Sheet1
| attach 4b | RFI Summary: Due 1st and 15th of each month: | Date: 06 MAR 2013 | Green Cost | Yellow Open | Red Critical Notes: | CO Notes | COR Response | ||
| RFI Number | Title | Date Created | No Response as of: | Response-Open-working | cost Y/N | Date Closed | @ = See RFI Files/Resolved | @ = See RFI Files/Resolved | |
| 1 | Electrical Clarification | 16-Nov-12 | change panel | N | 4-Dec-12 | @ | @ | @ | |
| 2 | Bay #3 | 19-Nov-12 | "see response to RFI#5"- proceed as original design | N | 29-Nov-12 | @ | @ | @ | |
| 3 | Bay #1 - Water | 20-Nov-12 | line and valve to be replaced | N | 29-Nov-12 | @ | @ | @ | |
| 4 | Bay #3 | 20-Nov-12 | remove superstructure as per contract | N | 29-Nov-12 | @ | @ | @ | |
| 5 | Carbon Monoxide Units | 20-Nov-12 | remove and demo CO2 producers | N | 29-Nov-12 | @ | @ | @ | |
| 11 - 11a | Electrical upgrade panel | 9-Dec-12 | * 3/6/2013 | clarification- see 11A | Y | * | |||
| 12 | Electrical | 22-Jan-13 | clarification on receptacle height | N | 23-Jan-13 | @ | @ | @ |
Sheet2