RFI_Crenshaw_2.pdf

PDF 16 KB Posted

Attached to
Hume Lake Dam Rehabilitation
Solicitation number
AG-9A40-S-15-0008
Issued by

About this file

Answers to RFI Crenshaw

View the file

Other files

File Type Posted
Amendment__1.pdf PDF
Hume_Lake_Drawdown-2010.pdf PDF
Revised_Drawing_Sheet_C1.1.pdf PDF
SF_30.pdf PDF
FAR_52.232-5_Payment_Under_Fixed-Price_Construction_Contracts.pdf PDF
Permits_and_Sediment_Discharge.pdf PDF
Revised_Drawing_Sheet_C1.7.pdf PDF
RFI_Vertech.pdf PDF
Sch_Items_Revised.xlsx XLSX spreadsheet
misc_photos_1984_and_prior.pdf PDF
Revisions_to_Specifications.pdf PDF
Hume_Lake_geo-tech_dam_report.pdf PDF
Nov_18_2010_Drained_Hume_Lake_Photos.pdf PDF
RFI_Carpi.pdf PDF
Section_I_Contract_Clauses.pdf PDF
Sch_Items_Revised.pdf PDF
Business_cards.pdf PDF
Existing_Outlet_Valves_Control_Schematics.pdf PDF
SF-30_Amendment_No._1.pdf PDF
PreBidMtgNotes_3-25-2015.pdf PDF
Attendance_Sheet.pdf PDF
RFI_Questions_2015.03.15.pdf PDF
1984FinalConstructionReport.PDF PDF
Remote_Monitoring_System_Data.pdf PDF
Solicitation.pdf PDF
Project_Specifications.pdf PDF
Fire_Plan.pdf PDF
Sch_Items.xlsx XLSX spreadsheet
Wage_Determination_CA29.pdf PDF
Drawings.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI Crenshaw

1. Schedule of Values, Option 1 – Foundation Grouting – 4 Licensed Grouting Engineer (Minimum 10 years experience) (in reference to the response to previous question): It is understood that the role of the Licensed Grouting Engineer will be to ensure that adequate oversite is provided for the grouting program and to perform technical consultation as required. This being the case, and considering that the professional will be offering oversite and not design services (ie, not required to stamp grouting plans), along with the circumstance that there are few individuals (outside the employ of grouting contractors) which are licensed and have ten years experience performing similar work, would either of the following be allowed to fulfill this role:

• An Engineer or Geologist who is licensed in a state other than California, but who has ten or more years experience performing grouting. Answer: A PE from any state is sufficient.

• Or, a consultant, who is not licensed, but who has ten or more years experience performing grouting. Answer: NO

2. Specification Section 4A.4.6 Microfine Cement and FAR 52.225-9 (Buy American

Act – Construction Materials): This question is a notification under the above referenced FAR clause that no domestically produced material meets the requirements of Specification Section 4A.4.6 (based on information from the major microfine suppliers and several grouting consultants). We would therefore request a variance to either 1) allow the use of non-domestically produced microfine which meets the project specifications or 2) to allow the use of domestically produced microfine which does not meet the project specifications.

Answer: Read Amendment 2, Buy American Act—Construction Materials (FAR 52.225-9)(May 2014) and provide additional information for the Contracting Officer’s determination.

3. Can a list of attendees for the pre-bid meeting be provided? Answer: See Amendment 1