DIVISION 1
01010 – SCOPE OF WORK
PART 1 – GENERAL
1.1 – Definitions
Contractor – the successful bidder who is awarded the contract.
Government – the Contracting Officer (CO) or designated Contracting Officer’s Representative (COR) of the Coronado National Forest.
1.2 – Description
Contractor shall furnish all materials, equipment, transportation, labor, supervision, and other associated work needed to complete work according to the scope of work, drawings and specifications.
1.3 – Location and Conditions
Work to take place at Columbine Work Center.
Electricity is available for Contractor use. Contractor is expected to use electricity as sparingly as possible.
Water for construction and personal use is available to the contractor. Large amounts of water are not available until after July. Minimal amounts are available prior to and during July. Coordinate water use with the Government.
Restroom facilities are available for contractor use.
It will be the Contractor’s responsibility to familiarize themselves with the existing conditions and notify the Government of any discrepancies shown in these documents.
1.4 – Schedule
A pre‐work meeting will be held at each site for clarification of the project.
A schedule for all work must be submitted to and approved by the Government.
The Contractor shall notify the Government three days in advance of any construction work.
The Contractor may stay in one or more of the Cabins at the Work Center during construction. The Contractor shall leave the cabin clean.
Estimated start work date is June, 28.
All work shall be completed within 90 120 days of award.
14. Pavement Marking Paint
15. Interior Paint
16. Interior Metal Doors
17. Lock Sets for Interior Doors
18. Towel Rods
19. Clothes Hooks
20. Toilet Paper Dispensers
21. Light Fixtures
22. Bathroom Heater/Fan Combinations
23. Toilet Grab Bars
24. Interior Cement Wall Board
25. Electrical Components
26. Porch Deck Material
27. Insulation
28. Floor Drain
29. Siding‐Fiber Cement Board
30. Faucets
31. Toilet Valve
32. Base Board Heater
A. Certificates of compliance are required for the following items:
1. Aggregate
2. Concrete
3. Asphalt
4. Rebar
5. Water Pipe
6. Sewer Pipe
7. Lumber
8. Sheetrock
*** END OF SPECIFICATION 01040 ***
2. CL: Approvals, inspections, sampling, testing or measuring under the direction of and certification by a qualified employee of a certified lab or by a Registered Professional Engineer in the state of Arizona. The Contractor shall be responsible for furnishing the Professional services as shown in Table 1400‐1.
TABLE 1400‐1
QUALITY CONTROL, INSPECTION, SAMPLING, TESTING, AND MEASUREMENTS
Item
Approvals, inspections, sampling, minimum or tests required
Frequency
Certification
Subgrade Compaction test 3 total CL
Aggregate base Compaction test 3 total CL
Asphalt concrete Compaction test 3 total CL
Concrete Cylinder set 2 1 total CL
Air entertainment test 2 total CL
Slump 2 total CL
*** END OF SPECIFICATION 01050 ***
DIVISION 2
02231 – CLEARING AND GRUBBING
PART 1 – GENERAL
1.1 – Summary
This section includes clearing of vegetation, and grubbing of stumps, roots, and debris;
disposal of unutilized materials; and other incidental work related to preparing the site for later use.
1.2 – Definitions
A. Clearing: Clearing shall consist of the felling, trimming, and cutting of obstructions such as trees into sections and the satisfactory disposal of the trees and other surface vegetation designated for removal, including down timber, snags, brush, and rubbish occurring in the areas to be cleared. The Government shall cut and buck all trees designated for removal.
B. Grubbing: Grubbing shall consist of the removal and disposal of below‐surface stumps, roots larger than 3‐inches in diameter, and matted roots from the designated grubbing areas.
1.3 – Project/Site Conditions
A. Work Limits: Work limits will be staked and control points established by the Government.
B. Burning of Slash: Shall not be permitted.
C. Landscape Preservation: Protect vegetation outside the work limits from injury.
Existing trees and shrubs shall not be disturbed or damaged.
PART 2 – PRODUCTS
(There are no applicable requirements)
PART 3 – EXECUTION
3.1 – Clearing
A. Requirements: Clear trees, stumps, roots, brush, and other vegetation in areas to be graded; cut off flush with or below the original ground surface, except such trees and vegetation indicated or directed to be left standing. Trees designated to be left standing within the cleared areas shall be trimmed of dead branches 1‐1/2 inches and shall be trimmed of all branches to the heights indicated by the Contracting Officer’s