Amendment 2 - Adds to Appendix D-2 SPS for road construction/recon. in 203.05 Disposing of Material.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-82B1-S-10-0040 Amendment 2
| AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT |
| 1. CONTRACT ID CODE |
| PAGE OF PAGES |
| 1 |
| 2 |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NO. (If applicable) |
| TWO (02) |
| 01-11-2010 |
| 6. ISSUED BY |
| CODE |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
USDA – Forest Service Intermountain EROC
740 Simms St.
Golden, CO 80401-4720 USDA-Forest Service (Address Offers/ to this address) Idaho Montana Acquisition Zone (IMAT) 3815 Schreiber Way
Couer d’Alene, ID 83815
| 8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) |
| (X) |
| 9A. AMENDMENT OF SOLICITATION NO. |
FORMCHECKBOX
AG-82B1-S-10-0040 Recovery L.Bvr.
9B. DATED (SEE ITEM 11)
12.21.09
FORMCHECKBOX
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
| CODE |
| FACILITY CODE |
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FORMCHECKBOX
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers FORMCHECKBOX is extended, FORMCHECKBOX is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
| (X) |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN |
THE CONTRACT ORDER NO. IN ITEM 10A.
FORMCHECKBOX
FORMCHECKBOX
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
FORMCHECKBOX
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
FORMCHECKBOX
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor FORMCHECKBOX is not, FORMCHECKBOX is required to sign this document and return 1 copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
This amedment concerns Appendix D-2 Special Project Specications (SPS) for Road Construction/Recon.
Under 203 – Removal of Structures and Obstructions 203.05 Disposing of Material add to the existing (e): Scatering …the following: (f), (g), (h), (i), (j), (k), (l), and (m).
SEE ATTACHED PAGE.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
| William Standley |
(Signature of person authorized to sign)
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
| 30-105 |
| STANDARD FORM 30 (REV. 10-83) |
Prescribed by GSAFAR (48 CFR)
203.05 Disposing of Material.
Add the following:
(e): Scattering. Scatter pieces of wood less than 3 inches in diameter and 3 feet in length within the clearing limits. Do not place construction slash in lakes, meadows, streams, or streambeds. Immediately remove construction slash that interferes with drainage structures.
(Amendment 2 additions below)
(f) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.
(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:
1. Place windrow segments on contours, wrap in type I geotextile.
2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.
3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.
4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.
Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.
End of Amendment 2