01300-1

SECTION 01300

MOBILIZATION

PART 1 - GENERAL

Description

This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site. Mobilization will be paid for only once, even if multiple mobilizations are warranted due to weather or other circumstances.

PART 2 - PRODUCTS None.
PART 3 - EXECUTION None.

PART 4 - MEASUREMENT AND PAYMENT

Payment
The Contractor can request payment for performance and payment bonds. The amount of the bond premium, including coinsurance and reinsurance agreements, will be paid upon receipt of evidence of full payment to the surety. When separate copayment for bonding cost is made, the bonding cost will be subtracted from the total contract amount for this pay item and the balance paid in accordance with the progress payment schedule outlined below.

Any bonding costs in excess of the total contract amount of this pay item will not be paid for directly but shall be considered subsidiary to other pay items under this contract. In no circumstance will the total amount of this contract be increased as a result of bonding costs exceeding the total contract amount of this pay item. The total of all payments shall not exceed the original contract amount for this item.

Progress payments will be made as follows:

When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.

When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.

Upon completion of all work on the project, any unpaid amount for mobilization will be paid.

The total of all payments, including bonding, shall not exceed the original contract amount for this item.

Payment will be made under:

Pay Item Description Pay Unit

01300(01) Mobilization (includes bonding) LS

END OF SECTION

Other files

File Type Posted
SF 30.pdf PDF
resp pkg 20 TP warehouse roof.docx DOCX document
A-1 Model —
A-5 Model —
T-1_TITLESHT T1.pdf PDF
01330-submittal_procedure.rtf RTF text file
A-4 Model —
13100_Lightning_Protection_BSD.rtf RTF text file
20 TP warehouse roof.docx DOCX document
A-3 Model —
01732_02.doc DOC document
A-6 Model —
07900_-_joint_sealers.docx DOCX document
07130_-_underlaymentr.rtf RTF text file
A-2 Model —
Wage Det NM100001 6-4-10 NM1.docx DOCX document
07410-metal_roofing.rtf RTF text file
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .