Lolo ARRA summary section 01010_merged.pdf
PDF 85 KB Posted
- Attached to
- Lolo Forestwide Exterior Painting
- Solicitation number
- AG-82B1-S-10-0293
About this file
AG-82B1-S-10-0293 Lolo ARRA summary section 01010_merged
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG-82B1-S-10-0293 Pre bid Q A Lolo paint.pdf | ||
| AG-82B1-S-10-0293 SF 30.pdf | ||
| AG-82B1-S-10-0293 solicitation_coversheet.pdf | ||
| AG-82B1-S-10-0293 Body.pdf | ||
| CompiledSchedules.xlsx | XLSX spreadsheet | |
| AG-82B1-S-10-0293 SF 1442.pdf | ||
| AG-82B1-S-10-0293 Drawings.pdf | ||
| AG-82B1-S-10-0293 Expierence Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01010 - 1
SUMMARY OF WORK
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
Work for this project consists of providing all labor and materials for performing exterior maintenance painting work on approximately 72 buildings at six Lolo National Forest administrative sites. Many buildings identified are either eligible or listed on the National
Register of Historic Places. The work to be done on most buildings will also include lead paint mitigation measures as required for painting surface preparation to be done in compliance with all related safety and environmental regulations.
A. Lead management and safety plan Requirments referencence specification section
02094.
1.2 LOCATION
Sites included are located from approximately 30 minutes to two hours driving time from
Missoula MT. Project sites are located at several sites on the Lolo National Forest in western
Montana. Sites include Ninemile Ranger Station approximately 20mi. west of Missoula MT, Seeley Lake Ranger Station near Seeley Lake MT, Plains Ranger Station, Plains MT, St. Regis
Work Center near St. Regis MT and Savenac Tree Nursery near Haugan MT. Individual building locations for each site are indicated on the Site Plan Drawings and are listed in the Contract
Schedule
Projects Sites Include:
Fort Missoula, Missoula County
Ninemile Ranger Station, Missoula County
Plains Ranger Station, Sanders County
Seeley Lake Ranger Station, Missoula County
Superior Ranger Station, Mineral County
Savenac Tree Nursery, Mineral County
St Regis Work Center, Mineral County
1.3 SITE CONDITIONS
A. All buildings are located on developed Forest Service Administrative sites. Buildings are occupied or otherwise in service according to the buildings use.
B. Work will need to be coordinated to allow continuous use of the facilities. The government will allow short term restrictions in use of entrances use, necessary
01010 - 2 rerouting of access routes, closure of walkways or measures necessary to control access to work areas.
C. Power and water is available at all sites.
D. Dumpsters and trash cans serving site shall not be used by contractor or for any construction debris. All waste shall be disposed of at approved offsite facilities.
E. Contractor shall provide sanitary facilities for workers.
1.4 HISTORICAL PRESERVATION CONSIDERATIONS.
A. Historical Preservation considerations will take precedence in materials and methods used in the execution of this work even if in some instances the contact schedules and specifications may differ from common general industry practices or methods allowed by product manufacturer. Manufactures guidelines shall apply except where there is a specific limitation made by the contract schedules or specifications.
B. The entire Ninemile and Savenac Administrative sites including building are listed on the National Register of Historic Places. No changes or alteration of any part of the site may occur without the written permission of the contraction officer.
C. The Superior, St Regis, Plains and Seeley Lake sites all contain a mix of listed, eligible or not eligible buildings. Consult with the COR for the status of particular building. Listed or eligible buildings may not be altered without written permission of the Contracting Officer.
1.5 USE OF PREMISES
A. General: Contractor shall not have use of interior areas of any buildings for any purpose except if required for monitoring purposes.
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees.
C. Confine storage of materials to areas as approved by the CO. Contractor and contractor’s employees shall park in areas as approved by COR.
D. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
E. Preservation of natural and Landscape features: Confines all operations to work limits of the project. Prevent damage to landscaped and natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
01010 - 3
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with CO to remove or mitigate vegetation, plantings or branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Maintain required lead removal controls to avoid contamination of lawns, vegetation or landscape plants.
5. Do not drive over lawns or undisturbed natural areas.
F. Existing Utilities: The scope of the work included in this project is not expected to affect or interfere with utility service.
1. Normal utility features are present at sites and it is the contractors’ responsibility to avoid damage to features. Typical features may include:
a. Overhead lines that may be present serving buildings and around buildings.
b. Gas meters and gas lines entering buildings.
c. Water meter boxes and valve boxes may be present around buildings.
2. Interruption of Existing Utility Service: Notify CO, 72 hours in advance if it appears any interruption of existing utilities is required.
1.6 CONSTRUCTION SEQUENCE
A. The contractor is required to submit a detailed schedule indicating the work sequence for this project. The schedule should include start work dates, task description and expected durations for each site and building. Schedules are required to be updated promptly if schedule dates are not met or other schedule changes become necessary.
B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
1.7 FIELD VERIFICATION
A. Field verifies existing conditions affecting the work of this contract before submitting schedules or ordering products.
1.8 PERMITS
A. Any permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 01100
SECTION 02094
WORK INVOLVING LEAD-BASED PAINT (LBP)
PART 1 - GENERAL
1.01 DESCRIPTION OF WORK:
Presence of Lead-Contaminated Paint:
All buildings of this project may contain lead-based paint on the exterior surfaces.
Work required to prepare the existing surfaces for painting may disturb lead-contaminated paint.
Work under this section includes those engineering controls which are necessary for surface preparation of materials to be resurfaced or for demolition/removal of materials that are coated with lead based paint
(LBP). This is a notification that the work under this contract will bring the Contractor into contact with LBP materials that will require worker and environmental protection.
1.02 NOTICE OF HAZARD:
A. The Government has determined that work under this contract will involve exposure to lead-based paint (LBP). Paint removed from Historically
Listed or Eligible buildings on past projects at Forest Service Sites have typically been found to contain lead. Any building built before 1987 should be assumed to contain lead paint unless tests indicate otherwise.
B. Exposure to airborne lead contaminants is a recognized hazard to human health. The Contractor shall assume that all painted surfaces on which work is required are coated with LBP.
1.03 SUBMITTALS:
A. Health and Safety Plan:
1. The Contractor shall provide a Health and Safety Plan for review and acceptance by the Contracting Officer. No work will commence until acceptance of the plan by the Contracting Officer.
a. The Health and Safety Plan will address, but not be limited to, the health-related standards and protective measures proposed to be utilized by the Contractor during work involving exposure to airborne lead contaminants. This plan will address compliance with OSHA 29
CFR 1926.62, Lead Exposure in Construction; EPA 40 CFR Part 745, Lead Renovation, Repair and Painting Rule; and EPA 40 CFR Part 261
Identification and Listing of Hazardous Wastes.
b. The Health and Safety Plan will also identify the engineering and work practice controls proposed to be implemented by the Contractor. Such controls will be identified to assure the Government that there will be no release to the environment of lead contamination for which liability may be imposed on the Government.
B. Proof of Contractor’s previous experience and qualifications meeting required
EPA standards. For work on identified target housing or child-occupied facilities, proof of EPA firm certification and renovator certification (Lead Renovation, Repair and Painting Rule).
C. Proof of training of Contractor’s employees for lead-related construction work.
D. Hazardous Waste Management Plan.
E. Hazardous Waste Disposal Plan.
F. Hazardous Waste Manifest.
1.04 WORKER PROTECTION:
A. OSHA requirements for worker protection shall be followed in accordance with 29 CFR 1926.62, Lead Exposure in Construction.
1.05 WASTE ANALYSIS AND MANAGEMENT:
A. The Contractor will be responsible for representative sampling and analysis of waste generated from work occurring on non-target housing. Waste meeting the hazard standards of 40 CFR 261 shall be disposed of in an approved and licensed TSD facility.
B. The Contractor shall segregate waste generated from Target Housing and non
Target Housing structures. Target Housing waste may be disposed of at an approved conventional waste facility, but in compliance with waste disposal requirements of the Lead Renovation, Repair and Painting Rule.
C. Paint debris shall not be placed on unprotected ground and shall be shielded adequately to prevent dispersion by wind or rainwater.
PART 2 - PRODUCTS
2.01 MATERIALS:
A. Disposal bags and sheeting: Provide 6 mil thick plastic disposal bags and sheeting for wrapping hazardous waste.
B. Disposal bins: Provide disposal bins for collection of non-hazardous and hazardous waste prior to disposal by Contractor.
All bins shall be secured when not in use to prevent deposit of unauthorized waste and debris.
C. Trisodium phosphate: Industry standard to mix with water for washing solutions on site.
PART 3 - EXECUTION
3.01 SITE PREPARATION:
A. The Contractor shall prepare the site in accordance with the Health and Safety Plan accepted by the Contracting Officer.
B. The Contractor is responsible for establishing and maintaining control measures sufficient to preclude any adverse affects to workers, Forest
Service personnel and dependents, the public, and the environment.
3.02 REPAIR
A. Structural repairs are not included in the scope of this project. Removal and reinstallation of items such as downspouts, rain gutters and shutters are required in some locations. The Contractor shall include consideration of the handling of these incidental items in the Health and Safety Plan accepted by the Contracting Officer.
B. All waste from incidental repair or component removal and replacements shall be handled in accordance with the provisions of this section 02094 and the directions of the
Contracting Officer.
3.03 CLEANUP:
A. Daily cleanup shall be in accordance with the Health and Safety Plan accepted by the Contracting Officer. Any environmental cleanup caused by Contractor's failure to comply with the provisions of law, of this contract, or the accepted Health and Safety Plan shall be at
Contractor's sole expense.
B. Do not allow any paint debris to enter industrial waste, storm drain or sanitary sewer lines.
3.04 LEAD-CONTAMINATED WASTE: The Contractor shall, at his own cost, comply with all laws, ordinances, rules, and regulations of federal, state, regional and local authorities regarding the handling, storing and disposal of lead waste material.
A. Lead-Based Paint/ Lead-Containing Paint Management Plan: Contractor shall submit a Lead-Based Paint Management Plan to the Contracting Officer ten (10) days prior to the start of any work involving disturbance of lead-contaminated paint.
B. Hazardous Waste Management Plan: Contractor shall submit a Hazardous
Waste Management Plan to Contracting Officer ten (10) days prior to the start of any work involving the disturbance of lead-contaminated paint. The Waste Management Plan shall include designation of the disposal facility to be used.
C. Hazardous Waste Manifest: The Contractor shall submit a Hazardous
Waste Manifest completed and signed by the treatment or disposal facility which receives any lead-contaminated paint or waste from this project. The waste manifest may only be signed by qualified individuals with DOT certification. The manifest shall be submitted to the Contracting Officer at the completion of the project.
3.05 PERMITS, NOTIFICATIONS AND APPROVALS
A. The Contractor shall be responsible for securing all necessary permits, applications, and the like, for work involving lead-contaminated paint and wastes, including hauling, removal, disposal, fire, materials usage, or any other required permits.
The Contractor shall pay for the costs of all such permits and applications.
3.06 INSPECTION:
Contractor shall cooperate and coordinate all work with the
Contracting Officer's inspection requirements. Inspection will center on compliance with the Health and Safety Plan accepted by the
Contracting Officer.
3.07 CLEARANCE:
A. Contractor shall notify Contracting Officer of readiness for final inspection. For work on Target Housing or child-occupied facilities, clearance will proceed per the Lead Renovation, Repair and Painting rule.
B. The visual inspection will occur no earlier than 24 hours after completion of the entire construction work.
C. Any visible debris will result in the Contractor re-cleaning the area at no additional cost to the Government.
END OF SECTION
LOLO REPAIRS 2010 07900-1
SEALANT/CAULKING
SECTION 07900
PART 1 GENERAL
1 .1 DESCRIPTION
A. The work of this section consists of furnishing and installing sealant, or caulking, to act as a barrier against air, water, moisture, dirt, or insects, and where needed for appearance.
1 .2 SUBMITTALS
A. Manufacturer's technical data and application instructions.
1 .3 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials in manufacturer's original, unopened containers and store in a protected area at temperatures recommended by manufacturer.
1 .4 ENVIRONMENTAL CONDITIONS
A. Install sealant/caulking in accordance with the manufacturer’s specifications.
PART 2 PRODUCTS
2 .1 APPROVED MANUFACTURERS
A. Other manufacturer's products may be used provided they are approved as equal.
1. Benjamin Moore & Company, Montvale, NJ.
2 .2 EXTERIOR SEALANT/CAULKING
A. Vertical Surfaces: Silicone or Urethane. ASTM C920-87, Type S, Grade NS, Class 25, Use M, A, or O, as applicable.
B. Horizontal Surfaces in Traffic Areas: Urethane. ASTM C920-87, Type S or M, Grade P, Class 25, Use T. Grade NS, Use T, in areas with slopes exceeding 1 percent.
PART 3 EXECUTION
3 .1 INSTALLATION OF SEALANT/CAULKING
A. Follow manufacturer's instructions for installation of sealant/caulking.
LOLO REPAIRS 2010 07900-2
B. Seal all cracks and joints up to 3/16” wide. Notify CO and allow time for US
National Forest Service (NFS) crew to make repairs on cracks and joints wider than 3/16”.
C. Do not apply sealant/caulking at window casings set into brick walls.
LOLO REPAIRS 2010 09900-1
PAINTING
SECTION 09900
PART 1 GENERAL
1 .1 DESCRIPTION
A. The work of this section consists of preparation and painting the exterior of buildings at
Administrative sites located on the Lolo National Forest. The exterior finishes of these structures have reached the end of their life cycle and now require attention to conventional and historic detailing including exterior paint finishes, color, craftsmanship, historic profiles, character, and brushwork.
B. Painting work shall include preparation of surfaces to provide a smooth surface for painting, application of wood preservative, application of a three-coat paint system and associated clean up. Application shall be by using a traditional brush application or spray where specifically allowed on buildings not having historical eligibility. Refer to finish and detail schedules for requirements of each building. Surfaces may be rolled if immediately brushed while paint is wet. Where specified the work shall include preparation of surfaces for the application of a two coat stain system and associated clean
up. Excluding window sash work on specified buildings, all painted and stained surfaces are to be repainted including exterior siding and trim, doors and window trim, exterior stairs, porches, decks and exposed wood roof members and eves. See the Finish schedule for details. All application processes must be in accordance with the manufacturer’s recommendations.
1 .2 RELATED WORK
A. Structural Modifications: The Contractor shall be responsible for advising the CO about any structural modifications that would reduce water infiltration into the structure of the structures. The contracting officer will determine the feasibility of making such modifications within the constraints of contract and negotiate if necessary for time for
NFS crew to make required modifications. The Contractor is not authorized to make structural modifications as part of this contract.
1 .3 SUBMITTALS
A. The Contractor shall submit for review and approval a complete list of proposed materials to be used on this project, including
1. Manufacturer’s Technical Information. Provide Material Safety Data Sheets
(MSDS) for all materials used on the project.
2. Provide paint label analysis and application instructions.
3. A complete list of materials proposed to be provided for the work.
LOLO REPAIRS 2010 09900-2
4. Color samples for all paint and stain products to be used.
5. Material data and manufacturer's certificate of performance for any proposed substitution for approved equal.
B. The Contractor shall submit for review a minimum of one test panel area on one building at each site. All test panels shall demonstrate the complete surface preparation process used to achieve a smooth and paintable surface including the application of all finish products. Test panels shall be a minimum of (two square feet) in size. The Contracting
Officer will select the building and the location of each test panel.
1 .4 PROJECT CONDITIONS
A. Apply water-based paints only when the temperature of the surfaces to be painted and the surrounding air temperatures are in accordance with manufacturer’s recommendations.
B. Apply solvent thinned paints only when temperature of surfaces to be painted and the surrounding air temperatures are in accordance with manufacturer’s recommendations.
C. Do not apply paint in rain, fog, or mist. Do not apply paint to damp or wet surfaces. Do not apply paint when relative humidity exceeds 85 percent. Do not apply paint unless the surface and or substrate has a moisture content is below 18 percent. Measure moisture content of surfaces using a Protimeter or moisture meter
D. Do not apply paint on surfaces in direct sunlight. Apply finishes only when air is free of dust that would speck the finish.
E. Keep fire hazard to a minimum; remove all oily rags, waste, and other combustibles not in covered metal containers from the area daily.
1 .5 EXTRA STOCK
A. Upon completion of the work of this Section, deliver to the NFS an extra stock equaling one gallon of each color, type, and gloss of paint used in the Work, in new, unopened containers, and clearly labeling with contents and location where used.
PART 2 PRODUCTS
2 .1 PRODUCT COMPATIBILITY
A. Contractor shall ensure compatibility of primers and other undercoat products, with the finish coats.
2 .2 WOOD PRESERVATIVES
A. MANUFACTURER: Benjamin Moore Paints, Benjamin Moore and Co. Montvale, NJ
07645. Or approved equal.
LOLO REPAIRS 2010 09900-3
B. PRODUCT: Moorwood Penetrating Clear Wood Finish & Preservative 088, phenolic, linseed, castor-tung resin. Or approved equal.
2 .3 PATCHING COMPOUNDS
A. MANUFACTURER: Benjamin Moore Paints, Benjamin Moore and Co. Montvale, NJ
07645. Or approved equal.
B. PRODUCT: Benjamin Moore Moorlastic 40 year Siliconized Caulk 467 (non-shrink). Or approved equal.
C. PRODUCT: Painter’s Putty (non-shrink).
2 .4 PAINT AND STAIN PRODUCTS
A. QUALITY ASSURANCE: Provide primers and other undercoat paint products by same manufacturer as finish coats. Paint and Stain products shall be fresh and well ground;
shall not settle readily, cake, or thicken in the container; shall be broken up readily with paddle to a smooth consistency; and shall have easy application properties. Other materials such as linseed oil, turpentine, mineral spirits, miscellaneous thinners, shall be the highest quality.
B. MANUFACTURER: Benjamin Moore Paints, Benjamin Moore and Co. Montvale, NJ
07645. Or approved equal.
C. PRODUCT: Moorwhite Primer 100 long-oil, alkyd based fast drying pigmented primer as a comprehensive exterior priming coat on unpainted wood, and previously painted weathered surfaces, painted surfaces, wood filler and hardener, sealant/caulking, and patching compounds. Or approved equal.
D. PRODUCT: MoorLife, Latex House Paint 105, premium, alkyd-modified, vinyl-acrylic latex flat paint, and matte finish as a comprehensive exterior first and second finish coat.
Or approved equal.
E. PRODUCT: Benjamin Moore Latex Floor and Patio Enamel 122, premium quality, quick-drying, epoxy-modified acrylic latex floor enamel for porch floors and stairs. Or approved equal.
F. PRODUCT: Benjamin Moore Retard-X Rust Inhibitive Latex Primer 162, for ferrous metals. Or approved equal.
G. PRODUCT: Benjamin Moore Alkyd Solid Stain C080, premium quality semi solid flat stain as a comprehensive exterior first and second coat. Or approved equal.
H. PRODUCT: Benjamin Moore Alkyd Solid Stain 329/C329, premium quality semi solid flat stain as a comprehensive exterior first and second coat. Or approved equal. (Wood
Roof shingles only).
I. PRODUCT: Benjamin Moore Premium Exterior Stain Alkyd Clear Wood Finish N076, premium quality clear wood finish as a comprehensive exterior first and second coat. Or approved equal.
LOLO REPAIRS 2010 09900-4
PART 3 EXECUTION
3 .1 GENERAL
A. Presence of Lead-Contaminated Paint: Work required to prepare the existing surfaces for painting may disturb lead-contaminated paint. Therefore the contractor shall ensure that work done under this contract complies with all applicable codes, laws, regulations, and ordinances relating to lead-contaminated paint.
1. As specified in section 01010
B. Cover and protect finished work and surfaces not to be painted including but not limited to sidewalks, trees, and plantings. Use drop cloths of a dimension to protect all areas around the structure measuring from the foundation line at grade to a minimum of twenty
(20) feet out from the structure. Without attaching to the building, properly fasten the protective measures to reduce windblow. Include protection for adjacent areas including plantings, grass, sidewalks, roadway, roof shingles, metal roofs, and trees. Protect trees including root system, trunk, and canopy.
C. Mix and prepare paint and stain materials in accordance with manufacturer's directions.
D. Where project work involves historic hardware, hardware fasteners, hardware accessories, machined surfaces, plates, lighting fixtures, and similar items not to be painted, the
Contractor shall either provide surface applied protection, remove and reinstall or carefully cut in according to industry standards. Retain all removed hardware on the job site in a secured area approved by the contracting officer. Reinstall removed items using original or equivalent fasteners and according to industry standards when Contracting
Officer has approved of the final coat.
E. Do not paint over dirt, rust, scale, grease, moisture, voids and blemishes, or other conditions detrimental to formation of a durable paint film.
3 .2 PREPARATION OF EXTERIOR WOOD SURFACES FOR PAINTING AND
STAINING
A. The Contractor shall provide a minimum of one test panel area on a building at each site.
All test panels shall demonstrate the complete surface preparation process used to achieve a smooth and paintable surface. Test panels shall be a minimum of (two square feet) in size. The Contracting Officer will select the building and the location of each test panel and determine if the completed panel is acceptable. The Contracting Officer shall be notified 48 hours prior to performing any test panels and shall be present during the execution of all test panels. The Contractor shall get the written approval of the panel from the COR prior to starting any further work. The Contacting Officer may determine that certain circumstances or site conditions may require more the one test panel.
B. Prepare all surfaces to receive prime coat, and subsequent finish coats of paint, through cleaning, and removal of paint that is not firmly adhered to wood substrate.
C. Remove all mildew and chalking prior to the application of primer coat of paint.
LOLO REPAIRS 2010 09900-5
D. Remove all dirt, scale, and organic matter prior to the application of primer coat of paint.
Utilize hand-brushing with a mild detergent solution. Rinse thoroughly with a low-pressure (less than 50 psi) clean-water rinse, protecting interiors from overspray, inundation, and deluge. Contain runoff and rinse water for proper disposal as per OSHA regulations, including 29CFR 1926.62.
E. Remove grease and oil by washing with mineral spirits or other solvent.
F. Remove sap on wood surfaces by scraping and washing with turpentine.
G. Seal all knots or resinous areas, and areas exhibiting bleeding of stains, with primer and allow to dry at least 2 hours before priming.
H. Set all loose nails, prime rusty nail heads with rust-inhibitive primer fill holes with patching compound, and spot prime.
I. Painted surfaces in good condition with good adhesion to wood substrate shall be lightly sanded by hand to ensure proper adhesion of primer coat and subsequent finish coats of paint.
J. Remove areas of paint exhibiting crazing, inter coat peeling, solvent blistering, wrinkling, peeling, cracking and alligatoring of existing paint to a sound substrate. Allow for a smooth and even transition from treated area to adjacent untreated areas.
K. Painted areas sanded or scraped to bare wood, without altering the original profile of the substrate, are to be treated with wood preservative, installed in accordance with manufacturer’s recommendations, prior to spot priming.
L. Remove dust, lint, and other foreign substances from surfaces to be painted, in accordance with paint manufacturer’s recommendations, prior to the application of primer coat of paint.
M. Prepare all surfaces to receive one base coat and one subsequent finish top coat of paint or stain, through cleaning, and removal of paint or stain that is not firmly adhered to wood substrate. All wood roof shingles are to be pressure washed to remove all existing loose paint/stain, mildew, dirt or other conditions detrimental to formulation of a durable stain film. The Contractor shall use caution during pressure washing to insure that the techniques and pressure used will not gouge or otherwise damage the substrate.
N. Remove all mold/mildew and chalking prior to the application of first coat of stain. Treat all previously mold/mildew areas with a mild solution of water and bleach. Rinse thoroughly with a low-pressure (less than 50 psi) clean-water rinse, protecting interiors from overspray, inundation, and deluge. Contain runoff and rinse water for proper disposal as per OSHA regulations, including 29CFR 1926.62.
3 .3 PREPARATION OF EXTERIOR FERROUS and NON-FERROUS METALS
A. Clean ferrous surfaces that are not galvanized or shop coated of oil, grease, dirt, loose mill scale, and other foreign substances by solvent or mechanical cleaning.
LOLO REPAIRS 2010 09900-6
B. Touch up shop-applied prime coats wherever damaged or bare.
C. Clean metal surfaces free of oil and surface contaminants with non-petroleum based solvent.
D. Remove all removable Rain Gutters and Downspouts from structure prior to building surface preparation and painting. Clean, prep, paint and re-install all Rain Gutters and
Downspouts in original locations with original hardware where feasible. All seamless aluminum gutters systems are to be cleaned, prepped, and painted in place.
E. Do not sand or scrap metal screens prior to painting.
3 .4 APPLICATION OF PAINT AND STAIN TO EXTERIOR WOOD SURFACES
A. Secure approval of Contracting Officer before applying overall primer and successive coats of paint.
B. Apply paint in accordance with manufacturer's directions. Utilize a natural fiber brush for applications of all coats of paint. Spraying will be permitted for specific products and specific building components. See the Finish schedule for details
C. Apply material evenly without runs, sags, or other defects. Leave moldings, trim, ornaments, edges, and millwork clean and true to details without excess paint in corners or depressions. Make edges of paint adjoining other materials or colors sharp and clean, without overlaps.
D. Apply materials at not less than manufacturer's recommended spreading rate, to establish a total dry film thickness as recommended by the manufacturer.
E. The manufacturer’s recommendations shall be followed for the minimum drying time.
Do not apply primer or succeeding coats until the substrate and/or undercoat is thoroughly dry. Utilize Protimeter or moisture meter to determine moisture content of dry substrate, primer, and successive coats.
F. Apply additional coats when undercoats, stains, or other conditions show through final coat of paint. Final finish shall have uniform finish, color, and appearance.
G. Finish designated exterior doors on tops, bottoms, and side edges same as exterior faces.
H. Finish designated exterior windows only on exposed surfaces. ** See finish schedule.
Refer any questions to CO.
3 .5 PAINTING EXTERIOR FERROUS and NON-FERROUS METALS
A. Apply paint in accordance with manufacturer's directions.
B. Secure approval of each coat from the Contracting Officer before proceeding with successive coats of paint.
C. Apply material evenly without runs, sags, or other defects. Make edges of paint adjoining other materials or colors sharp and clean, without overlaps.
LOLO REPAIRS 2010 09900-7
D. Apply materials at not less than manufacturer's recommended spreading rate, to establish a total dry film thickness as recommended by the manufacturer.
E. The manufacturer’s recommendations shall be followed for the minimum drying time.
Do not apply primer or succeeding coats until the substrate and/or undercoat is thoroughly dry.
F. Apply additional coats when undercoats, stains, or other conditions show through final coat of paint. Final finish shall have uniform finish, color, and appearance.
PART 4 EXTERIOR PAINT SYSTEMS
4.1 PAINT SYSTEMS
A. PAINT SYSTEM 1:
1. First coat: Moorwhite Primer 100, Premium, Alkyd/Oil, Exterior, or approved equal; Application: Hand Brush. Spraying will be permitted for specific products and specific building components. Refer to finish schedule for details.
2. Second coat: MoorLife Latex House Paint 105, Low Luster Exterior or approved equal, Application: Hand Brush. Spraying will be permitted for specific products and specific building components. Refer to finish schedule for details..
3. Third coat: MoorLife Latex House Paint 105, Low Luster Exterior or approved equal. Application: Hand Brush. Spraying will be permitted for specific products and specific building components. Refer to finish schedule for details.
B PAINT SYSTEM 2
First and Second coats: Moore’s Latex Floor and Patio Enamel 122, Satin, Exterior.
Application: Hand Brush. C PAINT SYSTEM 3
1. First coat: Retard-X Rust Inhibitive Latex Primer 162 or approved equal.
Application: Hand Brush.
2 Second coat: MoorLife Latex House Paint 105, Low Luster, Exterior. Application:
Hand Brush.
3 Third coat: MoorLife Latex House Paint 105, Low Luster, Exterior, or approved equal. Application: Hand Brush.
4.2 PAINT FINISH COLORS
A. Color tint Moorwhite Primer White with not to exceed 2.0 fl. Oz. Moor-o-matic colorants per gallon matching final coat. Tint the primer in according to the manufacturer’s recommendations.
B. Refer to finish schedule for details.
4.3 PAINT SCHEDULE
LOLO REPAIRS 2010 09900-8
A. WOOD SIDING, Painted Wood – Exterior: Utilize Paint System 1, Finish Color to match existing siding color. Refer to finish schedule for colors.
B. ARCHITECTURAL WOODWORK—GENERAL (Door and Window Casings, Columns and Pilasters, Stair Wing Walls, Skirting, Balustrades, Louvers) Painted Wood--Exterior:
Utilize Paint System 1, Refer to finish schedule for colors.
C. ARCHITECTURAL WOODWORK—PORCH CEILINGS, ROOF EAVES & RAFTER
TAILS, Painted Wood – Exterior: Utilize Paint System 1, Refer to finish schedule for colors.
D. WOOD DOORS AND DOOR FRAMES, Painted Wood – Exterior: Utilize Paint System
2, Refer to finish schedule for colors.
E. WOOD WINDOW SASH, WINDOW FRAME & SCREEN WINDOW SASH, Painted
Wood – Exterior: Utilize Paint System 1, Refer to finish schedule for colors.
F. WOOD FLOORING, THRESHOLDS, EXTERIOR STAIRS, Painted Wood – Exterior:
Utilize Paint System 2, Refer to finish schedule for colors.
PART 5 EXTERIOR STAIN SYSTEMS
5.1 STAIN SYSTEMS
A. STAIN SYSTEM 1
1. First coat: Moore 329/C329 Premium, Alkyd, Semi Solid Stain or approved equal. Spray applied. Second coat: Moore 329/C329 Premium, Alkyd, Semi Solid
Stain or approved equal. Spray applied.
5.2 STAIN FINISH COLORS
A Refer to finish schedule for colors.
5.3 STAIN SCHEDULE
A WOOD ROOF SHINGLES, Stained Wood- Exterior: Utilize Stain System 1, PART 6 CLEAN-UP
A. Upon approval of finish coat by the contracting officer implement clean-up procedures.
Remove all paint, stain, or other finish material where it has spilled or spattered.
B. Remove all overbrush, splatters, drips, and spills from associated architectural elements including window and door surrounds, window and door casings, window and door transoms, thresholds, associated floors, roof decks, wood shingles, metal roofs, ledges, and railings.
C. Remove all overbrush, splatters, drips, and spills from associated grounds, and plantings.
LOLO REPAIRS 2010 09900-9
D. Dispose of material and collected lead based paint chips, particles, and dust as per OSHA regulations, including 29CFR 1926.62, and all applicable federal, state and local regulations.