Hume Lake Dam Drawdown 2010 photos

View the file

Other files

File Type Posted
Amendment__1.pdf PDF
Revised_Drawing_Sheet_C1.1.pdf PDF
SF_30.pdf PDF
FAR_52.232-5_Payment_Under_Fixed-Price_Construction_Contracts.pdf PDF
Permits_and_Sediment_Discharge.pdf PDF
Revised_Drawing_Sheet_C1.7.pdf PDF
RFI_Vertech.pdf PDF
Sch_Items_Revised.xlsx XLSX spreadsheet
misc_photos_1984_and_prior.pdf PDF
Revisions_to_Specifications.pdf PDF
Hume_Lake_geo-tech_dam_report.pdf PDF
Nov_18_2010_Drained_Hume_Lake_Photos.pdf PDF
RFI_Carpi.pdf PDF
RFI_Crenshaw_2.pdf PDF
Section_I_Contract_Clauses.pdf PDF
Sch_Items_Revised.pdf PDF
Business_cards.pdf PDF
Existing_Outlet_Valves_Control_Schematics.pdf PDF
SF-30_Amendment_No._1.pdf PDF
PreBidMtgNotes_3-25-2015.pdf PDF
Attendance_Sheet.pdf PDF
RFI_Questions_2015.03.15.pdf PDF
1984FinalConstructionReport.PDF PDF
Remote_Monitoring_System_Data.pdf PDF
Solicitation.pdf PDF
Project_Specifications.pdf PDF
Fire_Plan.pdf PDF
Sch_Items.xlsx XLSX spreadsheet
Wage_Determination_CA29.pdf PDF
Drawings.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Nov 2010 – Overview of Hume Lake drained down to the top of the outlet works.

Nov 2010 – Remaining pool around outlet work in front of bay 6.

Nov 2010 – Drained Hume Lake looking upstream.

Nov 2010 – Drained Hume Lake looking toward the dam.

11-14-2010 ARRA – Hume Dam Valve Replacement – concrete pour – 1 cy concrete bucket lowered by truck crane down to control valves concrete support slab.

11-14-2010 ARRA – Hume Dam Valve Replacement – crane truck set-up with cable lowered over the dam down to existing 36” control ball valve.

11-14-2010 ARRA – Hume Dam Valve Replacement – 150 ton crane truck setting up installing counter weights 130 tons.

11-14-2010 ARRA – Hume Dam Valve Replacement – 150 ton crane truck backing into place on prepared pad covered with plastic sheeting.

11-14-2010 ARRA – Hume Dam Valve Replacement – 150 ton crane truck backing down prepared access road into lake bottom.

11-8-2010 ARRA – Hume Dam Valve Replacement – prepared pad for crane truck.

11-15-2010 – Hume Dam Valve Replacement – Crane truck set up for valve replacement;

upstream dam face and lakebed in the background.