601 Mobilization.doc

DOC document 22 KB Posted

Attached to
RECOVERY: Los Padres Road and Hazardous Fuels Clearing
Solicitation number
AG-9702-S-10-0149
Issued by

About this file

Mobilization

View the file

Other files

File Type Posted
FAQs2.docx DOCX document
FAQs.docx DOCX document
SF 1449(3_2005).pdf PDF
Section C.rtf RTF text file
Sch of Items.xls XLS spreadsheet
DRAWINGS.pdf PDF
Loc-Map Ojai.pdf PDF
Fire Plan.doc DOC document
Loc-Map MRD.pdf PDF
Vicinity Map.pdf PDF
842 Logging Out.doc DOC document
Loc-Map MPRD.pdf PDF
AG-9702-S-10-0149-Clauses.rtf RTF text file
Section-J.xls XLS spreadsheet
Section H.rtf RTF text file
Loc-Map SBRD.pdf PDF
841 Brush Cutting.doc DOC document
Loc-Map SLRD.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROJECT SPECIFICATION

SECTION 601 – MOBILIZATION

DESCRIPTION

601.01A WORK. This work consists of moving personnel, equipment, materials, and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the obtaining of permits, insurance, and bonds.

MEASUREMENT

601.02A METHOD. Mobilization will be measured by the Lump Sum.

PAYMENT

601.03A BASIS. The accepted quantity, measured as provided above, will be paid at the contract price per unit of measurement for the pay item listed below that is shown in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

The mobilization lump sum will be paid as follows:

(a) Bond premiums will be reimbursed after receipt of the evidence of payment.

(b) 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

(c) Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

(d) Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

Payment will be made under:

Pay Item

601 (01) Mobilization ………………………………………………Lump Sum

(includes bonding cost)

R5