50) inches.

e. Seeding

All disturbed areas shall be seeded and fertilized in accordance with requirements set forth in Section 836 and are incidental.

3. MEASUREMENT

Measurement for the ordered and accepted work will be the length of the road in miles as shown on the Road

Listing.

835(1) Roadway Drainage Maintenance Miles

836 ROAD DECOMMISSIONING (3/99)

This work shall consist of closing designated roads to use by vehicles over 42 inches wide and returning the roadway to resource production using one or a combination of the following items as specified in a written order, listing, or shown on an attached map: removing drainage structures, seeding, fertilizing, scarification, ripping, outsloping roadbed, earth barricade, slashing, and camouflaging road junction.

a. Remove Drainage Structures

1. All designated drainage structures such as culverts, metal or wooden open top water diverters, and rubber water diverters shall be removed. Dips and waterbars shall not be removed.

2. Culverts 24 inches or less in diameter shall be smashed and buried (covered with a minimum of one foot of compacted native material) in the roadbed, unless disposal sites for specific culverts are designated on an attached map. If disposal sites have been designated the culverts shall be hauled to the designated site or other agreed to location.

3. Culverts over 24 inches in diameter shall be hauled to designated site shown on attached map or to other agreed to location.

4. Wooden open top water diverters, metal open top water diverters, and rubber water diverters shall be treated the same as culverts 24 inches or less in diameter.

5. Stream channel width after drainage structures have been removed shall be no less than that of existing channel in the vicinity of the inlet and outlet. Stream banks shall be sloped to 3:1 or flatter unless agreed to otherwise. This work is incidental to structure removal.

b. Seeding

1. This work consists of furnishing and placing required seed mix on all areas disturbed under this contract and on any other areas specified. Seeding may not be done until all other ground disturbing work on the road has been completed and accepted. Unless a specific seeding season is listed below, seeding shall be done as soon as other ground disturbing work is accepted.

Seeding season: to .

2. The seed shall be applied in the following amounts and mixtures:

Application Rate:

Species % of Mixture (lb./acre)

White Horse Feed Oats 100 120

3. Hand operated seeding devices, or other devices approved by the Government, shall be used to apply seed.

4. Seed shall meet the requirements of Federal Specification JJJ-S-181. Seed shall be furnished separately or in mixture in standard containers with (1) seed name; (2) lot number; (3) net weight; (4) percentages of purity and of germination (in case of legumes, percentage of germination to include hard seed); and (5) percentage of maximum weed seed content clearly marked for each kind of seed. The contractor shall furnish the Government duplicate signed copies of a statement by the vendor, certifying that each lot of seed has been tested by a recognized laboratory for seed testing withing 12 months of date of delivery. This statement shall include (1) name and address of laboratory, (2) date of test, (3) lot number for each kind of seed, and (4) results of tests as to name, percentages of purity and of germination, and percentage of weed content for each kind of seed furnished, and, in case of a mixture, the proportions of each kind of seed. Legume seed shall be inoculated with approved cultures in accordance with the instructions of the manufacturer.

c. Fertilizing

1. This work consists of furnishing and placing dry fertilizer on all areas disturbed under this contract and on any other areas specified. The contractor shall apply fertilizer as soon as all other ground disturbing work on the road has been completed and accepted, but not before seeding has been completed.

2. The minimum percentage of available nutrients shall be:

% Nitrogen % Phosphorus % Potassium % Sulfur 16 20 0 0

3. Fertilizer shall be applied at lbs/acre.

4. Hand operated fertilizing devices, or other devices approved by the Government, shall be used to apply the fertilizer.

d. Scarification

1. This work shall consist of seedbed preparation on an existing roadbed by scarification.

2. Scarification shall be accomplished by rippers spaced not more than 6 inches apart and/or with heavy duty gang discs.

3. Scarification depth shall not be less the 3 inches or deeper than 12 inches unless otherwise agreed.

e. Ripping

1. Shank Type Rippers

a. This work shall consist of ripping an existing roadbed with a shank type ripper.

b. The distance between the ripper shanks shall not exceed 36 inches. Rippers shall have a minimum of two shanks.

c. The minimum ripping depth shall be 20 inches. The Government may agree to a lesser depth when excessive rock is encountered.

d. Equipment shall not be operated on ripped areas.

2. Wing Rippers

a. This work shall consist of subsoiling an existing roadbed by ripping with a winged ripper.

b. The distance between ripper shanks shall not exceed 36 inches. Each shank shall be equipped with a shoe and wings which have a total width of at least 18 inches.

The design of the shank and wing will be such that the treated soils are slightly lifted and well fractured rather than plowed, mixed or displaced.

c. Ripping shall be accomplished to a minimum depth of 20 inches. The Government may agree to a lesser depth when excessive rock is encountered.

d. Equipment shall not be operated on ripped areas.

f. Outsloping Roadbed

1. Designated roads or segments of roads shall be outsloped by pulling the fill shoulder towards the cut bank. Excavated material shall be spread over the roadbed forming a minimum outslope equal to the existing road grade percent. The Government may agree to a lesser outslope percent if soil conditions warrant.

2. Any existing ditches at the toe of the cut shall be filled with the material excavated during outsloping.

g. Earth Barricade

1. Earth barricades shall be constructed in locations specified in accordance with the attached drawing 836-6.

2. Multiple barricades at one site may be specified.

h. Slashing

1. This work shall consist of placing woody material over the roadbed to discourage vehicle traffic.

2. Woody material shall be dead timber and slash removed from an area within twenty five (25) feet of the road shoulders in the vicinity of the areas where it is to be placed.

3. Material shall be placed randomly over the roadbed to give a similar appearance of the surrounding area and may include rocks…