USDA/NPGQC
Maintenance Shop & Industrial Facility
Rev DC – Amendment 1Issued for Bid
07272 - 1 Fluid-Applied Membrane Air Barriers
SECTION 07272
FLUID-APPLIED MEMBRANE AIR BARRIERS
PART 1 GENERAL
1.1 SUMMARY
A. Section includes fluid-applied, vapor-permeable membrane air barriers.
1.2 DEFINITIONS
A. Air-Barrier Material: A primary element that provides a continuous barrier to the movement of air.
B. Air-Barrier Accessory: A transitional component of the air barrier that provides continuity.
C. Air-Barrier Assembly: The collection of air-barrier materials and accessory materials applied to an opaque wall, including joints and junctions to abutting construction, to control air movement through the wall.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1. Review air-barrier requirements and installation, special details, mockups, air-leakage and bond testing, air-barrier protection, and work scheduling that covers air barriers.
2. Conference shall be a minimum 30 days prior to field work of this Section.
1.4 SUBMITTALS
A. Section 01330 – Submittal Procedures.
B. Product Data: For each type of product.
1. Include manufacturer's written instructions for evaluating, preparing, and treating substrate; technical data; and tested physical and performance properties of products.
C. Shop Drawings: For air-barrier assemblies.
1. Show locations and extent of air barrier. Include details for substrate joints and cracks, counterflashing strips, penetrations, inside and outside corners, terminations, and tie-ins with adjoining construction.
2. Include details of interfaces with other materials that form part of air barrier.
07272 - 2 Fluid-Applied Membrane Air Barriers
D. Qualification Data: For Installer. Include list of ABAA-certified installers and supervisors employed by the Installer, who work on Project.
E. Product Certificates: From air-barrier manufacturer, certifying compatibility of air barriers and accessory materials with Project materials that connect to or that come in contact with the barrier.
F. Product Test Reports: For each air-barrier assembly, for tests performed by a qualified testing agency.
1.5 QUALITY ASSURANCE
A. Manufacturer’s Qualifications: Company specializing in producing air barrier products as specified with minimum ten years experience.
B. Comply with requirements in Section 01351, Sustainable Project Requirements.
C. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer.
1. Installer shall be licensed by ABAA according to ABAA's Quality
Assurance Program and shall employ ABAA-certified installers and supervisors on Project.
D. Mockups: Build mockups to set quality standards for materials and execution and for preconstruction testing.
1. Build integrated mockups of exterior wall assembly as specified in Section
04810, Unit Masonry Assemblies, incorporating backup wall construction, external cladding, window, storefront, door frame and sill, insulation, ties and other penetrations, and flashing to demonstrate surface preparation, crack and joint treatment, application of air barriers, and sealing of gaps, terminations, and penetrations of air-barrier assembly.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Remove and replace liquid materials that cannot be applied within their stated shelf life.
B. Protect stored materials from direct sunlight.
1.7 FIELD CONDITIONS
A. Environmental Limitations: Apply air barrier within the range of ambient and substrate temperatures recommended by air-barrier manufacturer.
1. Protect substrates from environmental conditions that affect air-barrier performance.
2. Do not apply air barrier to a damp or wet substrate or during snow, rain, fog, or mist.
07272 - 3 Fluid-Applied Membrane Air Barriers
1.8 WARRANTY
A. Material Warranty: Manufacturer's standard form in which manufacturer agrees to replace fluid-applied air barrier membrane materials that fail within specified warranty period when installed and used in strict conformance with written manufacturer's instructions.
1. Failures include, but are not limited to, the following:
a. Failure to maintain air permeance rating not to exceed .004 cfm/sq.
ft (0.02 L/s/sq. m.) when tested per ASTM E2178, within specified warranty period.
b. Failure to maintain a vapor permeance rating greater than 10 perms when tested in accordance with ATM E96, Method B.
2. Warranty Period: Twenty years from date of Substantial Completion.
PART 2 PRODUCTS
2.1 MATERIALS, GENERAL
A. Source Limitations: Obtain primary air-barrier materials and air-barrier accessories from single source from single manufacturer.
B. VOC Content: 250 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24) and complying with VOC content limits of authorities having jurisdiction.
2.2 PERFORMANCE REQUIREMENTS
A. General: Air barrier shall be capable of performing as a continuous vapor-permeable air barrier and as a liquid-water drainage plane flashed to discharge to the exterior incidental condensation or water penetration. Air-barrier assemblies shall be capable of accommodating substrate movement and of sealing substrate expansion and control joints, construction material changes, penetrations, and transitions at perimeter conditions without deterioration and air leakage exceeding specified limits.
B. The building envelope shall be designed and constructed with a continuous air barrier to control air leakage into, or out of the conditioned space. An air barrier shall also be provided for interior partitions between conditioned space and space designed to maintain temperature or humidity levels which differ from those in the conditioned space by more than 50% of the difference between the conditioned space and design ambient conditions. The air barrier shall have the following characteristics:
1. It must be continuous, with all joints made airtight.
2. It shall have an air permeability not to exceed 0.004 cfm/sq. ft. under a pressure differential of 0.3 in. water. (1.57 psf.)
07272 - 4 Fluid-Applied Membrane Air Barriers
3. It shall be capable of withstanding positive and negative combined design wind, fan and stack pressures on the envelope without damage or displacement, and shall transfer the load to the structure. It shall not displace adjacent materials under full load.
4. The membrane shall be a durable finished membrane to provide the specified performance for the expected service life of the building.
5. The air barrier shall be joined in an airtight and flexible manner to the air barrier material of adjacent systems, allowing for the relative movement of systems due to thermal and moisture variations and creep. The Air Barrier shall be chemically compatible with and provide adhesion to the material of adjacent systems. Air barrier seal shall be made between the following, but not limited to:
a. Foundation and walls.
b. Walls and windows or doors.
c. Different wall systems.
d. Wall and roof.
e. Wall and roof over unconditioned space.
f. Walls, floor and roof across construction, control and expansion joints.
g. Walls, floors and roof to utility, pipe and duct penetrations.
6. All penetrations of the air barrier and paths of air infiltration/exfiltration shall be made airtight.
2.3 FLUID-APPLIED VAPOR-PERMEABLE AIR-BARRIER
A. Basis of Design Manufacturer: Subject to compliance with requirements, provide
Barritech VP as manufactured by Carlisle Coatings & Waterproofing Inc. or comparable product by one of the following:
1. Grace, W.R. & Co. – Conn.
2. Henry Company.
3. Rubber Polymer Corporation, Inc.
4. Tremco Incorporated, an RPM company.
4.5. BASF Master Builders
B. Fluid-Applied, Vapor-Permeable Air Barrier: Synthetic polymer membrane.
1. Physical and Performance Properties:
a. Air Permeance: Maximum 0.004 cfm/sq. ft. of surface area at
1.57-lbf/sq. ft. pressure difference; ASTM E 2178.
b. Vapor Permeance: Minimum 11.2 perms; ASTM E 96/E 96M.
c. Assembly Performance: Provide a continuous air barrier assembly that has an air leakage not to exceed 0.0008 cfm/sq. ft. of surface area under a pressure differential of 0.3 in. water (1.57 pounds per square foot) when tested in accordance with ASTM E 2357.
d. UV Exposure Limit: Not more than 180 calendar days; per ASTM
D412 and ASTM E96-Method B.
07272 - 5 Fluid-Applied Membrane Air Barriers
2.4 ACCESSORY MATERIALS
A. General: Accessory materials recommended by air-barrier manufacturer to produce a complete air-barrier assembly and compatible with primary air-barrier material. Accessories shall maintain same performance requirements as air barrier.
B. Primer: Liquid waterborne primer recommended for substrate by air-barrier material manufacturer.
C. Substrate-Patching Membrane: Manufacturer's standard trowel-grade substrate filler.
D. Sprayed Polyurethane Foam Sealant: One- or two-component, foamed-in-place, polyurethane foam sealant, 1.5- to 2.0-lb/cu. ft density; flame-spread index of 25 or less according to ASTM E 162; with primer and noncorrosive substrate cleaner recommended by foam sealant manufacturer.
E. Liquid Membrane for Details and Terminations: As recommended by membrane manufacturer.
F. Flexible Membrane Wall Flashing: 0.8 mm of self-adhesive rubberized asphalt integrally bonded to 0.2 mm of cross-laminated, high-density polyethylene film to provide a min. 1.0 mm thick membrane. Membrane shall be interleaved with disposable silicone-coated release paper until installed, and of type as recommended by membrane manufacturer.
G. Joint Reinforcing Strip: Air barrier manufacturer's approved tape.
H. Transition Membrane: 0.8 mm of self-adhesive rubberized asphalt integrally bonded to 0.2 mm of cross-laminated, high-density polyethylene film to provide a min. 1.0 mm thick membrane. Membrane shall be interleaved with disposable silicone-coated release paper until installed, and of type as recommended by membrane manufacturer.
I. Joint Sealant: As recommended by membrane manufacturer.
PART 3 EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.
1. Verify that substrates are sound and free of oil, grease, dirt, excess mortar, or other contaminants.
07272 - 6 Fluid-Applied Membrane Air Barriers
2. Verify that concrete has cured and aged for minimum time period recommended by air-barrier manufacturer.
3. Verify that concrete is visibly dry and free of moisture. Test for capillary moisture by plastic sheet method according to ASTM D 4263.
4. Verify that masonry joints are flush and completely filled with mortar.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 SURFACE PREPARATION
A. Refer to manufacturer’s literature for requirements for preparation of substrates.
Surfaces shall be sound and free of voids, spalled areas, loose aggregate and sharp protrusions. Remove contaminants such as grease, oil and wax from exposed surfaces. Remove dust, dirt, loose stone and debris. Use repair materials and methods that are acceptable to manufacturer of the fluid-applied air barrier system.
B. Masonry Substrates: Apply air and vapor barrier over concrete block and brick with smooth trowel-cut mortar joints, struck full and flush. Fill all voids and holes, particularly in the mortar joints, with a lean mortar mix, non-shrinking grout or parge coat.
C. Related Materials: Treat construction joints and install flashing as recommended by manufacturer
D. Clean, prepare, treat, and seal substrate according to manufacturer's written instructions. Provide clean, dust-free, and dry substrate for air-barrier application.
E. Mask off adjoining surfaces not covered by air barrier to prevent spillage and overspray affecting other construction.
F. Remove grease, oil, bitumen, form-release agents, paints, curing compounds, and other penetrating contaminants or film-forming coatings from concrete.
G. Remove fins, ridges, mortar, and other projections and fill honeycomb, aggregate pockets, holes, and other voids in concrete with substrate-patching membrane.
H. Remove excess mortar from masonry ties, shelf angles, and other obstructions.
I. At changes in substrate plane, apply sealant or termination mastic beads at sharp corners and edges to form a smooth transition from one plane to another.
J. Cover gaps in substrate plane and form a smooth transition from one substrate plane to another with stainless-steel sheet mechanically fastened to structural framing to provide continuous support for air barrier.
07272 - 7 Fluid-Applied Membrane Air Barriers
3.3 JOINT TREATMENT
A. Concrete and Masonry: Prepare, treat, rout, and fill joints and cracks in substrate according to ASTM C 1193 and air-barrier manufacturer's written instructions.
Remove dust and dirt from joints and cracks complying with ASTM D 4258 before coating surfaces.
1. Prime substrate and apply a single thickness of air-barrier manufacturer's recommended preparation coat extending a minimum of 3 inches along each side of joints and cracks. Apply a double thickness of fluid air-barrier material and embed a joint reinforcing strip in preparation coat.
3.4 TRANSITION MEMBRANE INSTALLATION
A. General: Install strips, transition strips, and accessory materials according to air-barrier manufacturer's written instructions to form a seal with adjacent construction and maintain a continuous air barrier.
1. Coordinate the installation of air barrier with installation of roofing membrane and base flashing to ensure continuity of air barrier with roofing membrane.
2. Install strip on roofing membrane or base flashing so that a minimum of 3 inches of coverage is achieved over each substrate.
3. Install all flashing only after application of air barrier.
B. Apply primer to substrates at required rate and allow it to dry. Limit priming to areas that will be covered by fluid air-barrier material on same day. Reprime areas exposed for more than 24 hours.
1. Prime glass-fiber-surfaced gypsum sheathing with number of prime coats needed to achieve required bond, with adequate drying time between coats.
C. Connect and seal exterior wall air-barrier material continuously to roofing-membrane air barrier, concrete below-grade structures, floor-to-floor construction, exterior glazing and window systems, glazed curtain-wall systems, storefront systems, exterior louvers, exterior door framing, and other construction used in exterior wall openings, using accessory materials.
D. At end of each working day, seal top edge of strips and transition strips to substrate with termination mastic.
E. Apply joint sealants forming part of air-barrier assembly within manufacturer's recommended application temperature ranges. Consult manufacturer when sealant cannot be applied within these temperature ranges.
F. Wall Openings: Prime concealed, perimeter frame surfaces of windows, curtain walls, storefronts, and doors. Apply transition strip so that a minimum of 3 inches
07272 - 8 Fluid-Applied Membrane Air Barriers of coverage is achieved over each substrate. Maintain 3 inches of full contact over firm bearing to perimeter frames with not less than 1 inch of full contact.
1. Transition Membrane: Roll firmly to enhance adhesion.
G. Fill gaps in perimeter frame surfaces of windows, curtain walls, storefronts, and doors, and miscellaneous penetrations of air-barrier material with foam sealant.
H. Repair punctures, voids, and deficient lapped seams in strips and transition strips.
Slit and flatten fishmouths and blisters. Patch with transition strips extending 6 inches beyond repaired areas in strip direction.
3.5 FLUID AIR-BARRIER MEMBRANE INSTALLATION
A. General: Apply fluid air-barrier material to form a continuous air barrier according to air-barrier manufacturer's written instructions. Apply fluid air-barrier material within manufacturer's recommended application temperature ranges.
B. Membrane Air Barriers: Apply a continuous unbroken air-barrier membrane to substrates according to the following thickness. Apply air-barrier membrane in full contact around protrusions such as masonry ties.
1. Vapor-Permeable Membrane Air Barrier: Total dry film thickness as recommended in writing by manufacturer to meet performance requirements, but not less than 90-mil wet film thickness, 45-mil wet film thickness, applied in one or more equal coats.
C. Do not cover air barrier until it has been inspected by COR.
D. Correct deficiencies in or remove air barrier that does not comply with requirements; repair substrates and reapply air-barrier components.
3.6 CLEANING AND PROTECTION
A. Protect air-barrier system from damage during application and remainder of construction period, according to manufacturer's written instructions.
1. Protect air barrier from exposure to UV light and harmful weather exposure as required by manufacturer. If exposed to these conditions for more than 150 days, remove and replace air barrier or install additional, full-thickness, air-barrier application after repairing and preparing the overexposed membrane according to air-barrier manufacturer's written instructions.
2. Protect air barrier from contact with incompatible materials and sealants not approved by air-barrier manufacturer.
B. Clean spills, stains, and soiling from construction that would be exposed in the completed work using cleaning agents and procedures recommended by manufacturer of affected construction.
07272 - 9 Fluid-Applied Membrane Air Barriers
I:\Projects\3018427\3018427_0001\50_Deliverables & Submittals\Record of all submittals to client - PDF\2017.08.29_Amendment
1\07272.docxI:\Projects\3018427\3018427_0001\70_Specifications\2016.10 Specifications for Edit 100% Resubmission_12-2-
2016\07272.docx
C. Remove masking materials after installation.
END OF SECTION