Electrical_100CD_4.27.12.pdf
PDF 12 MB Posted
- Solicitation number
- AG-56A1-S-12-0002
About this file
Electrical Drawings 19 pages
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WalkerAmdmnt004.PDF | ||
| Amendment003.doc | DOC document | |
| 0013_001 | — | |
| 5.30.12Attendees.pdf | ||
| Walkeramdmnt002attachments.PDF | ||
| walkeramdmnt002.PDF | ||
| Walkeramdmnt001.PDF | ||
| SECTION J.docx | DOCX document | |
| SF 25APaymentBond.pdf | ||
| Responsibility Questionnaire.doc | DOC document | |
| Fire Protection_100CD_4.27.12.pdf | ||
| V1_Specifications_100CD_5.06a.12.pdf | ||
| SF 25PerformanceBond.pdf | ||
| V2_Specifications_100CD_4.27.12.pdf | ||
| SF 24BidBond.pdf | ||
| Final_Walker2012.pdf | ||
| General_100CD_4.27.12.pdf | ||
| Structural_100CD_5.6.12.pdf | ||
| Architectural_100CD_4.27.12.pdf | ||
| Technology_100CD_4.27.12.pdf | ||
| Plumbing_100CD_4.27.12.pdf | ||
| MN Wage Rate 5.4.12.docx | DOCX document | |
| CIVIL_100CD_4.27.12.pdf | ||
| Landscape_100CD_4.27.12.pdf | ||
| Mechanical_100CD_4.27.12.pdf |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELECTRICAL COVER SHEET
Plotter Scale
Date
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex
Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
E000
MARWIT
CHRFRA
NO SCALE
Date
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
0 30'15' 60' 90'45'
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
ELECTRICAL SITE PLAN
E001
SCOHOL
CLASEI
1" = 30' - 0"
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #1 - Admin Building & Heated Garage
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
FIRST FLOOR LIGHTING PLAN
R T H
N O
1 SCALE: 1/8" = 1'-0"
FIRST FLOOR LIGHTING PLAN
EL111
SCOHOL
CLASEI
1/8" = 1'-0"
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #1 - Admin Building & Heated Garage
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
FIRST FLOOR POWER PLAN
R T H
N O
1 SCALE: 1/8" = 1'-0"
FIRST FLOOR POWER PLAN
EP111
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #1 - Admin Building & Heated Garage
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
FIRST FLOOR SYSTEMS PLAN
R T H
N O
1 SCALE: 1/8" = 1'-0"
FIRST FLOOR SYSTEMS PLAN
ES111
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #1 - Admin Building & Heated Garage
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
SECOND FLOOR LIGHTING PLAN
R T H
N O
1 SCALE: 1/8" = 1'-0"
SECOND FLOOR LIGHTING PLAN
EL112
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #1 - Admin Building & Heated Garage
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
SECOND FLOOR POWER PLAN
R T H
N O
1 SCALE: 1/8" = 1'-0"
SECOND FLOOR POWER PLAN
EP112
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #1 - Admin Building & Heated Garage
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
SECOND FLOOR SYSTEMS PLAN
R T H
N O
1 SCALE: 1/8" = 1'-0"
SECOND FLOOR SYSTEMS PLAN
ES112
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #1 - Admin Building & Heated Garage
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
ROOF ELECTRICAL PLAN
R T H
N O
1 SCALE: 1/8" = 1'-0"
ROOF ELECTRICAL PLAN
E113
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #2 - Vehicle Garage (Non-Heated)
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
FIRST FLOOR LIGHTING PLAN
R T
HN
O
1 SCALE: 1/8" = 1'-0"
FIRST FLOOR LIGHTING PLAN
EL121
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #2 - Vehicle Garage (Non-Heated)
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
FIRST FLOOR POWER PLAN
R T
HN
O
1 SCALE: 1/8" = 1'-0"
FIRST FLOOR POWER PLAN
EP121
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #5 - Crew Quarters
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
FIRST FLOOR LIGHTING DEMOLITION PLAN
SCALE: 1/8" = 1'-0"
R T
HN
O
FIRST FLOOR LIGHTING PLAN
SCALE: 1/8" = 1'-0"
R T
HN
O
FIRST FLOOR LIGHTING PLAN
EL151
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #5 - Crew Quarters
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
FIRST FLOOR POWER DEMOLITION PLAN
SCALE: 1/8" = 1'-0"
R T
HN
O
1 FIRST FLOOR POWER PLAN
SCALE: 1/8" = 1'-0"
R T H
N O
FIRST FLOOR POWER PLAN
EP151
SCOHOL
CLASEI
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
0 8'4' 16' 24'2' 12'
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
SITE KEY PLAN
N.T.S.
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
Building #5 - Crew Quarters
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
FIRST FLOOR SYSTEMS DEMOLITION PLAN
SCALE: 1/8" = 1'-0"
R T H
N O
FIRST FLOOR SYSTEMS PLAN
SCALE: 1/8" = 1'-0"
R T H
N O
FIRST FLOOR SYSTEMS PLAN
ES151
SCOHOL
CLASEI
ELECTRICAL ONE-LINE
DIAGRAMS
Plotter Scale
Date
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex
Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
E400
SCOHOL
CLASEI
ELECTRICAL DETAILS
Date
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex
Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
E500
SCOHOL
CLASEI
ELECTRICAL DETAILS
Date
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex
Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
E501
SCOHOL
CLASEI
ELECTRICAL SCHEDULES
Date
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex
Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
E600
SCOHOL
CLASEI
ELECTRICAL SCHEDULES
Date
CAD Archive No.
Checked
Drawn
Drawing Sheet No.
Project Name
Drawing Title
Sheet of
CBE Project No.
10-0014
Walker District Administrative Complex
Chippewa National Forest Walker Ranger District
REGION NINE
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
04/27/2012
Drawing Scale
No. Date
DRAWING NOTES
Revision/Issue
Building Name & Number
A
B
C
D
E
1 2 3 4 5 6 7
1 2 3 4 5 6 7
A
B
C
D
E
REVISION 1 00/00/00
REVISION 2 00/00/00
REVISION 3 00/00/00
***NOTE***
SEE 'BID SCHEDULE' ON SHEET G101 FOR
DESCRIPTIVE NARRATIVES FOR ALL BASE BID &
OPTIONAL BID ITEMS TO BE PROVIDED WITHIN THE
SCOPE OF THIS PROJECT WORK.
E601
SCOHOL
CLASEI
| E000.dwg |
| E000 |