Section_151_mobilization_new.doc
DOC document 23 KB Posted
- Solicitation number
- AG-83A7-S-10-0006
About this file
Attachment - Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 30.pdf | ||
| Section_154_contractor_sampling_and_testing_new.doc | DOC document | |
| Canjilon_Creek_Restoration 2.pdf | ||
| Gen Dec Num NM100002 3-12-10.docx | DOCX document | |
| Section_211_Roadway_Obliteration.rtf | RTF text file | |
| Section_106_Acceptance_of_Work.doc | DOC document | |
| Section_635_Temporary_Traffic_Control.doc | DOC document | |
| Section_725_miscellaneous_materials_new.doc | DOC document | |
| Section_705_Rock.docx | DOCX document | |
| CONSTRUCTION rfq FR559.docx | DOCX document | |
| Canjilon_Creek_Restoration.pdf | ||
| Section_710_Fence_and_Guardrail.rtf | RTF text file | |
| Section_303_road_reconditioning_new.doc | DOC document | |
| Canjilon_Creek_Restoration_title_sheet Layout1 | — | |
| Section_703_Aggregate.doc | DOC document | |
| Section_301_untreated_aggregate_courses_new.doc | DOC document | |
| Section_109_Measurement_and_Payment.doc | DOC document | |
| response package.docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 151. — MOBILIZATION
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the obtaining of permits, insurance, and bonds.
Measurement
151.02 Measure mobilization according to Subsection 109.02.
Payment
151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151(01) pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Progress payments for mobilization lump sum will be paid as follows:
(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.