Solicitation Request for Proposal
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amendment2.doc | DOC document | |
| amendment1.doc | DOC document | |
| VicinityHogPark.pdf | ||
| HogParkAppendixC.doc | DOC document | |
| HogParkAppendixA.doc | DOC document | |
| CAMHogPark.pdf | ||
| HogParkSolicitation.doc | DOC document | |
| HogParkAppendixBscaled.doc | DOC document | |
| irsc_scaled_template_appendix_B.doc | DOC document | |
| appendix_C_road_maintenance.doc | DOC document | |
| irsc_treemeasurement_appendix_A.doc | DOC document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMERCIAL ITEMS
SOL. # AG-82X9-S-09-0149
FHTR Stewardship
| SOLICITATION/CONTRACT/ORDER AL ITEMS |
| 1. REQUISITION NUMBER |
| PAGE 1 OF |
| OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30 |
| 65 |
| 2. CONTRACT NO. |
| 3. AWARD/EFFECTIVE |
| 4. ORDER NUMBER |
| 5. SOLICITATION NUMBER |
| 6. SOLICIATION ISSUE |
| DATE |
| AG-82X9-S-09-0149 |
| DATE |
July 15, 2009
| a. NAME |
| b. TELEPHONE NUMBER(No collect |
| 8. OFFER DUE DATE/ |
August 14, 2009
| 7. FOR SOLICITATION |
| RICHARD BRAUN; rabraun@fs.fed.us |
| p.303-275-5264 |
| LOCAL TIME |
INFORMATION CALL:
| f.303-275-5299 |
| at 4:00 p.m. |
| 9. ISSUED BY CODE |
| 10. THIS ACQUISITON IS |
| 11. DELIVERY FOR |
| 12. DISCOUNT TERMS |
FOB DESTINATION
| US Forest Service |
| 100% Small Business Set-Aside |
| UNLESS BLOCK IS |
Region 2, Regional Office
MARKED
Attn: Richard Braun 740 Simms St.
Golden, CO 80401
FORMCHECKBOX
SEE SCHEDULE
FORMCHECKBOX
13a. THIS CONTRACT IS A RATED
ORDER UNDER DPAS (15 CFR 700)
13b. RATING
| NAICS: 113310 |
| N/A |
| SIZE STANDARD: 500 Employ- |
| 14. METHOD OF SOLICITATION |
| ees |
| FORMCHECKBOX |
RFQ FORMCHECKBOX
IFB X RFP
15. DELIVER TO CODE
Same as block 9
16. ADMINISTERED BY CODE
Same as block 9
17a. CONTRACTOR/ CODE FACILITY
OFFEROR CODE
18a. PAYMENT WILL BE MADE BY CODE
Albuquerque Service Center
TELEPHONE N0.
FORMCHECKBOX
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
| OFFER |
| IS CHECKED |
FORMCHECKBOX
SEE ADDENDUM
| 19. |
| 20. |
| 21. |
| 22. |
| 23. |
| 24. |
| ITEM N0. |
| SCHEDULE OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Hazard Tree Removal Slash Treatment associated with Hazard Tree Removal Option Period 1, 2 years
Option Period 2, 1 year Quantities will be specified at the task order level
| Acre, tree or ton |
| Pricing to be determined at the Task Order Level thru the Fair Opportunity Process. |
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
$ 0.0
| X |
| 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA |
| X |
| ARE |
ARE NOT ATTACHED
| X |
| 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.2124. FAR 52.212-5 IS ATTACHED. ADDENDA |
| X |
| ARE |
ARE NOT ATTACHED
| 28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN |
| FORMCHECKBOX |
29. AWARD OF CONTRACT: REF. OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
| DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY |
| DATED .. YOUR OFFER ON SOLICITATION |
| ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN. |
| (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE |
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
| 30a. SIGNATURE OF OFFEROR/CONTRACTOR |
| 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) |
| 30b. NAME AND TITLE OF SIGNER (Type or print) |
| 30c. DATE SIGNED |
| 31b. NAME OF CONTRACTING OFFICER (Type or print) |
| 31c. DATE SIGNED |
TIMBER PRODUCTS: Values of timber products removed to be applied at Flat Rates
19.
SPECIES
20.
PRODUCT
21.
ESTIMATED
QUANTITY
22.
UNIT OF MEASURE
23.
MINIMUM ACCEPTABLE OFFER
24.
OFFER
(FLAT)
25.
TOTAL OFFER
| Will be specified at the Task Order level |
| SAW |
| Will be specified at the Task Order level |
| CCF |
| Will be specified at the Task Order level |
| Will be specified at the Task Order level |
| POL |
| Will be specified at the Task Order level |
| CCF or Ton |
| Will be specified at the Task Order level |
| Will be specified at the Task Order level |
| Biomass |
| Will be specified at the Task Order level |
| CCF or Ton |
| Will be specified at the Task Order level |
See Timber Removal Project Terms and Specifications in Appendix B.
32a. QUANTITY IN COLUMN 21 HAS BEEN
FORMCHECKBOX
RECEIVED
FORMCHECKBOX
INSPECTED
FORMCHECKBOX
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ________________________________________
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
| 33. SHIP NUMBER |
| 34. VOUCHER NUMBER |
| 35. AMOUNT VERIFIED |
CORRECTFOR
| 36. PAYMENT |
| 37. CHECK NUMBER |
|PARTIAL | |FINAL
FORMCHECKBOX
COMPLETE FORMCHECKBOX
PARTIAL FORMCHECKBOX
FINAL
| 38. S/R ACCOUNT NUMBER |
| 39. S/R VOUCHER NUMBER |
| 40. PAID BY |
| 41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER |
| FOR PAYMENT |
| 42a. RECEIVED BY (Print) |
| 41 b. SIGNATURE AND TITLE OF CERTIFYING OFFICER |
| 41 c. DATE |
42b. RECEIVED AT (Location)
| 42c. DATE RECD (YY/MM/DD) |
| 42d. TOTAL CONTAINERS |
STANDARD FORM 1449 (REV.4/2002) BACK
FAIR OPPORTUNITY PROCEDURES
Any contractor who is awarded a contract resulting from this solicitation will be given a fair opportunity to compete for future task order requirements. Contract holders will be contacted by the contracting officer prior to issuance of any task order. Those who wish to compete for the order will be sent the statement of work, evaluation factors, and other pertinent information along with a deadline for submitting a proposal. Proposals will be evaluated and the task order will be awarded to the firm that offers the best value to the government. Contractors are under no obligation to submit a proposal for any given task order.
TASK ORDER FORMS
Task orders may be issued on the OF 347, SF 1449, or any other form approved by the contracting officer.
ESTIMATED QUANTITIES OF WORK
The Forest Service (FS) estimates that it may order between 200 and 600 acres of service work per year thru the contracts that result from this solicitation. This is not a representation to an offeror or contractor that the estimated quantity will be required or ordered, or that conditions affecting requirements will be stable or normal. This estimate does not include the FS’ in-house capability to perform up to 100 acres of this type of work annually.
CONTRACT CLAUSES
52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders -- Commercial Items (Jun 2009)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.222-50, Combating Trafficking in Persons (FEB 2009) (22 U.S.C. 7104(g)).
(2) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(3) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the contracting officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
[Contracting Officer shall check as appropriate.] ___ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sep 2006), with Alternate I (Oct 1995)(41 U.S.C. 253g and 10 U.S.C. 2402).
___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Dec 2008) (Pub. L. 110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Mar 2009) (Section 1553 of Pub L. 111-5) (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009).
___ (4) 52.204-11, American Recovery and Reinvestment Act—Reporting Requirements (Mar 2009) (Pub. L. 111-5).
___ (5) 52.219-3, Notice of Total HUBZone Set-Aside (Jan 1999)(15 U.S.C. 657a).
___ (6) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Jul 2005) (if the offeror elects to waive the preference, it shall so indicate in its offer)(15 U.S.C. 657a).
___ (7) [Reserved]
_X__ (8) (i) 52.219-6, Notice of Total Small Business Aside (June 2003) (15 U.S.C. 644).
___ (ii) Alternate I (Oct 1995) of 52.219-6.
___ (iii) Alternate II (Mar 2004) of 52.219-6.
___ (9) (i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003)(15 U.S.C. 644).
___ (ii) Alternate I (Oct 1995) of 52.219-7.
___ (iii) Alternate II (Mar 2004) of 52.219-7.
_X_ (10) 52.219-8, Utilization of Small Business Concerns (May 2004) (15 U.S.C. 637(d)(2) and (3)).
___ (11) (i) 52.219-9, Small Business Subcontracting Plan (Apr 2008)(15 U.S.C. 637 (d)(4).)
___ (ii) Alternate I (Oct 2001) of 52.219-9.
___ (iii) Alternate II (Oct 2001) of 52.219-9.
_X_ (12) 52.219-14, Limitations on Subcontracting (Dec 1996)(15 U.S.C. 637(a)(14)).
___ (13) 52.219-16, Liquidated Damages—Subcontracting Plan (Jan 1999)(15 U.S.C. 637(d)(4)(F)(i)).
___ (14) (i) 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns (Oct 2008)(10 U.S.C. 2323) (if the offeror elects to waive the adjustment, it shall so indicate in its offer).
___ (ii) Alternate I (June 2003) of 52.219-23.
___ (15) 52.219-25, Small Disadvantaged Business Participation Program—Disadvantaged Status and Reporting (Apr 2008)(Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).
___ (16) 52.219-26, Small Disadvantaged Business Participation Program—Incentive Subcontracting (Oct 2000) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).
___ (17) 52.219-27, Notice of Total Service-Disabled Veteran-Owned Small Business Set-Aside (May 2004) (15 U.S.C. 657 f).
_X__ (18) 52.219-28, Post Award Small Business Program Rerepresentation (Apr 2009) (15 U.S.C. 632(a)(2)).
_X_ (19) 52.222-3, Convict Labor (June 2003)(E.O. 11755).
_X_ (20) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Feb 2008) (E.O. 13126).
_X_ (21) 52.222-21, Prohibition of Segregated Facilities (Feb 1999).
_X_ (22) 52.222-26, Equal Opportunity (Mar 2007)(E.O. 11246).
_X_ (23) 52.222-35, Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (Sep 2006)(38 U.S.C. 4212).
_X_ (24) 52.222-36, Affirmative Action for Workers with Disabilities (Jun 1998)(29 U.S.C. 793).
_X_ (25) 52.222-37, Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (Sep 2006)(38 U.S.C. 4212).
___ (26) 52.222-39, Notification of Employee Rights Concerning Payment of Union Dues or Fees (Dec 2004) (E.O. 13201).
___ (27) 52.222-54, Employment Eligibility Verification (Jan 2009). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)
___ (28) (i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)(42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (29) 52.223-15, Energy Efficiency in Energy-Consuming Products (Dec 2007) (42 U.S.C. 8259b).
___ (30) (i) 52.223-16, IEEE 1680 Standard for the Environmental Assessment of Personal Computer Products (Dec 2007) (E.O. 13423).
___ (ii) Alternate I (Dec 2007) of 52.223-16.
___ (31) 52.225-1, Buy American Act--Supplies (Feb 2009)(41 U.S.C. 10a-10d).
___ (32) (i) 52.225-3, Buy American Act –Free Trade Agreements – Israeli Trade Act (Jun 2009) (41 U.S.C. 10a-10d, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, Pub. L. 108-77, 108-78, 108-286, 108-301, 109-53, 109-169, 109-283, and 110-138).
___ (ii) Alternate I (Jan 2004) of 52.225-3.
___ (iii) Alternate II (Jan 2004) of 52.225-3.
___ (33) 52.225-5, Trade Agreements (Jun 2009) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).
___ (34) 52.225-13, Restrictions on Certain Foreign Purchases (Jun 2008) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
___ (35) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).
___ (36) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).
___ (37) 52.232-29, Terms for Financing of Purchases of Commercial Items (Feb 2002) (41 U.S.C. 255(f), 10 U.S.C. 2307(f)).
___ (38) 52.232.30, Installment Payments for Commercial Items (Oct 1995)(41 U.S.C. 255(f), 10 U.S.C. 2307(f)).
_X_ (39) 52.232-33, Payment by Electronic Funds Transfer—Central Contractor Registration (Oct. 2003)(31 U.S.C. 3332).
___ (40) 52.232-34, Payment by Electronic Funds Transfer—Other Than Central Contractor Registration (May 1999)(31 U.S.C. 3332).
___ (41) 52.232-36, Payment by Third Party (May 1999)(31 U.S.C. 3332).
___ (42) 52.239-1, Privacy or Security Safeguards (Aug 1996)(5 U.S.C. 552a).
___ (43) (i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006)(46 U.S.C. Appx 1241(b) and 10 U.S.C. 2631).
___ (ii) Alternate I (Apr 2003) of 52.247-64.
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or executive orders applicable to acquisitions of commercial items:
[Contracting Officer check as appropriate.]
_X_ (1) 52.222-41, Service Contract Act of 1965 (Nov 2007)(41 U.S.C. 351, et seq.).
_X_ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 1989)(29 U.S.C. 206 and 41 U.S.C. 351, et seq.).
_X_ (3) 52.222-43, Fair Labor Standards Act and Service Contract Act -- Price Adjustment (Multiple Year and Option Contracts) (Nov 2006)(29 U.S.C.206 and 41 U.S.C. 351, et seq.).
___ (4) 52.222-44, Fair Labor Standards Act and Service Contract Act -- Price Adjustment (Feb 2002)(29 U.S.C. 206 and 41 U.S.C. 351, et seq.).
___ (5) 52.222-51, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (Nov 2007) (41 U.S.C. 351, et seq.).
___ (6) 52.222-53, Exemption from Application of the Service Contract Act to Contracts for Certain Services--Requirements (Feb 2009) (41 U.S.C. 351, et seq.).
___ (7) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (Mar 2009) (Pub. L. 110-247).
___ (8) 52.237-11, Accepting and Dispensing of $1 Coin (Sep 2008)(31 U.S.C. 5112(p)(1)).
(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, and does not contain the clause at 52.215-2, Audit and Records -- Negotiation.
(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.
(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.
(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.
(e)
(1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), (c) and (d) of this clause, the Contractor is not required to flow down any FAR clause, other than those in paragraphs (e)(1) of this paragraph in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause--
(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Dec 2008) (Pub. L. 110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).
(ii) 52.219-8, Utilization of Small Business Concerns (May 2004)(15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $550,000 ($1,000,000 for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.
(iii) [Reserved]
(iv) 52.222-26, Equal Opportunity (Mar 2007)(E.O. 11246).
(v) 52.222-35, Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (Sep 2006)(38 U.S.C. 4212).
(vi) 52.222-36, Affirmative Action for Workers with Disabilities (June 1998)(29 U.S.C. 793).
(vii) 52.222-39, Notification of Employee rights Concerning Payment of Union Dues or Fees (Dec 2004) (E.O. 13201).
(viii) 52.222-41, Service Contract Act of 1965, (Nov 2007), flow down required for all subcontracts subject to the Service Contract Act of 1965 (41 U.S.C. 351, et seq.)
(ix) 52.222-50, Combating Trafficking in Persons (Feb 2009) (22 U.S.C. 7104(g)).
___ Alternate I (Aug 2007) of 52.222-50 (22 U.S.C. 7104(g)).
(x) 52.222-51, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (Nov 2007) (41 U.S.C. 351, et seq.)
(xi) 52.222-53, Exemption from Application of the Service Contract Act to Contracts for Certain Services--Requirements (Feb 2009) (41 U.S.C. 351, et seq.)
(xii) 52.222-54, Employment Eligibility Verification (Jan 2009).
(xiii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (Mar 2009) (Pub. L. 110-247). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.
(xiv) 52.247-64, Preference for Privately-Owned U.S. Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx 1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.
(2) While not required, the contractor may include in its subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.
(End of Clause)
52.216-18 - Ordering (Oct 1995)
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from Date of Contract award through the termination of the contract.
(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.
(c) If mailed, a delivery order or task order is considered “issued” when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods.
52.216-19 - ORDER LIMITATIONS (OCT 1995)
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than __10 ACRES _, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor --
(1) Any order for a single item in excess of __500 ACRES;
(2) Any order for a combination of items in excess of 500 ACRES; or
(3) A series of orders from the same ordering office within __365 days that together call for quantities exceeding the limitation in subparagraph (b)(1) or (2) of this section.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.
(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within 15 days after issuance, with written notice stating the Contractor’s intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
52.216-21 –REQUIREMENTS, ALT 1(APR 1984)
(a) This is a requirements contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies or services specified in the Schedule are estimates only and are not purchased by this contract. Except as this contract may otherwise provide, if the Government’s requirements do not result in orders in the quantities described as “estimated’’ or “maximum” in the Schedule, that fact shall not constitute the basis for an equitable price adjustment.
(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. Subject to any limitations in the Order Limitations clause or elsewhere in this contract, the Contractor shall furnish to the Government all supplies or services specified in the Schedule and called for by orders issued in accordance with the Ordering clause. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.
(c) The estimated quantities are not the total requirements of the Government activity specified in the Schedule, but are estimates of requirements in excess of the quantities that the activity may itself furnish within its own capabilities. Except as this contract otherwise provides, the Government shall order from the Contractor all of that activity’s requirements for supplies and services specified in the Schedule that exceed the quantities that the activity may furnish within its own capabilities.
(d) The Government is not required to purchase from the Contractor requirements in excess of any limit on total orders under this contract.
(e) If the Government urgently requires delivery of any quantity of an item before the earliest date that delivery may be specified under this contract, and if the Contractor will not accept an order providing for the accelerated delivery, the Government may acquire the urgently required goods or services from another source.
(f) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period.
52.216-27 -SINGLE OR MULTIPLE AWARDS (OCT 1995)
The Government may elect to award a single task order contract or to award multiple task order contracts for the same or similar supplies or services to two or more sources under this solicitation.
52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within15 days of the end of the contract; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 20 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 5 years.
CONTRACT DOCUMENTS, EXHIBITS OR ATTACHMENTS
1.
PROJECT DESCRIPTION/ SCOPE OF WORK
(a) Description of Work- This solicitation and any resultant contract is a stewardship project in accordance with Section 323 of Public Law 108-7 (16 U.S.C. 2104 Note, as revised February 28, 2003 to reflect sec. 323 of J.J. Res. 2 as enrolled), the Consolidated Appropriations Resolution, 2003, amending Public Law 105-277, sec. 347. This is a commercial item acquisition that has been tailored to fit the Government’s method of trading goods for services. Work includes performance of stewardship activities within the boundaries of the Medicine Bow-Routt National Forest. The work required by this contract includes all of the requirements outlined in block 20, Schedule of Supplies/Services, as well as timber harvest and removal of sawtimber, nonsawtimber, and biomass. Specific requirements will be specified at the task order level.
(b) Scope of Work - The scope of work for this Requirements Contract is for the contractor to fell, limb, skid, deck and remove Hazard Trees within Forest Service (FS): campgrounds, picnic areas, trailheads, administrative sites; and Forest Service roads, state roads, and county roads that are within or adjacent to the Medicine Bow-Routt National Forest. Work along road ways and in campgrounds and administrative sites may include but is not limited to: chipping, whole tree yarding, lopping and scattering slash, roller chopping, hand piling or machine piling, and machine trampling. One or more of these activities may be included in a task order but at a minimum, removal of the bole of the tree will be required in all task orders. The definition of Hazard Tree can include any sawtimber, nonsawtimber, and/or biomass sized tree that the FS considers to be a hazard to life, health, safety, or the environment. Within the areas specifically described by this paragraph, the following work is specifically excluded from the scope of work: 1) work that is offered as a Timber Sale and receives at least 1 responsible, responsive bid, and 2) work areas where the value of timber products is estimated by the Forest Service to be greater than the cost of the service work.
(c) The Contractor shall provide everything necessary to perform this contract unless such items are specifically identified herein as Government-furnished property.
(d) Resulting Contract – The resultant contract will be an unpriced Requirements Contract.
(e) Project Locations – All projects will be located within the Medicine Bow-
Routt National Forest. Specific locations will be identified at the task order level.
2.
SPECIFICATIONS
Specifications for each Stewardship Activity individually described by an item number in Schedule of Supplies/Services will be specified at the task order level in Appendix A of the applicable task order. Specifications for timber removal will be specified at the task order level in Appendix B of the applicable task order.
3.
CONTRACTOR QUALITY CONTROL INSPECTION SYSTEM
The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contractor shall produce written inspection records in a format and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data.
4.
ACCEPTANCE
The Forest Service shall perform an inspection upon Contractor’s written request and assurance that work has been completed. Request shall be for a reasonable portion of work. Acceptance may be made for all or portions of work.
5.
GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
Quality assurance plans specific to individual items will be found in Appendix A of the applicable task order.
6. 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after receipt of Notice to Proceed on any task order, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the date specified on the task order. The time stated for completion shall include final cleanup of the premises.
Timber Removal activities shall be scheduled and carried out in accordance with the Timber Removal Specifications in Appendix B of the applicable task order and as approved by the Contracting Officer.
7.
AGAR 452.211-74 PERIOD OF PERFORMANCE (FEB 1988)
The period of performance for this contract is 1 year from date of contract award. The period of performance for each task order will be specified at the task order level.
8. SCHEDULES AND REPORTS
Pursuant to contract requirements, the following submittals are required prior to issuance of a Notice to Proceed on any task order, for review and/or approval, unless stated elsewhere in the specifications or otherwise mutually agreed:
| ITEM DESCTRIPTION |
| COPIES REQUIRED |
| Proposed progress schedule showing starting and completion dates of various phases of the work (includes service work and timber removal). |
| 2 |
| List of proposed sub-contractors and their intended work. Sub-contractors must have Contracting Officers Written approval prior to starting work on the project. Submit on Standard Form 1413. |
| 2 |
| Traffic Control Plan, when applicable |
| 2 |
| Soil Erosion and Water Pollution Control Plan, when applicable |
| 2 |
| Designation of Contractor personnel describing responsibilities and authorities |
| 2 |
All schedules and reports shall be submitted to: the Contracting Officer or the designated Contracting Officer’s Representative.
9.
PAYMENT
It is anticipated that funds will be exchanged in the performance of this contract because the value of the timber will not completely offset the value of the work to be performed. When payment is made to the contractor for work performed, it will be made in accordance with FAR 52.232-1 – Payments.
The value of work completed and timber removed will be documented in an Integrated Resource Statement of Account produced by Timber Sale Accounting (TSA) monthly when harvesting operations are underway.
10.
STEWARDSHIP CREDITS
Stewardship Credits are credits that are earned and established when work listed in the Schedule of Supplies/Services has been performed and accepted. Stewardship credits shall be earned at the rate as shown in the Schedule. Earned credits may be used to pay for timber value included in Schedule. Unless otherwise indicated in the Schedules, credits will be earned based upon Actual Quantities accomplished and accepted.
11.
ESTABLISHMENT OF STEWARDSHIP CREDITS
Notwithstanding references to payments in “Payment” clauses or provisions of this contract, payment for Stewardship Activities will be made with Stewardship Credits as indicated in the award document.
Stewardship Credits will be established on a monthly basis. Stewardship credits will be established for the number of units of each activity that have been completed and accepted. Acceptance may be for all, or a reasonable portion of, any specific activity.
Stewardship credits will not be established for work that is in progress that has not been accepted by the Forest Service. No credits will be established for timber removal work performed under the terms of Appendix B, Timber Removal Specifications.
12.
CONTRACTOR CERTIFICATION
Monthly, as Stewardship Credits are established, the Contractor shall furnish the following certification (Contractor Certification - Earned Stewardship Credits) or credit will not be received.
CONTRACTOR CERTIFICATION - EARNED STEWARDSHIP CREDITS
Name of Stewardship Project or Task Order:
I hereby certify, to the best of my knowledge and belief, that--
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) Payments to subcontractors and suppliers have been made, and timely payments will be made for the work activities covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments/credits does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date)
13.
TIMBER PAYMENT GUARANTEE
(1) General—(a) To guarantee payment for timber scheduled for removal under the IRSC, the Contractor may earn Stewardship Credits in advance of removal, or provide a Timber Payment Guarantee in the form of an acceptable surety payment bond, or make cash payment.
(b) Any earned Stewardship Credits and alternate Timber Payment Guarantee together will maintain a minimum unobligated balance equal to the applicable charges for timber the Forest Service estimates will be cut in 60 calendar days plus the value of any outstanding charges, or equal to the total value of the timber that has not been paid for. (Applicable only to Scaled Contracts)
(b) Any earned Stewardship Credits and alternate Timber Payment Guarantee together will maintain a minimum unobligated balance equal to the outstanding charges for payment units released for cutting, or equal to the total value of timber that has not been paid for. (Applicable only to Tree Measurement Contracts)
(c) The penal sum of such surety bond shall be the maximum amount of the payment guaranteed.
(2) A Timber Payment Guarantee for a single contract shall be provided utilizing FS Form 6500-12.
(3) Blanket Surety Bond—(a) Contractor may furnish an acceptable bond to guarantee payment for timber from multiple contracts. Contractor shall not start cutting hereunder until this contract receives an allocation that will meet the obligation for payment guarantee.
(b) The amount of such bond shall be allocated to such contracts by the Forest Service. The Contractor will provide the contact information for the Forest Service representative administering the Blanket Surety Bond.
(c) When there is to be no timber cutting hereunder for 30 days or more and payment of current charges has been made, the allocation to this contract shall be reallocated to other contracts at Contractor’s request.
(d) A Timber Payment Guarantee for multiple contracts (Blanket Guarantee) shall be provided utilizing FS Form 6500-12a.
(3) Letters of Credit for Payment Bond—Contractor may use an Irrevocable Letter of Credit in lieu of a surety bond for payment bond purposes when approved by Contracting Officer.
14.
EXCESS STEWARDSHIP CREDITS
In the event there are excess (unused) established Stewardship Credits when all of the included timber has been cut and removed the Forest Service shall make payment by Electronic Funds Transfer (EFT).
15.
EXCESS TIMBER VALUE
In the event the value of the included timber exceeds the total value of all service work, the Contractor shall make cash payment for the excess timber value.
16.
REFUND OF EXCESS CASH
If at any time the credit balance of the Integrated Resource Statement of Account exceeds the charges for timber removed to date and for timber that the Forest Service estimates will be cut within the next 60 calendar days, any portion of such excess from cash in the account shall be refunded if requested by Contractor. If no cutting is planned within the next 60 calendar days, refund of the entire unencumbered cash balance may be made. After a refund, deposits shall be made to meet the requirements of the clause entitled, “TIMBER PAYMENT GUARANTEE” before additional timber may be cut.
17.
FINAL PAYMENT - RELEASE OF CLAIMS
The Government shall pay the amount due the Contractor under this contract after—
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.
18.
AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled within 30 days after the date of contract award and after issuance of each task order. The conference will be held at: will be specified in the task order, and will include discussion of contract terms and work performance requirements, work progress schedule and fire prevention/suppression and safety plans.
19. N/A 20.
AGAR 452.236-72 USE OF PREMISES (NOV 1996)
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
21.
AGAR 452.237-74 KEY PERSONNEL (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel:
Overall Project Manager
Logging Supervisor
Fuels Treatment Supervisor
(b) During the first 120 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 120-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
22.
FSAR 4G52.222-701 EMPLOYMENT OF ELIGIBLE WORKERS (DEC 1999)
Section 274A of the Immigration and Nationality Act (8 USC 1324a) makes it unlawful for an employer to hire unauthorized aliens. The Immigration and Naturalization Service (INS) has established the Form I-9, Employment Eligibility Verification Form, as the document to be used for employment eligibility verification (see 8 CFR 274a).
The contractor is required to (1) have all employees complete and sign the I-9 Form to certify that they are eligible for employment; (2) examine documents presented by the employee and ensure the documents appear to be genuine and related to the individual; (3) record information about the documents on the form, and complete the certification portion of the form; (4) retain the form for three years, or one year past the end of employment of the individual, whichever is longer.
It is illegal to discriminate against any individual (other than a citizen of another country who is not authorized to work in the United States) in hiring, discharging, or recruiting because of that individual's national origin or citizenship status.
Compliance with Section 274A of the Immigration and Nationality Act (8 U.S.C. 1324a) is a material condition of the contract. If the contractor employs unauthorized workers during contract performance in violation of section 274A, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.
For further information on the requirements of the Act, contractors should contact the Employer and Labor Relations Officer of their local INS office.
23.
FSAR 4G52.222-702 LABOR STANDARDS FOR CONTRACTS INVOLVING MIGRANT AND SEASONAL AGRICULTURAL WORKERS (DEC 1999) (a) General. This contract is subject to the Migrant and Seasonal Agricultural Workers Protection Act (MSPA) (29 U.S.C 1801-1872) and to Department of Labor regulations implementing MSPA (see 29 CFR 500). The purpose of MSPA is to eliminate activities that are detrimental to migrant and seasonal agricultural workers, to require registration of farm labor contractors, and to assure necessary protections for the workers. In addition to traditional farm labor activities, the Act applies to predominately manual forestry work including, but not limited to, tree planting, release, precommercial thinning, and site preparation and wildland fire fighting.
(b) Definitions.
"Migrant Agricultural Worker" and "Seasonal Agricultural Worker", as used in this clause, mean individuals employed in agricultural (including forestry) work on a seasonal or temporary basis. A worker who moves from one seasonal activity to another is employed on a seasonal basis even though the worker may continue to be employed during a major portion of the year. Migrant workers are required to be absent overnight from their permanent place of residence. Seasonal workers are not required to be absent overnight from their permanent place of residence. Members of the contractor's immediate family are not considered to be either migrant or seasonal workers. "Immediate family" includes only (1) spouse; (2) children, stepchildren, or foster children; (3) parents, stepparents, or foster parents; and (4) brothers and sisters.
"Farm Labor Contractor", as used in this clause, means an individual who, for any money or other valuable consideration, paid or promised to be paid, performs any recruiting, soliciting, hiring, employing, furnishing, or transporting of any migrant or seasonal agricultural worker.
(c) Registration Requirement. Any contractor who provides or hires migrant or seasonal workers to perform agricultural or manual forestry work shall first obtain a Certificate of Registration from the Department of Labor or an authorized State agency. The contractor shall carry the Certificate at all times while engaged in contract performance, and shall display it upon request. Any of the contractor's employees who also perform any one or more of the activities defined for a "Farm Labor Contractor" in paragraph (b) must have their own Farm Labor Contractor Employee Certificate.
(d) Worker Protections. The contractor shall comply with the following protections and standards related to wage disclosure, recordkeeping, vehicle safety, and housing:
(1) The contractor shall display and maintain at the place of employment the MSPA poster provided by the Department of Labor.
(2) Wage and Payroll Standards
(i) The contractor shall disclose in writing to each worker in a language common to the worker the full terms of their employment, including workers compensation information, at the time they are recruited or hired. The Department of Labor provides an optional form WH-516 for contractor's use in disclosure.
(ii) The contractor must keep the following payroll records for each employee: name, address, social security number, basis for wages (i.e. per hour, per tree, per acre), number of units earned if paid on a per unit basis, hours worked, total pay, withholdings and purpose for each, and net pay. Payroll records shall be retained for three years.
(iii) Payments must be made no less frequently than every two weeks or semi-monthly. At the time of each payment, the contractor shall provide to the employee a written itemization of the information listed above and which shall include the employer's tax identification number.
(iv) If paid on a piece rate basis, the employee's wage must be at least equivalent to the required hourly wage for the hours worked, including overtime differential for time in excess of 40 hours per week.
(3) Motor Vehicle Safety
(i) The contractor must be registered to transport employees, unless employees provide their own transportation or carpool by their own arrangement in one of their own vehicles. The authorization to transport employees must appear on the contractor's certificate. If the contractor directs or requests employees to carpool, the registration requirement is still applicable. Any driver who transports workers for a fee or at the direction of the contractor must be registered as a farm labor contractor or a farm labor contractor employee.
(ii) Any vehicle under the ownership or control of the contractor shall comply with safety standards applicable to that vehicle. Generally passenger vehicles or station wagons must comply with Department of Labor regulations at 29 CFR 500.104. Vehicles other than passenger vehicles or station wagons which are driven more than 75 miles must comply with Department of Transportation Regulations at 29 CFR 500.105. All drivers must have a current, valid State driver’s license.
(iii) Each vehicle under the ownership or control of the contractor which is used to transport any migrant or seasonal agricultural worker shall be covered by vehicle insurance of $100,000 per seat (maximum $5,000,000). A workers compensation policy which covers the workers while being transported plus an additional property damage policy for $50,000 for loss or damage in any one accident to the property of others may be substituted for the vehicle insurance requirement.
(4) Housing
(i) The contractor shall house workers only in a commercial establishment or a facility that has been certified by a health authority or other appropriate agency. The contractor must post the certificate of occupancy at the housing site.
(ii) The authorization to furnish housing, other than commercial lodging, must appear on the contractor's certificate.
(iii) If the contractor is not furnishing worker housing:
Workers on this contract may obtain housing only in a residential accommodation, including a commercial establishment such as a hotel or motel, which meets all applicable state and federal standards for employee housing.
Within 10 days after award, and prior to the issuance of Notice to Proceed, the contractor must notify the Contracting Officer of the planned worker housing site.
If the housing site is located on a National Forest, the Contractor must obtain a permit from the District Ranger for the District on which the housing site is located and the facilities established for the workers must meet the applicable U.S. Department of Labor (USDOL) MSPA standards for such sites.
If the housing site is not located on a National Forest, the site must meet the applicable housing standards in MSPA.
If an exemption from the permit requirement is claimed, the contractor must provide a written statement identifying the law authorizing the exemption, stating the facts constituting an exemption under that law, and identifying a USDOL employee or official who stated or concurred that the accommodations were exempt, citing name, date, and means of communication.
If the housing site is changed after approval by the Contracting Officer, the contractor must provide a new Permit or exemption statement. The above requirements are material conditions of this contract. If the contractor fails to comply, the Government may terminate the contract. In addition, other remedies or penalties prescribed by law may apply
Field Sanitation
In accordance with US Department of Labor Fact Sheet No. ESA 97-28 “Field Sanitation Standards” (Ref. 29CFR 1928.110), employers must provide:
· Potable drinking water, suitably cool and in sufficient amounts, dispensed in single-use cups or by fountains, located so as to be readily accessible to employees.
· Facilities maintained in accordance with public health sanitation practices include upkeep of water quality through daily change or more often if necessary.
· Notification to each employee of the location of the water and allowance of reasonable opportunities during the workday to use them. The employer also must inform the employee of the relevant health hazards in the field and the practices necessary to minimize them.
Employees cannot be made to bear the costs incurred by the employer for providing required facilities.
(e) For further information on the requirements of the Act, contractors should contact their local Wage and Hour Division of the Department of Labor.
24.
FSAR 4G52.222-703 MIGRANT AND SEASONAL AGRICULTURAL WORKER PROTECTION ACT REGISTRATION (DEC 1999) The Migrant and Seasonal Agricultural Worker Protection Act (MSPA) (29 U.S.C. 1801-1872) and implementing regulations issued by the Department of Labor (29 CFR 500), require any employer who hires or anticipates hiring employees subject to MSPA to obtain an MSPA registration number.
If the contractor employs or anticipates hiring employees subject to MSPA, the contractor shall provide a valid U.S. Department of Labor MSPA Registration Number to the Contracting Officer within 10 days after notification of award of the contract.
The Government may demand that the contractor display MSPA registration at any time during contract performance if it appears that the contractor is employing workers subject to MSPA. On demand, the contractor shall display its MSPA registration or state why it is exempt from MSPA.
Compliance with MSPA is a material condition of the contract. If the contractor fails to provide a valid MSPA number in accordance with this clause, or falsely states that it is exempt from the MSPA, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.
25.
PROTECTION MEASURES NEEDED FOR PLANTS, ANIMALS, CULTURAL RESOURCES, AND CAVE RESOURCES
Locations of known areas needing special measures for the protection of plants, animals, cultural resources, and/or cave resources are shown on Contract Area Map and/or identified on the ground. Special protection measures needed to protect such known areas are identified.
In addition to any special protection measures noted, Contractor has…