Section I Contract Clauses

View the file

Other files

File Type Posted
Amendment__1.pdf PDF
Hume_Lake_Drawdown-2010.pdf PDF
Revised_Drawing_Sheet_C1.1.pdf PDF
SF_30.pdf PDF
FAR_52.232-5_Payment_Under_Fixed-Price_Construction_Contracts.pdf PDF
Permits_and_Sediment_Discharge.pdf PDF
Revised_Drawing_Sheet_C1.7.pdf PDF
RFI_Vertech.pdf PDF
Sch_Items_Revised.xlsx XLSX spreadsheet
misc_photos_1984_and_prior.pdf PDF
Revisions_to_Specifications.pdf PDF
Hume_Lake_geo-tech_dam_report.pdf PDF
Nov_18_2010_Drained_Hume_Lake_Photos.pdf PDF
RFI_Carpi.pdf PDF
RFI_Crenshaw_2.pdf PDF
Sch_Items_Revised.pdf PDF
Business_cards.pdf PDF
Existing_Outlet_Valves_Control_Schematics.pdf PDF
SF-30_Amendment_No._1.pdf PDF
PreBidMtgNotes_3-25-2015.pdf PDF
Attendance_Sheet.pdf PDF
RFI_Questions_2015.03.15.pdf PDF
1984FinalConstructionReport.PDF PDF
Remote_Monitoring_System_Data.pdf PDF
Solicitation.pdf PDF
Project_Specifications.pdf PDF
Fire_Plan.pdf PDF
Sch_Items.xlsx XLSX spreadsheet
Wage_Determination_CA29.pdf PDF
Drawings.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-9A40-S-15-0008

Hume Lake Dam Rehabilitation

Amendment #2

PART 1 – THE SCHEDULE

SECTION I - CONTRACT CLAUSES

I.1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-02) (Feb 98)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address:

http:\\www.acquisition.gov

52.202-01 - Definitions (Nov 2013) 52.203-03 - Gratuities (Apr 84) 52.203-05 - Covenant Against Contingent Fees (May 2014) 52.203-06 - Restrictions on Subcontractor Sales to the Government (Sept 06) 52.203-07 - Anti-Kickback Procedures (May 2014) 52.203-08 - Cancellation, Rescission, and Recovery of Funds for Illegal or Improper

Activity (May 2014) 52.203-10 - Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.204-04 - Printed or Copied Double-Sided on Post Consumed Fiber Content Paper

(May 2011) 52.204-07 - System for Award Management (Jul 2013) 52.209-06 - Protecting the Government's Interest When Subcontracting With

Contractors Debarred, Suspended, or Proposed For Debarment (Aug 2013) 52.211-18 - Variation in Estimated Quantity (Apr 1984) 52.219-08 - Utilization of Small Business Concerns (Oct 2014 52.222-03 - Convict Labor (June 03) 52.222-04 - Contract Work Hours And Safety Standards--Overtime Compensation (May

2013) 52.222-06 – Construction Wage Rate Requirements (May 2014) 52.222-07 - Withholding of Funds (May 2014) 52.222-08 - Payrolls and Basic Records (May 2014) 52.222-09 - Apprentices and Trainees (July 05) 52.222-10 - Compliance with Copeland Act Requirements (Feb 88) 52.222-11 - Subcontracts (Labor Standards) (May 2014) 52.222-12 - Contract Termination - Debarment (May 2014) 52.222-13 - Compliance with Construction Wage Requirements and Related

Regulations (May 2014) 52.222-14 - Disputes Concerning Labor Standards (Feb 88) 52.222-15 - Certification of Eligibility (May 2014) 52.222-26 - Equal Opportunity (Mar 07) 52.222-27 - Affirmative Action Compliance Requirements for Construction (Feb 99)

52.222-35 - Equal Opportunity for Veterans, (July 2014) 52.222-36 - Affirmative Action for Workers with Disabilities, (July 2014) 52.222-37 - Employment Reports on Veterans , (July 2014) 52.222-55 - Minimum Wages Under Executive Order 13658 (Dec 2014) 52.223-02 - Affirmative Procurement of Biobased Products Under Service and

Construction Contracts (Sept 2013) 52.223-05 - Pollution Prevention and Right-to-Know Information (May 2011) 52.223-06 - Drug-Free Workplace (May 01) 52.227-01 - Authorization and Consent (Dec 07) 52.227-02 - Notice and Assistance Regarding Patent and Copyright Infringement (Dec 07) 52.227-04 - Patent Indemnity -- Construction Contracts (Dec 07) 52.228-12 - Prospective Subcontractor Requests For Bonds (May 2014) 52.228-13 - Alternative Payment Protections (July 2000) 52.228-14 - Irrevocable Letter Of Credit (Nov 2014) 52.229-03 - Federal, State, and Local Taxes (Feb 2013) 52.232-05 - Payments Under Fixed-Price Construction Contracts (May 2011) 52.232-17 - Interest (May 2014) 52.232-23 - Assignment Of Claims (May 2014) 52-232-27 - Prompt Payment for Construction Contracts (May 2014) 52.232-34 - Payment by Electronic Funds Transfer - Other than System for Award

Management (July 2013) 52.233-01 - Disputes (May 2014) 52.233-02 - Service of Protest (Sept 06) 52.233-03 - Protest After Award (Aug 96) 52.236-07.- Permits and Responsibilities (Nov 1991) 52-236-26 - Preconstruction Conference (Feb 95) 52-242-13 - Bankruptcy (Jul 95) 52.242-14 - Suspension of Work (Apr 1984) 52.243-04 - Changes (June 2007) 52.245-01 - Government Property. Alt 1(Apr 2012) 52.245-09 - Use and Charges (Apr 2012) 52.246-21 - Warranty Of Construction (Mar 1994) 52.249-01 - Termination for Convenience of the Government (Fixed-Price) (Short Form)

(Apr 84) 52.249-02 - Termination for Convenience of the Government (Fixed-Price) (Apr 2012) 52.249-10 - Default (Fixed-Price Construction) (Apr 84) 52.253-01 - Computer Generated Forms (Jan 91)

I.2 AUDIT AND RECORDS – NEGOTIATION (FAR 52.215-2) (Oct 2010)

(a) As used in this clause, “records” includes books, documents, accounting procedures and practices, and other data, regardless of type and regardless of whether such items are in written form, in the form of computer data, or in any other form.

(b) Examination of costs. If this is a cost-reimbursement, incentive, time-and-materials, labor-hour, or price redeterminable contract, or any combination of these, the Contractor shall maintain and the Contracting Officer, or an authorized representative of the Contracting Officer, shall have the right to examine and audit all records and other evidence sufficient to reflect properly all costs claimed to have been incurred or anticipated to be incurred directly or indirectly in performance of this contract. This right of examination shall include inspection at all reasonable times of the Contractor’s plants, or parts of them, engaged in performing the contract.

(c) Cost or pricing data. If the Contractor has been required to submit cost or pricing data in connection with any pricing action relating to this contract, the Contracting Officer, or an authorized representative of the Contracting Officer, in order to evaluate the accuracy, completeness, and currency of the cost or pricing data, shall have the right to examine and audit all of the Contractor’s records, including computations and projections, related to—

(1) The proposal for the contract, subcontract, or modification;

(2) The discussions conducted on the proposal(s), including those related to negotiating;

(3) Pricing of the contract, subcontract, or modification; or

(4) Performance of the contract, subcontract or modification.

(d) Comptroller General.—

(1) The Comptroller General of the United States, or an authorized representative, shall have access to and the right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract or a subcontract hereunder and to interview any current employee regarding such transactions.

(2) This paragraph may not be construed to require the Contractor or subcontractor to create or maintain any record that the Contractor or subcontractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(e) Reports. If the Contractor is required to furnish cost, funding, or performance reports, the Contracting Officer or an authorized representative of the Contracting Officer shall have the right to examine and audit the supporting records and materials, for the purpose of evaluating—

(1) The effectiveness of the Contractor’s policies and procedures to produce data compatible with the objectives of these reports; and

(2) The data reported.

(f) Availability. The Contractor shall make available at its office at all reasonable times the records, materials, and other evidence described in paragraphs (a), (b), (c), (d), and

(e) of this clause, for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in Subpart 4.7, https://www.acquisition.gov/far/current/html/Subpart%204_7.html%23wp1082800

Contractor Records Retention, of the Federal Acquisition Regulation (FAR), or for any longer period required by statute or by other clauses of this contract. In addition—

(1) If this contract is completely or partially terminated, the Contractor shall make available the records relating to the work terminated until 3 years after any resulting final termination settlement; and

(2) The Contractor shall make available records relating to appeals under the Disputes clause or to litigation or the settlement of claims arising under or relating to this contract until such appeals, litigation, or claims are finally resolved.

(g) The Contractor shall insert a clause containing all the terms of this clause, including this paragraph (g), in all subcontracts under this contract that exceed the simplified acquisition threshold, and—

(1) That are cost-reimbursement, incentive, time-and-materials, labor-hour, or price-redeterminable type or any combination of these;

(2) For which cost or pricing data are required; or

(3) That require the subcontractor to furnish reports as discussed in paragraph (e) of this clause. The clause may be altered only as necessary to identify properly the contracting parties and the Contracting Officer under the Government prime contract.

(End of clause)

I.3 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (FAR 52.225-9) (May 2014)

a) Definitions. As used in this clause—

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph

(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

None

[Contracting Officer to list applicable excepted materials or indicate “none”]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description

Unit of Measure Quantity Price (Dollars)*

Item 1:

Foreign construction material

Domestic construction _______ _______ _______ material

Item 2: _______ _______ _______ Foreign construction material

Domestic construction material

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

I.4 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS

(FAR 52.225-10)(May 2014)

Notice of Buy American Requirement—Construction Materials (May 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American— Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

https://acquisition.gov/far/current/html/52_223_226.html%23wp1169273 https://acquisition.gov/far/current/html/52_223_226.html%23wp1169273

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding;

or

(ii) May be accepted if revised during negotiations.

(End of provision)

I.5 ADDITIONAL BOND SECURITY (FAR 52.228-02) (Oct 97)

The Contractor shall promptly furnish additional security required to protect the Government and persons supplying labor or materials under this contract if ---

(a) Any surety upon any bond or issuing financial institution for other security, furnished with this contract becomes unacceptable to the Government;

(b) Any surety fails to furnish reports on its financial condition as required by the Government;

(c) The contract price is increased so that the penal sum of any bond becomes inadequate in the opinion of the Contracting Officer; or

(d) An irrevocable letter of credit (ILC) used, as security will expire before the end of the period of required security. If the Contractor does not furnish an acceptable extension or replacement ILC, or other acceptable substitute, at least 30 days before an ILC's scheduled expiration, the Contracting officer has the right to immediately draw on the

ILC.

https://acquisition.gov/far/current/html/FormsStandard61.html%23wp1177057 https://acquisition.gov/far/current/html/FormsStandard61.html%23wp1177057

I.6 PLEDGES OF ASSETS (JAN 2012)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee, a performance bond, or a payment bond—

(1) Pledge of assets; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) Pledges of assets from each person acting as an individual surety shall be in the form of—

(1) Evidence of an escrow account containing cash, certificates of deposit, commercial or Government securities, or other assets described in FAR 28.203-2 (except see 28.203-2(b)(2) with respect to Government securities held in book entry form); and/or

(2) A recorded lien on real estate. The offeror will be required to provide—

(i) A mortgagee title insurance policy, in an insurance amount equal to the amount of the lien, or other evidence of title that is consistent with the requirements of Section 2 of the United States Department of Justice Title Standards at http://www.justice.gov/enrd/ENRD_Assets/Title_Standards_2001.pdf. This title evidence must show fee simple title vested in the surety along with any concurrent owners;

whether any real estate taxes are due and payable; and any recorded encumbrances against the property, including the lien filed in favor of the Government as required by FAR 28.203-3(d);

(ii) Evidence of the amount due under any encumbrance shown in the evidence of title;

(iii) A copy of the current real estate tax assessment of the property or a current appraisal dated no earlier than 6 months prior to the date of the bond, prepared by a professional appraiser who certifies that the appraisal has been conducted in accordance with the generally accepted appraisal standards as reflected in the Uniform Standards of Professional Appraisal Practice, as promulgated by the Appraisal Foundation.

(End of clause)

I.7 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (FAR 52.228-15)

(Oct 2010)

(a) Definitions. As used in this clause—

“Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting https://acquisition.gov/far/current/html/FormsStandard7.html%23wp1189346 https://acquisition.gov/far/current/html/Subpart%2028_2.html%23wp1073352 https://acquisition.gov/far/current/html/Subpart%2028_2.html%23wp1073352 http://www.justice.gov/enrd/ENRD_Assets/Title_Standards_2001.pdf https://acquisition.gov/far/current/html/Subpart%2028_2.html%23wp1073377

Officer as follows:

(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(3) Additional bond protection.

(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.

(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.

(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.

(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:

U.S. Department of the Treasury Financial Management Service Surety Bond Branch 3700 East West Highway, Room 6F01 Hyattsville, MD 20782.

Or via the internet at http://www.fms.treas.gov/c570/.

(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.

I. 8 BID GUARANTEE (FAR 52.228-1) (SEPT. 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of 100the United States.

The Contracting Officer will return bid guarantees, other than bid bonds-

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I. 9 REIMBURSEMENT FOR BOND PREMIUMS--FIXED-PRICE CONSTRUCTION

CONTRACTS (AGAR 452.232-70) (Nov 1996)

The Contract Price includes the total amount for premiums that the Contractor attributes to the furnishing of performance and payment bonds required by the contract.

Reimbursement for bond premiums under the clause at FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not cover any amount therefore not included in the contract price.

I.10 AGAR 452.209-71 ASSURANCE REGARDING FELONY CONVICTION OR TAX

DELINQUENT STATUS FOR CORPORATE APPLICANTS Alternate 1 (Feb 2012).

(a) This award is subject to the provisions contained in the Consolidated Appropriations Act, 2012 (P.L. No. 112-74), Division E, Sections 433 and 434 regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –

(1) does not have a tax delinquency, meaning that it is not subject to any unpaid

Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and

(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.

(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434.

(End of Clause)