Attachment 2_02052_Demolition.doc
DOC document 32 KB Posted
- Attached to
- RECOVERY: Remove and Replace Water Distribution System Federal contract opportunity
- Solicitation number
- AG-9702-S-10-0045
About this file
Attachment 2 Demolition
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 7_120507_Fire Plan.doc | DOC document | |
| Attachment 1_01300_Submittals.doc | DOC document | |
| Attachment 8_Project Location Map.jpg | JPG image | |
| Attachment 9_Trench Detail.pdf | ||
| Attachment 3_02222_Trench.doc | DOC document | |
| Attachment 6_02675_Disinfection.doc | DOC document | |
| Attachment 10_Wage Determination CA33.pdf | ||
| Attachment 4_02640_Valves.doc | DOC document | |
| Attachment 5_02660_Water Distribution.doc | DOC document | |
| AG-9702-S-10-0045 RFQ.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 02052
DEMOLITION
PART 1 - GENERAL
1.01 Scope
Perform demolition work AS SHOWN ON THE DRAWINGS and as specified herein. Work may be indicated by note or by non-inclusion in work shown to remain. The work consists of:
A. Removing existing distribution water line from the well to the storage tank.
B.
Disposing of demolished and removed materials
1.02 Project Conditions
A.
Existing Utilities: It may be necessary to relocate or stub-off or plug domestic water lines to complete the work.
B.
Safety: Demolition work shall be performed in a manner ensuring the safety of persons, and existing facilities designated to remain against damage by settlement, falling debris, or other causes in connection with this work.
C.
All of such work shall be in accordance with codes, regulations, and safety orders, and subject to approval of the Contracting Officer.
PART 2 - PRODUCTS
2.01 Equipment
The Contractor shall select equipment of a size and type suitable for the space and other constraints of this contract as subject to approval by the Contracting Officer.
PART 3 - EXECUTION
3.01 Demolition
A.
Existing Utilities:
1.
Information on the drawings relating to existing utility lines and services is from the best sources presently available. All such information is furnished only for information and is not guaranteed. The Contractor shall verify actual locations.
2.
Perform work and provide necessary materials to disconnect or relocate existing utilities as necessary.
3.
Above Ground Utilities: Remove existing water line from the well to the storage tank. Removed material shall be disposed of off Government land.
3.02 Disposal Remove all waste materials, rubbish, and debris. Accumulation is not permitted. Clean-up, transport and dispose of such in accordance with applicable codes and regulations.
END OF SECTION
WATER DISTRIBUTION
DIVISION 2
Section 02052-1