Appendix_D-2_L.Bvr_road_sps_ftp_12.21.09_a.pdf
PDF 363 KB Posted
- Attached to
- RECOVERY - Little Beaver Hazardous Fuels Reduction Project - Stewardship - Kootenai Nationjal Forest Montana
- Solicitation number
- AG-82B1-S-10-0040
About this file
Appendix D-2 Road Specs
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
109.02 Measurement Terms and Definitions
151 - Mobilization
151.01 Description
Appendix D-2
AG-82B1-S-10-0040
151.02 Measurement
155 - Schedules for Construction Contracts
155 Delete
201 - Clearing and Grubbing
201.01 Description
201.06 Disposal
203 - Removal of Structures and Obstructions
203.03 Salvaging Material
203.05 Disposing of Material
203.01 Description
203.04 Removing Material
203.05 Disposing of Material
204 - Excavation and Embankment
204.06 Roadway Excavation
204.11 Compaction
204.14 Disposal of Unsuitable or Excess Material
204.15 Acceptance
204.09 Preparing Foundation for Embankment Construction
204.10 Embankment Construction
204.13 Sloping, Shaping, and Finishing
Table 204-2 Construction tolerances
204.14 Disposal of Unsuitable or Excess Material
209 - Structure Excavation and Backfill
209.10 Backfill
209.11 Compacting
209.12 Acceptance
303 - Road Reconditioning
303.03 Ditch Reconditioning
303.04 Shoulder Reconditioning
303.05 Roadbed Reconditioning
303.07 Roadway Reconditioning
303.09 Acceptance
303.10 Measurement
303.06 Aggregate Surface Reconditioning
Appendix D-2
303.06 Asphalt and Aggregate Surface Reconditioning
303.07 Roadway Reconditioning
602 - Culverts and Drains
602.03 General
625 - Turf Establishment
625.03 General
625.04 Preparing Seedbed
625.05 Watering
625.06 Fertilizing
625.07 Seeding
625.08 Mulching
625.09 Protecting and Caring for Seeded Areas
625.11 Measurement
625.03 General
625.04 Preparing Seedbed
625.05 Watering
625.06 Fertilizing
625.07 Seeding
625.08 Mulching
625.09 Protecting and Caring for Seeded Areas
625.11 Measurement
625.07 Seeding
(c) Seeding Seasons
(d) Application Methods for Seed, Fertilizer & Limestone
625.08 Mulching
(c) Application of Mulch
718 - Traffic Signing and Marking Material
718.05 Aluminum Panels
Appendix D-2
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the
“purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal
Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale
Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition
Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges.
Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The
Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
Appendix D-2
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of
15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
109.02_0114_us_06_09_2008
109.02 Measurement Terms and Definitions.
Add the following definition:
(q) Actual quantity. (AQ) These quantities are determined from measurements of completed work.
151 - Mobilization
151.01_0114_us_08_04_2005
151.01 Description
This work consists of washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands.
Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.
Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.
Notify the CO in writing at least 24 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.
Use methods of cleaning and locations for cleaning approved by the C.O.
For work at a commercial washing facility, use an approved facility.
New infestations of noxious weeds of concern to Forest Service and identified by either
Contractor or Forest Service, on the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found.
A current list of noxious weeds of concern to Forest Service is available at each Forest
Service office.
151.02 Measurement
Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment under this item will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
201 - Clearing and Grubbing
201.01_nat_us_02_18_2005
201.01 Description
Replace with the following
This work consists of clearing and grubbing within clearing limits and other designated areas.
201.06_nat_us_02_18_2005
201.06 Disposal.
Delete the first sentence of this subsection and substitute the following:
Dispose of merchantable timber designated for removal according to the provisions of the timber sale contract.
203 - Removal of Structures and Obstructions
203.00_01_us_10_11_2006
203.03 Salvaging Material.
Delete this subsection and add the following:
Unless shown on the plans, remove all designated material from the project area and
National Forest land.
203.05 Disposing of Material.
(a) Remove from project.
Delete this paragraph and add the following:
All removed material may be salvaged by the Contractor unless otherwise shown on the plans. Dispose of all items not designated to be salvaged for the Government in any legal manner.
203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.04_nat_us_02_18_2005
203.04 Removing Material.
Replace the fourth and fifth paragraphs with the following:
Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.
Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation. Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.
203.05_nat_us_02_24_2005
Appendix D-2
203.05 Disposing of Material.
(e): Scattering. Scatter pieces of wood less than 3 inches in diameter and 3 feet in length within the clearing limits. Do not place construction slash in lakes, meadows, streams, or streambeds. Immediately remove construction slash that interferes with drainage structures.
204 - Excavation and Embankment
204.06_nat_us_03_02_2005
204.06 Roadway Excavation
(a) General.
Add the following:
Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.
204.06_0114_us_07_06_2005
204.06 Roadway Excavation
(d) Drainage Excavation. Drainage excavation includes construction of side ditches, minor channel changes, inlet and outlet ditches, furrow ditches, rolling drainage dips, surface water deflectors and other minor earth drainage structures as shown on the plans. Compaction for drainage excavation is as shown on the plans.
204.11 Compaction
Delete the first paragraph and replace it with the following:
For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d), (e), or (f) no sieve test is required.
Add the following compaction methods:
(d) Hauling and Spreading Equipment. Adjust the moisture content to a level suitable for compaction. Compact the material by operating equipment over the full width of the roadway.
(e) Roller Compaction. Adjust the moisture content to a level suitable for compaction.
Operate Rollers over the full width of each layer until visual displacement ceases, but not fewer than three complete passes. Use rollers that meet the following requirements:
(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch of width of the compression roll or rolls.
(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum weight of 6 tons, specifically designed to compact the material on which it is used.
(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi.
(4) Sheepsfoot, tamping, or grid rollers capable of exerting a force of 250 lbs/inch of width of roller drum.
(f) Mechanical Tamper. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each 6 inch layer with a minimum of three complete passes with a mechanical tamper, approved by the CO.
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites or legally off the project.
204.15 Acceptance
Delete the first paragraph.
204.09_nat_us_03_02_2005
204.09 Preparing Foundation for Embankment Construction.
Delete subsection (a) and replace it with the following:
(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying. Compact the ground surface according to Subsection 204.11.
204.10_nat_us_03_02_2005
204.10 Embankment Construction.
Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline.
(a) General.
Delete the third paragraph and add the following:
Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.
204.13_0114_us_03_21_2008
204.13 Sloping, Shaping, and Finishing.
Delete section (d) and add the following:
(d) Finishing. Finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace with suitable material. Finish roadbeds to the designated tolerance class as shown in table 204-
2.
Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
Use the designated methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Grid roller or approved equal according to Subsection 204.11 (e).
(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.
(4) Method D. Reduce in place or remove and dispose of rocks larger than 4 inches extending above the finished road surface.
Add Table 204-2—Construction Tolerances:
Table 204-2 Construction tolerances.
Tolerance Class (a)
A B C D E F G H I J K L M
Roadbed width (ft) +0.5 +0.5 +1.0 +1.0 +1.0 +1.0 +1.5 +1.0 +2.0 +2.0 +2.0 +2.0 +2.0
Subgrade elevation
(ft)
+0.1 +0.2 +0.2 +0.5 +0.5 +1.0 +1.0 +1.5 +2.0 +3.0 +2.0 +3.0 (c)
Centerline alignment
(ft)
+0.2 +0.2 +0.5 +0.5 +1.0 +1.0 `+1.5 +1.5 +2.0 +3.0 +3.0 +5.0 (c)
Slopes, excavation, and embankment (% slope(b)
+3 +5 +5 +5 +5 +5 +10 +10 +10 +10 +20 +20 +20
a. Maximum allowable deviation from construction stakes and drawings.
b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.
c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.
Appendix D-2
204.14_nat_us_03_02_2005
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites or legally off of the project.
209 - Structure Excavation and Backfill
209.10_nat_us_10_23_2007
209.10 Backfill.
(a) General.
Add the following:
Replace any pipe that is distorted by more than 5 percent of nominal dimensions, or that is ruptured or broken.
Do not place or backfill pipe that meets any of the following conditions until the excavation and foundation have been approved in writing by the CO:
• Embankment height greater than 6 feet at subgrade centerline.
• Installation in a protected streamcourse.
• Round pipe with a diameter of 48 inches or greater.
• Pipe arches with a span of 50 inches or greater.
• Any box culvert of structure other than pipe culverts.
(b) Pipe culverts.
(1) Pipe culverts with compacted backfill.
Add the following:
Excavate an area on each side of the pipe as needed to effectively achieve compaction requirements. Backfill without damaging or displacing the pipe. Complete backfilling of the trench with suitable material.
209.11_0114_us_02_15_2005
209.11 Compacting.
Delete the subsection and add the following:
Compact backfill using designated compaction method A, B, or C:
Method A. Ensure that backfill density exceeds the density of the surrounding embankment.
Method B. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each 6 inch layer with a minimum of three complete passes with a mechanical tamper, approved by the CO. For compaction under sections 252, 254, 255, 257, 258 and 262 compact with a vibratory steel wheeled roller with a mass of at least 8 tons.
Method C. Determine optimum moisture content and maximum density according to
AASHTO T 99 method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact material placed in all layers to at
Appendix D-2 least 95 percent of the maximum density. Determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
209.12 Acceptance
Compaction methods (A) and (B) do not require sampling and testing.
303 - Road Reconditioning
303.03_0114_us_08_04_2005
303.03 Ditch Reconditioning
Delete the last sentence and add the following:
Dispose of waste as shown on the plans.
303.04 Shoulder Reconditioning
Delete the last sentence and add the following:
Dispose of waste as shown on the plans.
303.05 Roadbed Reconditioning
Delete and add the following:
Repair soft and unstable areas according to Subsection 204.07. Remove all organic, deleterious material larger than 6 inches from the top 6 inches of subgrade. Dispose of waste as shown on the plans. Scarify and shape the traveled way and shoulders at locations and to the depth and width designated on the plans. Remove surface irregularities and shape to provide a uniform surface.
Dispose of rock larger than 4 inches brought to the surface during scarification in areas designated on the plans.
For portions of roads not requiring scarification, the roadbed may contain rocks larger than 4 inches provided they do not extend above the finished roadbed surface. Reduce in place or remove rock extending above the finished roadbed surface. Dispose of removed rock in areas designated on the plans.
Compact using the following method as specified:
(a) Compaction A. Operate equipment over the full width.
(b) Compaction B. Operate rollers over the full width of each layer until visual displacement ceases, but not fewer than three complete passes. Use rollers that meet the following requirements:
(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch of width of the compression roll or rolls.
(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum weight of 6 tons, specifically designed to compact the material on which it is used.
(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi.
303.07 Roadway Reconditioning
Blade and shape the subgrade for both surfaced and unsurfaced roads when moisture content is suitable for compaction.
303.09 Acceptance
Delete the first sentence.
Appendix D-2
303.10 Measurement
Delete the first sentence of the third paragraph and replace with:
Measure roadbed reconditioning, aggregate surface reconditioning, roadway reconditioning, and pulverizing by the mile, by the station, or by the square yard.
303.06_nat_us_08_05_2008
303.06 Aggregate Surface Reconditioning.
Delete and replace with the following:
303.06 Asphalt and Aggregate Surface Reconditioning.
Repair soft and unstable areas to the full depth of the aggregate surface and according to
Subsection 204.07. Scarify to the depth of the aggregate surface or to a depth of 6 inches, whichever is less, and remove surface irregularities. Reshape, finish, and compact the entire aggregate surface according to Subsection 301.05, Subsection 321.05, or
Subsection 322.05 as applicable.
For asphalt surfaces, clean the existing surface of all loose material, dirt, or other deleterious substances by approved methods. Remove and dispose of unsuitable material that shows evidence of distress, excess asphalt material, or settlement in the roadbed.
Patch the areas with approved material that conforms to and is compatible with the adjacent pavement structure. Perform the patch work according to Section 301, 404, 430, or other sections as applicable for the layer or courses being repaired. Clean and seal cracks in the existing asphalt surface according to Subsection 414.05. Correct surface irregularities exceeding 6 inches in depth with a specified aggregate. Place and compact the aggregate according to Subsections 301.04 and 301.05. Prelevel other dips, depressions, sags, excessive or nonexistent crown, or other surface irregularities with asphalt concrete according to Section 404. Spread and compact the asphalt concrete in layers parallel to the grade line not to exceed 2 inches in compacted depth.
Delete Table 303-1 and replace with the following:
303.07_nat_us_03_02_2005
T a b le
-1
S a m p li n g a n d
T es ti n g R eq u ir em en ts
R ep o rt in g im e
B ef o re u si n g i n w o rk
B ef o re p la ci ex t la y er
(1
M in im u m o f p o in ts p er p ro ct r.
p li t
S a m le
Y es w h re q u es te d
P in t o f
S a m p li
P ro ce ss ed m at er ia l b ef co rp o ra ti n g i rk
In -p la ce a m p li
F q u cy er e ac ix tu re o r ch an g e at er ia l p er y es t M et h o d s
S p ec if ic a ti o n s
A A
S H
T O
T
(1
R -1
M ar sh al l
A A
S H
T O
(1
R -1
M ar sh al l
A A
S H
T O
T r o th er a p p ro v ro ce d u re s
C a te g ry
C a ra ct er is ti c
M o is tu re -d en si ty
M et h o
D is tu re -d en h o
E is tu re -d en h o
F is tu re -d en h o
G
In -p la ce d en o is tu co te n t
T y p e o f
A cc ep ta
(S u b se ct io n
M ea su re d a te st fo r co n fo rm an
(1 .0
M a te ri a l o r
P ro d u ct
E x is ti n g R o ad ay
303.07 Roadway Reconditioning.
Remove cattleguard decks. Clean the deck and the area beneath the cattleguard of soil and other material to the bottom of the original foundation over the entire width of the installation. Reinstall the cattleguard deck.
602 - Culverts and Drains
602.03_0114_us_08_04_2005
602.03 General.
Delete second paragraph and add the following:
The lengths and locations of individual pipe “as shown on the plans” are approximate.
Do not order pipe until culvert locations are designated on the ground and a written list of the correct lengths is approved by the C.O.
625 - Turf Establishment
625.00_01_us_10_12_2006
625.03 General.
Delete this subsection and replace with the following:
Apply turf establishment to prepared ground between (Date1) and (Date2) or any disturbed area. Apply turf establishment to the areas shown on the drawings or in the worklists within XX days after completion of ground disturbing activities. For road construction activities, apply turf establishment after each XXXX foot section of road has been constructed to final grade, unless otherwise directed by the CO. Seeded areas damaged by construction activities shall be reseeded within 10 days of the damage.
Seed as soon as possible after constructed to template lines unless otherwise specified in writing by the CO. Do not seed during windy weather or when the ground is excessively wet, frozen, snow covered.
Assure that all seed and mulch used in the work conforms to the weed free requirements of Section 713.
625.04 Preparing Seedbed.
Delete entire subsection.
625.05 Watering
Delete entire subsection.
625.06 Fertilizing.
Delete entire section and replace with the following:
Apply fertilizer having a chemical analysis as listed below by the following methods.
(a) Dry Method. Apply the fertilizer with approved power driven seeders, drills, fertilizer spreaders or other mechanical equipment. Hand operated methods are satisfactory on areas inaccessible to mechanical equipment.
(b) Hydraulic method. Use hydraulic-type equipment capable of providing a uniform application using water as the carrying agent. Add fertilizer to the slurry and mix before adding seed.
Fertilizer. Apply fertilizer at the rate of XXXX pounds per acre. Insure that the fertilizer meets the following chemical analysis:
Appendix D-2
Nutrient Percent
Nitrogen, N . . . . . . . . . . . . . XXXXXX
Phosphorus, P205 . . . . . . . . . XXXXXX
Potassium, K . . . . . . . . . . . . . XXXXXX
625.07 Seeding.
Delete the first sentence and add the following.
Apply seed mix by the following methods.
(a) Dry method. Delete the third sentence.
Add the following after subsection (b).
Seed Mix. Furnish and apply the following kinds and amounts pure live seed:
Quantity of Pure
Kind of Seed Live Seed (Lbs/Acre)
1. ______________ ____________ ______________________
2. __________________________ _______________________
3. __________________________ _______________________
4. __________________________ _______________________
5. __________________________ ______________________
6. __________________________ _______________________
7. __________________________ _______________________
Total _____________________
Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.
Example 5 lbs. pure live seed/acre = 6.55 lbs. commercial
0.90 x 0.85 seed per acre; purity = 90% and germination = 85%
Appendix D-2
625.08 Mulching.
Delete the entire subsection and replace with the following:
Apply Mulch within XX hours after seeding by the following methods.
(a) Dry Method. Apply mulch with a hand / a spreader utilizing forced air at a rate of XXXX pounds per acre. Anchor the mulch with an approved stabilizing emulsion tackifier at a rate of N/A gallons per acre. Do not mark or deface structure, pavements, utilities, or plant growth with tackifier.
(b) Hydraulic Method. Apply mulch in a separate application from the seed using hydraulic-type equipment according to Subsection 625.07(b).
Apply wood fiber or grass straw cellulose fiber mulch at a rate of XXXX pounds per acre.
Apply bonded fiber matrix hydraulic mulch at a minimum rate of XXXX pounds per acre. Apply so no hole in the matrix is greater than 0.04 inches. Apply so that no gaps exist between the matrix and the soil.
Mulch areas inaccessible to mulching equipment by hand. Apply mulch uniformly over the entire disturbed area.
625.09 Protecting and Caring for Seeded Areas
Delete the first sentence and add the following:
Protect and care for seeded areas until final acceptance.
625.11 Measurement.
Delete the entire Subsection and replace with the following:
Measure the Section 625 items listed in the bid schedule according to Subsection 109.02.
625.00_0114_us_07_12_2007
625.03 General.
Delete the first sentence and add the following:
Apply turf establishment to portions of slopes, ditches, waste areas, and other disturbed areas within 14 days after being constructed to template lines unless otherwise specified in writing by the C.O..
Appendix D-2
625.04 Preparing Seedbed.
Delete the second sentence of the first paragraph.
Delete the third paragraph.
625.05 Watering
Delete the entire paragraph.
625.06 Fertilizing.
Delete the entire subsection and add the following.
Apply fertilizer having a chemical analysis as listed in (c) below by the following methods. Apply seed and fertilizer in one application.
(a) Dry Method. Apply the fertilizer with approved power driven seeders, drills, fertilizer spreaders or other mechanical equipment. Hand operated methods are satisfactory on areas inaccessible to mechanical equipment.
(b) Hydraulic method. Use hydraulic-type equipment capable of providing a uniform application using water as the carrying agent. Add fertilizer to the slurry and mix before adding seed.
(c) Chemical analysis. Apply fertilizer at the rate of 240 pounds per acre. Apply fertilizer having the following chemical analysis.
Nutrient Percent
Nitrogen, N 27
Phosphorus, P2O5 10
Potassium, K 10
Fertilizer having a different chemical analysis may be used if approved in advance by the CO.
625.07 Seeding.
Delete the first sentence and add the following.
Apply seed mix shown in (c) below by the following methods.
(a) Dry method.
Delete the third sentence.
Add the following after subsection (b).
(c) Seed Mix. In terms of pure live seed, furnish and apply the following kinds and amounts of seed. Obtain the pounds of seed to furnish per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.
Example: 5 lbs Pure Live Seed/Acre = 6.55 lbs Commercial Seed/Acre
0.90 X 0.85 (Purity = 90% and Germination = 85%)
Kind of Seed Quantity of Pure Live Seed
(Lbs/Acre)
1. Annual Rye 18
2. Hard Fescue 6
3. Orchard Grass 6
Total 30
625.08 Mulching.
(b) Hydraulic method.
Delete the first sentence and add the following.
Appendix D-2
Apply mulch in a separate application from the seed or in a single application with the seed using hydraulic-type equipment according to Subsection 625.07(b).
625.09 Protecting and Caring for Seeded Areas.
Delete the first sentence and add the following.
Protect and care for seeded areas until final acceptance.
625.11 Measurement
Delete the second paragraph and add the following.
Measure seeding, fertilizing, and mulching by the acre on the ground surface or by lump sum.
625.07_0114_us_12_21_2004
625.07 Seeding
(c) Seeding Seasons.
"Seed shall be placed on portions of road fill and/or back slopes, waste areas, and other disturbed areas that have been constructed to template lines within 5 days of the construction activity unless otherwise specified in writing by the CO."
(d) Application Methods for Seed, Fertilizer & Limestone.
"The kinds of seed to be furnished and the amounts to be applied in terms of pure live seed shall be as follows:
Kind of Seed Quantity of Pure Live Seed
(Lbs/Acre)
1. Annual Rye 12
2. Hard Fescue 6
3. Orchard Grass 6
4. Alsike Clover (Inoculated) 6
Total 30
Pounds of seed to be furnished per acre shall be obtained by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.
Example: 5 lbs Pure Live Seed/Acre = 6.55 lbs Commercial Seed Per Acre
0.90 x 0.85 (Purity = 90% and Germination = 85%)
Seed shall be applied by the Dry method. Fertilizer shall be applied at a rate of
* pounds per acre in 1 applications by the Dry method and have a chemical analysis as listed below:
Nutrient 1
Application
Percent nd
Application
Percent
Nitrogen, N 25 25
Phosphorus, P2O5 10 10
Appendix D-2
Potassium, K 10 10
* Note: 1
Fertilizer Application at 240 lbs/acre with seed. If a second application is specified, the rate shall be 200 lbs/acre the season following the application of seed.
Limestone shall be applied at a rate of N/A pounds per acre by the N/A method."
625.08 Mulching
(c) Application of Mulch.
The following is added:
"Mulch material shall be N/A and shall be applied at a rate of N/A pounds per acre.
Asphalt emulsion used as a tiedown or adhesive shall be applied at a rate of N/A gallons per acre.
Wood cellulose mulch shall be applied at a rate of N/A pounds per acre.
When mulch is required, it may/may not be applied in a one-step operation with the seed and fertilizer."
718 - Traffic Signing and Marking Material
718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM
B-449.