01330-1
SECTION 01330
SUBMITTAL PROCEDURES
PART 1 - GENERAL
Description Work under this section consists of furnishing all manufacturer's data, samples, certifications, guarantees, reports, installation manuals, and maintenance manuals.
Submittals also include all shop drawings, as built drawings, warranties, inspection and test reports, and quantity measurements.
| Submittals |
| Manufacturer's Literature |
| The Contractor will demonstrate compliance to this contract by submission of Manufacturer's literature and shop drawings. The purpose of the Manufacturer's Literature and shop drawings is to demonstrate to the COR that the Contractor has an understanding of the equipment and material he intends to furnish and install, and the details of the fabrication and installation intended to be used. |
PART 2 - PRODUCTS - None.
PART 3 - EXECUTION
Timing and Approval It will be the Contractor's responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work which involves the item. Contractor shall allow ten (10) working days from date of receipt, by the Government, for processing of submittals, unless otherwise specified. If after review, the COR determines that the submittal requires changes or revisions, the Contractor shall supply the COR with a revised submittal. The Government review period will be repeated for each re-submittal. The Government will assume no liability for loss of time or money should the Contractor fail to comply with this specification.
| The approval of the shop drawings by the COR shall not be construed as a complete check but will indicate only that the general method of construction is satisfactory. Approval of the shop drawings will not relieve the Contractor of the responsibility for any errors or omissions which may exist on the approved shop drawings as the Contractor will be responsible for the satisfactory construction of all work covered under this contract. If deviations, discrepancies or conflicts between shop drawings and specifications are discovered either prior to or after shop drawings submittals are approved by the COR, the design drawings and specifications shall control and shall be followed. |
| Number of Copies and Information Required |
| Submit two (2) copies to the COR for approval on the items required herein. For each submittal, the Contractor must receive written approval from the COR to use the item before incorporating it into the project work. All submittals shall have the project name, the intended location, and reference specification number on the submittal. All data and literature submitted shall be complete and marked or otherwise designated to show the exact model, type, size, number required, etc., the Contractor proposes to use. Information must be adequate to determine compliance with the specifications. If material or equipment other than that specified is submitted for approval, the submittal data shall clearly show and point out any differences with adequate information to determine its equality. |
Submittals will be waived if Contractor furnishes exact item used for design when manufacturer's model, size, etc. are shown in the contract, however a copy of the invoice from the supplier shall be provided to the COR.
Submittals should preferably be made in groups of items which are related to facilitate cross checking and coordination.
PART 4 - MEASUREMENT AND PAYMENT
Measurement
| The work specified herein will not be measured for payment. |
| Payment |
The work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SECTION
Other files
| File | Type | Posted |
|---|---|---|
| SF 30.pdf | ||
| resp pkg 20 TP warehouse roof.docx | DOCX document | |
| A-1 Model | — | |
| A-5 Model | — | |
| T-1_TITLESHT T1.pdf | ||
| A-4 Model | — | |
| 13100_Lightning_Protection_BSD.rtf | RTF text file | |
| 01300-mobilization.rtf | RTF text file | |
| 20 TP warehouse roof.docx | DOCX document | |
| A-3 Model | — | |
| 01732_02.doc | DOC document | |
| A-6 Model | — | |
| 07900_-_joint_sealers.docx | DOCX document | |
| 07130_-_underlaymentr.rtf | RTF text file | |
| A-2 Model | — | |
| Wage Det NM100001 6-4-10 NM1.docx | DOCX document | |
| 07410-metal_roofing.rtf | RTF text file |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .