Table 2 - Description of Work
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 2 - Hardin Ridge
Length (Feet) Width
(inches) Sq Ft. Work Status
28 32 75 Base
31 30 78 Base
28 32 75 Base
28 32 75 Base
28 32 75 Base
27 30 68 Base
16 30 39 Base
19 40 63 Base
HRRA Paving Contract
Table 2 - Description of Work
ORB-3027
Holland
Total
HRRA Paving Contract ORB-3027 - Tier 1 - Additional Paving needs
Location Remove 3" depth of existing fill material and patch over designated culverts with 3" compacted depth of
#9 HMA Binder.
Bluegill Site 126
Bluegill Site 127
Bluegill Site 128
Southern Point Site 25
Southern Point Site 26
Southern Point Site 27
White Oak
HRRA Paving Contract
Table 2
HRRA Paving Contract ORB-3027 - Pine Camping Loop
Spur # Width
(Feet) Length (Feet) Sq Ft.
Tree to remove Work Status
187 20 48 960 1 Base
188 20 48 960 3 Base
189 20 53 1060 7 Base
190 20 43 860 5 Base
153 20 48 960 3 Base
172 20 55 1100 0 Base
164 20 50 1000 1 Base
165 20 58 1160 Base
Bath house 1 27 90 2430 Base
Bath house 2 20 45 900 Base
Totals 11390 20
Remove existing asphalt, excavate, and shape to meet required dimensions. Place 6" depth of #53 aggregate and place 3' depth of #9 asphalt binder. Paint parking lines and walkway (optional item).
Construct parking area as staked on the ground by the FS. Place 6" depth of #53 aggregate and place 3" depth of #9 asphalt binder. Paint parking lines (optional item).
Add material to gain width
Remove pipe across jct. Const ditch between lift station and spur.
Camping spur work shall consist of excavating spur to a depth of 8" to length and width shown. Backfill excavated area with 6" of compacted #53 aggregate. Pave spur with a 3" depth of #9 HMA. Place #73 aggregate along edge of asphalt sloping to drain.
Remove identified trees along with stump(s). Backfill and compact stump hole(s) with excavated spur material.
Raise grade at back of spur as staked
HRRA Paving Contract ORB-3027 - Bluegill Camping Loop
Spur # Width
(Feet) Length (Feet) Sq Ft.
Tree to remove Work Status
131 20 36 720 1 Base
87 20 50 1000 2 Base
88 20 43 860 Base
20 42 840 Base
20 47 940 1 Base
20 60 1200 5 Base
20 70 1400 Base
90 20 50 1000 1 Base
Totals 7960 10
Install 15" pipe across junction
Numerous small trees to be removed
Camping spur work shall consist of excavating spur to a depth of 8" to length and width shown. Backfill excavated area with 6" of compacted #53 aggregate. Pave spur with a 3" depth of #9 HMA. Place #73 aggregate along edge of asphalt sloping to drain.
Remove identified trees along with stump(s). Backfill and compact stump hole(s) with excavated spur material.
Raise grade at back of spur as staked
HRRA Paving Contract ORB-3027 - Southern Point Camping Loop
Spur # Width
(Feet) Length (Feet) Sq Ft.
Tree to remove Work Status
59 20 47 940 2 Base
44 20 42 840 Base
43 20 43 860 Base
20 37 740 Base
20 40 800 1 Base
Totals 4180 3
Reconstruct ditch left side of spur
Camping spur work shall consist of excavating spur to a depth of 8" to length and width shown. Backfill excavated area with 6" of compacted #53 aggregate. Pave spur with a 3" depth of #9 HMA. Place #73 aggregate along edge of asphalt sloping to drain.
Remove identified trees along with stump(s). Backfill and compact stump hole(s) with excavated spur material.
Need to excavate spur as staked to meet grade.
Raise grade as staked
Raise grade as staked