Attachment_1_01301_Mobilization.pdf

PDF 54 KB Posted

Attached to
Lake Isabella Boarding Floats Replacement Project Federal contract opportunity
Solicitation number
AG-9A23-S-13-0039
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

Attachment 1 Specification - Section 01301 Mobilization

View the file

Other files for this federal contract opportunity

Other files attached to Lake Isabella Boarding Floats Replacement Project, newest first.
File Type Posted
Amend_1_to_AG-0039.pdf PDF
RFP_AG-9A23-S-13-0039_LI_Boarding_Floats.pdf PDF
Attachment_8_Bid_Bond_SF-24.pdf PDF
Attachment_6_PAL_Variance_Data.pdf PDF
Attachment_3_02500_Boarding_Floats_and_Gangplanks.pdf PDF
Attachment_7_Wage_Determination.pdf PDF
Attachment_4_Project_Drawings.pdf PDF
Attachment_2_02100_Demolition.pdf PDF
Attachment_5_Fire_Plan.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01301 - 1

SECTION 01301- MOBILIZATION

PART 1 - GENERAL

1.1 DESCRIPTION

A. This Work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site.

Mobilization includes the obtaining of all permits, insurance, and bonds.

1.2 PERMITS

A. The Government does not purchase building, electrical, plumbing, or encroachment permits. The Contractor will not be reimbursed for such permits. The Contractor, under its program for project quality control, may request and pay for inspection of these items from the local jurisdiction. All other permits remain the Contractor’s responsibility to obtain.

B. The contractor is responsible for the fees and permits required to move oversize loads on state and local roads.

1.3 MEASUREMENT AND PAYMENT

A. Method of Measurement: Lump Sum Quantity (LSQ).

B. Unit of Measurement: Job. The Government will only pay for the initial project mobilization. Additional project mobilizations, regardless of cause, will not be paid.

Mobilization is shown on the SCHEDULE OF ITEMS using pay item 01301(01); with payment for mobilization to project location: Lake Isabella.

C. Progress payment for Mobilization lump sum will be paid as follows:

1. Bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments

Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.

2. When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

3. When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

4. Any portion of the mobilization item in excess of the 10 percent of the original contract amount will be paid after final acceptance.

END OF SECTION