Questions-Answers 2.docx

DOCX document 11 KB Posted

Attached to
Rampart Range Road Maintenance
Solicitation number
AG-82BH-S-11-0019
Issued by

About this file

Questions and answers

View the file

Other files

File Type Posted
Questions and Answers.docx DOCX document
Amendment 000001.pdf PDF
Rampart Range roads maintenance.doc DOC document
Attachment I.doc DOC document
SF 33.pdf PDF
Attachment II.pdf PDF
Attachment III.docx DOCX document
Rampart Range Road Mainenance Package.doc DOC document
Attachment IV.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

AG-82BH-S-11-0019

Rampart Range Roads Maintenance

1. For past performance in the technical proposal section, do projects of the subcontractors count towards past performance projects allowed to be submitted? Only work done by your company done as the prime or subcontractor can be considered as past performance.

2. If a wash area washes out again after repair, is the contractor responsible to repair it again? Is there a warranty period for the repairs? If the road has been inspected and accepted then they won't have to rework it but if it hasn't been accepted then it still the contractor’s responsibility.

3. I don't see any requirement for insurance or bonding to be submitted with the proposal. Is any required with the proposal? Or am I just not referencing the correct supplemental information? Bonding or Insurance requirements are required for construction projects and this solicitation is for a service.