Text version
EngEst
| PART I THE SCHEDULE |
| SECTION B - SERVICE AND SUPPLIES |
| SEQUOIA NATIONAL FOREST |
| Hume Lake Dam Rehabilitation | ||||||
| ITEM NO. | DESCRIPTION | MM | ESTIMATED QUANTITY | PAY UNIT | UNIT PRICE | AMOUNT |
| Base Bid Items: | ||||||
| 1 | Mobilization/Demobilization (includes bonding costs) | L.S.Q. | 1 | L.S. | $0.00 | |
| 2 | Geomembrane system (100 mil PVC liner) with Geocomposite geonet drainage layer and drain system (Includes all associated costs.) | A.Q. | 21,000 | S.F. | $0.00 | |
| 3 | Outlet works integrity investigation | L.S.Q. | 1 | L.S. | $0.00 |
Sub-Total Base Bid: $0.00
| Option 1 - Foundation Grouting: | |||||
| 4 | Mobilization/Demobilization for Grouting | L.S.Q. | 1 | L.S. | $0.00 |
| 5 | Licensed Grouting Engineer (Minimum 10 years experience) | A.Q. | 50 | HR | $0.00 |
| 6A | Drill grout hole for Bays 4 and 5 (includes pressure test and washing) | A.Q. | 300 | L.F. | $0.00 |
| 6B | Drill grout hole for Bays 1, 2, and 3 (includes pressure test and washing) | A.Q. | 450 | L.F. | $0.00 |
| 7A | Portland Cement for Bays 4 and 5 (Sand, microfine, fly ash, and additives are incidental.) | A.Q. | 700 | Bag | $0.00 |
| 7B | Portland Cement for Bays 1, 2, and 3 (Sand, microfine, fly ash, and additives are incidental.) | A.Q. | 700 | Bag | $0.00 |
| 8A | Grout production, processing, and placement for Bays 4 and 5 | A.Q. | 100 | Pump Hours | $0.00 |
| 8B | Grout production, processing, and placement for Bays 1, 2, and 3 | A.Q. | 100 | Pump Hours | $0.00 |
Sub-Total Option 1: $0.00
| Option 2 - Outlet Works Rehabilitation: | |||||
| 9 | Outlet works Intake structure fabrication (includes transportation) | L.S.Q | 1 | L.S. | $0.00 |
| 10 | Outlet works Intake structure installation (Includes removal of existing intake structure. Combine crane costs with item 9 if possible.) | L.S.Q | 1 | L.S. | $0.00 |
| 11 | Rehabilitation in Place of outlet works outfall conduit using one of the following methods based on results of integrity inspection | $0.00 | |||
| 11A | Cured in Place Pipe (CIPP) | A.Q. | 70 | L.F. | $0.00 |
| 11B | Interior resurfacing, corrosion protection, or coating | A.Q. | 600 | S.F. | $0.00 |
| 11C | Bituminious Coating | L.S.Q | 1 | L.S. | $0.00 |
Sub-Total Option 2: $0.00
| Option 3 - Scour Protection in Bay 4: | |||||
| 12 | Bay 4 scour protection (Includes leveling rock, anchors, hardware, geomembrane, articulated concrete block matt, crane and operator for 5 days) | A.Q. | 100 | S.Y. | $0.00 |
Sub-Total Option 3: $0.00
| Option 4 - Supervisory Control And Data Acquisition (SCADA) System: | |||||
| 13A | Furnish and Install remote valve controls at valves; solar array, battery bank, control panel, and accessories at generator building. Size solar array and battery bank to power monitoring system only (not valve actuators). | L.S.Q. | 1 | L.S. | $0.00 |
| 13B | Furnish and Install additional solar generation and power storage capability at generator building to operate valve actuators without activating generator. | L.S.Q. | 1 | L.S. | $0.00 |
| 14 | Install remote sensing system, including pressure transducer, control cable, and control panel. (Equipment is government furnished.) | L.S.Q. | 1 | L.S. | $0.00 |
| 15A | Furnish and Install webcam at trail bridge. Power supply and controls to be selected from item B or C below. | L.S.Q. | 1 | L.S. | $0.00 |
| 15B | Furnish and Install solar panel, battery, and wireless controls/data transfer for webcam. | L.S.Q. | 1 | L.S. | $0.00 |
| 15C | Furnish and Install conduit and conductors for power supply and data transfer from SCADA control panel in generator building to webcam. | A.Q. | 550 | L.F. | $0.00 |
| 16 | Furnish and Install conduit and conductors for power supply and data transfer from SCADA control panel in generator building to valve controls at outlet works. | A.Q. | 475 | L.F. | $0.00 |
Sub-Total Option 4: $0.00
| Option 5 Generator Building Replacement: | |||||
| 17 | Furnish and install prefabricated concrete generator building and new fenced enclosure (includes demolition and removal of existing building and chain link fencing) | L.S.Q | 1 | L.S. | $0.00 |
Sub-Total Option 5: $0.00
| TOTAL BID: | $0.00 | |
| Note: Work includes all transportation, installation, or placement costs. Items not listed shall be considered incidental. |
Solicitation No. AG-9A40-S-15-0008