RFI_Questions_2015.03.15.pdf

PDF 49 KB Posted

Attached to
Hume Lake Dam Rehabilitation
Solicitation number
AG-9A40-S-15-0008
Issued by

About this file

RFI Questions and Answers

View the file

Other files

File Type Posted
Amendment__1.pdf PDF
Hume_Lake_Drawdown-2010.pdf PDF
Revised_Drawing_Sheet_C1.1.pdf PDF
SF_30.pdf PDF
FAR_52.232-5_Payment_Under_Fixed-Price_Construction_Contracts.pdf PDF
Permits_and_Sediment_Discharge.pdf PDF
Revised_Drawing_Sheet_C1.7.pdf PDF
RFI_Vertech.pdf PDF
Sch_Items_Revised.xlsx XLSX spreadsheet
misc_photos_1984_and_prior.pdf PDF
Revisions_to_Specifications.pdf PDF
Hume_Lake_geo-tech_dam_report.pdf PDF
Nov_18_2010_Drained_Hume_Lake_Photos.pdf PDF
RFI_Carpi.pdf PDF
RFI_Crenshaw_2.pdf PDF
Section_I_Contract_Clauses.pdf PDF
Sch_Items_Revised.pdf PDF
Business_cards.pdf PDF
Existing_Outlet_Valves_Control_Schematics.pdf PDF
SF-30_Amendment_No._1.pdf PDF
PreBidMtgNotes_3-25-2015.pdf PDF
Attendance_Sheet.pdf PDF
1984FinalConstructionReport.PDF PDF
Remote_Monitoring_System_Data.pdf PDF
Solicitation.pdf PDF
Project_Specifications.pdf PDF
Fire_Plan.pdf PDF
Sch_Items.xlsx XLSX spreadsheet
Wage_Determination_CA29.pdf PDF
Drawings.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hume Lake Dam Rehabilitation Questions March 15, 2015

Shedule of Values, Option 1 – Foundation Grouting – 4 Licensed Grouting Engineer (Minimum 10 years experience) – We cannot locate a measurement and payment definition for this pay item. Will the hourly rate be paid for all time the Engineer spends on site? Should the Contractor expect that required hours will be uninterrupted or will multiple trips be required by the Engineer? If multiple trips will be required, can a pay item be added to cover the Engineer’s mobilization/demobilization?

The intent of the Grouting Engineer pay item is to ensure that adequate expertise is available to oversee completion of Foundation Grouting. The Grouting Engineer should be on site initially to make sure the work is correctly laid out, operations are set up, and running smoothly. Thereafter, he doesn’t need to be on site, but should be available by telephone in case technical consultation is needed. He will be paid for hours on site, and should plan an allowance of two trips.

Shedule of Values, Option 1 – Foundation Grouting – 7A and 7B Portland Cement … – The schedule of values states that Microfine Cement will be incidental to these pay items. We assume that microfine would be used in lieu of standard Portland cement (as mixing the two materials would negate any advantage in reduced particle size of the microfine). Two questions:

• How will the use of microfine versus Portland cement be determined? Will the Contracting Officer direct the use of microfine cement or will the decision to use microfine be left to the Contractor?

The use of microfine cement will be determined by the Contractor based on site conditions to achieve a thorough foundation grouting program that will durable and long lasting. The use of microfine cement will be approved by the Contracting Officer, through approval of the Grout Mix design and changes (see Table 3-1 Documentation Submittal schedule).

• If the use of microfine will be directed, can separate pay items for microfine be provided? This is requested because the cost of microfine cement per pound is approximately 5-6 times the cost of Portland cement per pound. Therefore, under the current pay items, the Contractor would have to make some determination of the amount of Portland cement used versus microfine cement used as the basis of pricing. Based on actual quantities used, this could result in either 1) the Government paying an extremely high price for Portland cement or 2) the Contractor not being fully reimbursed for the use of microfine cement.

Microfine cement is currently incidental to Portland cement. If a change in pay items is made, it will be published in a solicitation amendment after the pre-bid tour scheduled for March 24.