Duff_Creek_Schedule_of_Items.xls

XLS spreadsheet 34 KB Posted

Attached to
Duff Creek Aquatic Organism Passage Federal contract opportunity
Solicitation number
AG-9A40-S-16-0004
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

Revised Schedule of Items

View the file

Other files for this federal contract opportunity

Other files attached to Duff Creek Aquatic Organism Passage, newest first.
File Type Posted
Construction_Drawings_Rev_04_21.pdf PDF
Habitat_Boulder_Specifications.pdf PDF
Duff_Creek_Schedule_of_Items.xls XLS spreadsheet
SF_30.pdf PDF
RFI_Bates_Construction.pdf PDF
Specifications_REV_04_21.pdf PDF
SF-30_Amendment_No._3.pdf PDF
RFI_Bates_Construction.pdf PDF
Habitat_Boulder_Specifications.pdf PDF
SF-30_Amendment_No.2.pdf PDF
RFI_March_21.pdf PDF
Drawings_REV_2.pdf PDF
Duff_Creek_Schedule_of_Items.xls XLS spreadsheet
Drawings_REV_1.pdf PDF
PART_IV.pdf PDF
Pre-bid_Attendance_Sheet.pdf PDF
SF_30.pdf PDF
EROSION_CONTROL_PLAN.pdf PDF
Pre-bid_Notes.pdf PDF
SOW.pdf PDF
Specifications.pdf PDF
Duff_Creek_Schedule_of_Items.xls XLS spreadsheet
SF_24_Bid_Bond.pdf PDF
Fire_Plan_2013.pdf PDF
Wage_Provision_.pdf PDF
Construction_Drawings.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EngEst

SCHEDULE OF ITEMS
DUFF CREEK AOP SITE 1 CULVERT REPLACEMENT
HIGH SIERRA RANGER DISTRICT
SIERRA NATIONAL FOREST
FRESNO COUNTY
PROJECT: Duff Creek AOP Site 1 Culvert Replacement
Pay Item No.Item DescriptionEst QuanUnitUnit PriceAmount
Base Work Items:
152(05)Culvert Staking1LS$_______$___________
154(01)Contractor Sampling And Testing Compaction and Concrete1LS$_______$___________
157(13)Soil Erosion and Pollution Control Plan and Implementation1LS$_______$___________
201(02)Clearing and grubbing1LS$_______$___________
203(05)Removal of Structures and Obstructions1LS$_______$___________
204(71)Embankment Construction, Compaction Method D, Finishing Method B (includes excavation for new profile grade.)1LS$_______$___________
208(01)Structural Excavation133CY$_______$___________
208(03)Structural Backfill112CY$_______$___________
251(01)Placed Riprap, Class 4, method A8CY$_______$___________
251(10)Hand Placed Riprap, Class 24CY$_______$___________
301(01)Aggregate Base, Grading C, Compaction D150Ton$_______$___________
403(01)Hot asphalt concrete pavement class C, grading B100Ton$_______$___________
553(05)Precast 12' Span, 6' Rise concrete box culvert1LS$_______$___________
648(02)Placed Bank Armoring Rock, Rock - 2, (24" Dia.), Method A56EA$_______$___________
TOTAL$___________
SCHEDULE OF ITEMS
DUFF CREEK AOP SITE 2 CULVERT REPLACEMENT
HIGH SIERRA RANGER DISTRICT
SIERRA NATIONAL FOREST
FRESNO COUNTY
PROJECT: Duff Creek AOP Site 2 Culvert Replacement
Pay Item No.Item DescriptionEst QuanUnitUnit PriceAmount
Base Work Items:
151(01)Mobilization (includes bonding cost) Both sites1LS$_______$___________
152(05)Culvert Staking1LS$_______$___________
154(01)Contractor Sampling And Testing Compaction and Concrete1LS$_______$___________
157(13)Soil Erosion and Pollution Control Plan and Implementation1LS$_______$___________
201(02)Clearing and Grubbing1LS$_______$___________
203(05)Removal of Structures and Obstructions1LS$_______$___________
204(18)Drainage Excavation, Type Minor Channel change320CY$_______$___________
204(71)Embankment Construction, compaction Method D, finishing Method B, (Includes excavation for new profile grade)1LS$_______$___________
208(01)Structural Excavation605CY$_______$___________
208(03)Structural Backfill400CY$_______$___________
251(02)Placed Riprap, Class 4, method A100CY$_______$___________
251(16)Geotextile, Type IV-C170SY$_______$___________
301(01)Aggregate Base, grading C, Compaction D150Ton$_______$___________
403(01)Hot asphalt concrete pavement class C, grading B100Ton$_______$___________
552(01)Structural Concrete Class A (AE) includes forms, falsework and reinforcing steel65CY$_______$___________
554(01)Reinforcing Steel8800LB$_______$___________
603(02)20' Span, 10' Rise, Structural Plate Pipe Arch, 10 gauge Thick72LF$_______$___________
634(01)Pavement Markings Type A1LS$_______$___________
635(01)Temporary Traffic Control1LS$_______$___________
648(02)APlaced Channel Rock, Rock 3 (36" Dia.), method A112EA$_______$___________
648(04)Placed Streambed simulation rock, bed class 8, method A288CY$_______$___________
TOTAL$___________
Optional Item
202(01)Additional Clearing and Grubbing (Tree Removal)4EA$_______$___________

&R&12Solicitation No. AG-9S40-S-16-0004 Duff Creek Aquatic Organism Passage Amendment No. One

File details come from the government source that posted it. Updated .